Permit: DP20-0209
Permit Details
Apply Date:
10/14/2020
Applicant:
Steven Shell
Description:
SITE - Broadway and Campbell Restaurant. Broadway Improvements Remediation.
Permit Reviews
Permit Number - DP20-0209
Permit Status: Complete
Permit Description: SITE - Broadway and Campbell Restaurant. Broadway Improvements Remediation.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/14/2020 | DEV PKG - OK TO SUBMIT | 10/21/2020 | COMPLETED |
10/21/2020 | DEV PKG | 12/21/2020 | COMPLETED |
12/22/2020 | DEV PKG - RESUBMITTAL | 12/28/2020 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP20-0209
Permit Description: SITE - Broadway and Campbell Restaurant. Broadway Improvements Remediation.
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/10/2021 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 02/10/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by VLEON1 - Approved. Mike with Epstein at 891-1158. Campbell and Broadway Starbucks site. Steve shell. Water harvesting specified. No underground storm drain piping. One trash enclosure, please call for inspection when ready to start. Track out protection and other stormwater protections. Estimated two month project.} ; {Activity date: 02/09/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VLEON1 - Partially approved. Courtesy unscheduled inspection,Mike with Epstein construction. 891-1158. Steve shell architect. Starbucks site to break ground this week. Demolition, temporary fence installation. Please schedule inspections from development package permit. } |
|
04/22/2021 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 04/22/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by VLEON1 - } ; {Activity date: 02/10/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VLEON1 - PARTIAL APPROVAL} ; {Activity date: 02/09/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VLEON1 - PARTIAL APPROVAL, MIKE WITH ESTEIN TEMPORARY FENCING IN PREPARATION FOR DEMO} | |
05/20/2021 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 05/20/2021; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - } ; {Activity date: 05/19/2021; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 02/09/2021; Status: Not Applicable; Inspector: BBENEDON; Comment: Entered by VLEON1 - NOT APPLICABLE} | |
05/20/2021 | SITE - Stormwater Follow-up | Passed | {Activity date: 05/20/2021; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - } ; {Activity date: 05/19/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - } ; {Activity date: 03/18/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE NO ISSUES} | |
05/20/2021 | SITE - Stormwater Final Inspection | Passed | {Activity date: 05/20/2021; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - } | |
05/20/2021 | COT - ENGR - Signage Final | Passed | {Activity date: 05/20/2021; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - } | |
06/28/2021 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 06/28/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by VLEON1 - } ; {Activity date: 06/24/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VLEON1 - } ; {Activity date: 06/24/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VLEON1 - Partially approved. Plants and trees} ; {Activity date: 06/18/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VLEON1 - PARTIAL APPOVAL TREES INSTALLED} ; {Activity date: 06/03/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - Not ready. No landscaping has been installed at this time } ; {Activity date: 05/19/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - Not ready. Remove construction debris’s prior to start of landscape materials.} |
|
07/30/2021 | ENGR Engineering Final | Passed | {Activity date: 07/30/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 05/20/2021; Status: Partial Approval; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - } | |
07/30/2021 | ENGR Grading Final | Passed | {Activity date: 07/30/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 05/26/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - Continued. Rough grading completed. TI contractor on site} ; {Activity date: 01/07/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by VLEON1 - GRADING-CHECK FOR ACTIVITY IS CONTINUED AT THIS TIME. THE EXISTING SITE HAS BEEN CLOSED DUE TO THE NEW CONSTRUCTION ON BROADWAY. NO WORK HAS BEEN DONE TO THIS SITE AT THIS TIME.} |