Permit: DP20-0226
Permit Details
Apply Date:
10/30/2020
Applicant:
Jean Armstrong
Description:
Site/Grading/SWPPP - Tucson Medical Center, Rincon ASC, new medical office.
Permit Reviews
Permit Number - DP20-0226
Permit Status: Complete
Permit Description: Site/Grading/SWPPP - Tucson Medical Center, Rincon ASC, new medical office.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/01/2021 | DEV PKG - RESUBMITTAL | 03/15/2021 | COMPLETED |
03/15/2021 | DEV PKG - RESUBMITTAL | 03/19/2021 | COMPLETED |
10/30/2020 | DEV PKG - OK TO SUBMIT | 11/04/2020 | COMPLETED |
11/04/2020 | DEV PKG | 01/18/2021 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP20-0226
Permit Description: Site/Grading/SWPPP - Tucson Medical Center, Rincon ASC, new medical office.
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/02/2022 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
08/02/2022 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 05/11/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN STILL NEED TO FINISH THE PLANTING.} | |
08/02/2022 | ENGR Engineering Final | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 04/29/2022; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by VVERA1 - IS NOT READY AT THIS TIME, LANDSCAPE CREWS WORKING ON IRRIGATION LINE INSTALLATIONS. THE FOLLOWING AREAS WERE NOTED AS NEEDING ATTENTION: 1) ADVISED THE CONTRACTOR THAT THE ADA PARKING SPACES AND ACCESS AISLES WERE NON-COMPLIANT FOR GRADES, AREAS EXCEEDING 2% WITHIN THE DESIGNATED SPACES. 2) THE SIDEWALK RAMPS LOCATED ALONG THE SOUTH SIDE OF THE BUILDING EXCEED 5% IN THE RUNNING SLOPE AND WILL REQUIRE HANDRAILS ON BOTH SIDES OF THE AFFECTED SIDEWALKS/RAMPS(3). 3) ALL CRACKS IN THE SIDEWALKS FOR THIS SITE WILL BE CHECKED TO ENSURE THST THEY HAVE BEEN REPLACED AS REQUIRED. I HAVE ADVISED THE CONTRACTOR THAT EVERY CRACK WILL BE CHECKED FOR MOVEMENT. ALSO ANY PANEL WITH MORE THAN ONE CRACK IN IT WILL NEED TO BE REMOVED AND REPLACED. 4) ADJACENT TO THE TRASH ENCLOSURE THE CONTRACTOR ADDED AN ADDITIONAL WATER HARVESTING BASIN. I HAVE ASKED FO THIS TO BE PUT ON THE APPROVED PLANS AS A REVISION PRIOR TO CLOSING THIS PROJECT OUT. THIS SITE WILL BE RE-INSPECTED PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF OCCUPANCY.} ; {Activity date: 04/07/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN CONTRACTOR NOT ON SITE NEED TO RESCHEDULE.} | |
08/02/2022 | SITE - Stormwater Follow-up | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 03/10/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN/ NO CONCERNS AS OF TODAY} ; {Activity date: 02/15/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN/ GOOD} ; {Activity date: 01/28/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by VVERA1 - IS CONTINUED, NO CONCERNS AT THIS TIME. ROADWAYS AND PARKING AROUND THE NEW BUILDING HAS NOT BEEN CONSTRUCTED AT THIS TIME } ; {Activity date: 01/19/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN /GOOD AT IS TIME NO CHANGE.} ; {Activity date: 01/04/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN /EVERYTHING LOOKS GOOD AT IS TIME.} ; {Activity date: 12/08/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN/GOOD AT IS TIME} ; {Activity date: 12/02/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN GOOD AT IS TIME.} ; {Activity date: 11/10/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN GOOD AS OF TODAY.} ; {Activity date: 10/14/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN / GOOD AT IS TIME} ; {Activity date: 09/28/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN /GOOD AT IS TIME /INFORMED THE CONTRACTOR TO CAAL IN FOR INSPECTION EVERY TWO WEEKS. } ; {Activity date: 07/02/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by RSALDAT1 - CONTINUED, NO CONCERNS AT THIS TIME } ; {Activity date: 06/18/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME} ; {Activity date: 06/10/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - } ; {Activity date: 05/28/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by VLEON1 - CN FOR 10360 E DREXEL RD - NO CONCERNS AT THIS TIME, STORMWATER CONTROLS APPEAR TO BE WORKING AS NEEDED. REMEMBER TO MONITOR ALL OPEN SITES AT ALL TIMES TO ENSURE THAT BLOWING DUST IS KEPT TO A BARE MINIMUM, BLOWING DUST IS A CITABLE OFFENSE OFFENSE BY THE ARIZONA DEPARTMENT OF ENVIRONMENTAL QUALITY AND MAY ALSO CAUSE A SHUTDOWN OF A SITE.} ; {Activity date: 05/17/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - CN . NEED SOME WATTLES IN THE SOUTHEAST CORNER. OF PROJECT. } ; {Activity date: 05/07/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by VLEON1 - CONTINUED, NO CONCERNS AT THIS TIME} |
|
08/02/2022 | ENGR Grading Final | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
08/02/2022 | SITE - Stormwater Final Inspection | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
08/02/2022 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 01/11/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN/ EVERYTHING IS GOOD TODAY NO CONCERNS TODAY.} | |
08/02/2022 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 05/06/2021; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by VLEON1 - PARTIAL A THIS TIME. TMC WANTS TO HAVE A GROUNDBREAKING CEREMONY ON TUESDAY EVENING THIS WEEK. I HAVE ADVISED THE CONTRACTOR THAT THE CLEARING OF THIS PORTION OF THE SITE NEEDS TO BE MONITORED BY THE LANDSCAPE ARCHITECT FOR ALL REMOVALS. I HAVE VIEWED THE PLANS FOR THIS SITE AND THE NPPO IS VERY QUESTIONABLE AT THIS TIME. THE PLANS HAVE SHOWN THE SAVING OF 4 SAGUAROS BUT HAS NO CALL OUT LIST OF ANY OTHER PLANTS. THE LANDSCAPE PLANS FOR THIS SITE SHOWS NOT ONLY THE SAGUAROS ARE TO BE SAVED, BUT ALSO TREES AND BARREL CACTUS.} | |
08/02/2022 | COT - ENGR - Signage Final | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 04/07/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN NEED TO RESCHEDULE} |