Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address:
727 E EVANS BL
Address NEW:
727 E EVANS BL
Apply Date:
10/17/2019
Applicant:
Araceli Juarez
Description:
SITE/GRADING - Airgas Parking Lot expansion.

Permit Reviews

Permit Number - DP19-0255
Permit Status: Complete
Permit Description: SITE/GRADING - Airgas Parking Lot expansion.
Start Date Submittal Complete Date Status  
09/18/2019 DEV PKG - OK TO SUBMIT 10/22/2019 COMPLETED Review Details
10/22/2019 DEV PKG 11/12/2019 COMPLETED Review Details
11/15/2019 DEV PKG - RESUBMITTAL 12/04/2019 COMPLETED Review Details
12/10/2019 DEV PKG - RESUBMITTAL 12/10/2019 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP19-0255
Permit Description: SITE/GRADING - Airgas Parking Lot expansion.
Total Completed Inspections - 9
Date Description Inspector Results Comments
01/16/2020 PDSD Site/Engineering Division - NPPO Passed {Activity date: 01/16/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
01/16/2020 SITE - Stormwater Follow-up Passed {Activity date: 01/16/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
01/16/2020 SITE - Stormwater Final Inspection Passed {Activity date: 01/16/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
01/16/2020 SITE - Stormwater Setup and Controls Passed {Activity date: 01/16/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
01/16/2020 COT - ENGR - Signage Final Passed {Activity date: 01/16/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
01/21/2020 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 01/21/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
01/21/2020 ENGR Engineering Final Passed {Activity date: 01/21/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 01/16/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Complete the requirements stated in the locks holds and notices
Correct the installation of the accessible parking sign and correct the broken asphalt within the accessible path.
Work within the right of way requires permits and inspections.}
01/21/2020 ENGR Grading Final Passed {Activity date: 01/21/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
01/21/2020 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 01/21/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }

Documents

File Name Document Type  
PERMIT.PDF DOCUMENTS VIEW
COT LOI.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
DRAINAGE STATEMENT.PDF DOCUMENTS VIEW
NPPO APPLICATION FOR EXCEPTION_10_16_19_ DJC.PDF DOCUMENTS VIEW
COMMENT RESPONSE LTR, 11.15.19.PDF DOCUMENTS VIEW
SIGNEDLOTCOMBO, PIMACO ASSESSOR.PDF DOCUMENTS VIEW
COMMENT LETTER 12.3.19.PDF DOCUMENTS VIEW
COMMENT RESPONSE LETTER, 12.10.19.PDF DOCUMENTS VIEW
1-5 OF 5.PDF DEVELOPMENT PACKAGE VIEW