Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Development Package
Apply Date:
09/24/2019
Applicant:
Description:
TENTATIVE PLAT/GRADING/FLD - Sentinel Vista, Lots 1-11, CA "A" (priv road and parking), CA "B" (land

Permit Reviews

Permit Number - DP19-0226
Permit Status: Issued
Permit Description: TENTATIVE PLAT/GRADING/FLD - Sentinel Vista, Lots 1-11, CA "A" (priv road and parking), CA "B" (land
Start Date Submittal Complete Date Status  
01/11/2021 REVISION - - 1ST 01/11/2021 COMPLETED Review Details
01/15/2021 REVISION - - 1ST 04/07/2021 COMPLETED Review Details
01/21/2020 TENTATIVE PLAT REVIEW 03/02/2020 COMPLETED Review Details
03/20/2020 TENTATIVE PLAT REVIEW 04/21/2020 COMPLETED Review Details
05/19/2020 TENTATIVE PLAT REVIEW 06/10/2020 COMPLETED Review Details
06/17/2020 TENTATIVE PLAT REVIEW 07/13/2020 COMPLETED Review Details
08/23/2019 DEV PKG - OK TO SUBMIT 09/30/2019 COMPLETED Review Details
09/30/2019 TENTATIVE PLAT REVIEW 10/31/2019 COMPLETED Review Details
11/30/2020 DEV PKG - OK TO SUBMIT 01/11/2021 COMPLETED Review Details

Outstanding Inspections

Permit Status: Issued
Permit Number: DP19-0226
Permite Description: TENTATIVE PLAT/GRADING/FLD - Sentinel Vista, Lots 1-11, CA "A" (priv road and parking), CA "B" (land
Total Outstanding Inspections - 9
Last Inspection Date Description Inspector Results Comments
05/11/2022 SITE - Stormwater Setup and Controls N/A Complete (Recurring) {Activity date: 05/11/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. Provide Concrete containment as needed} ; {Activity date: 10/27/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Controls in place.} ; {Activity date: 07/14/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. New Stormwater controls are necessary at basin overflow during construction.} ; {Activity date: 12/18/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. No controls installed.} ; {Activity date: 11/12/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Partially approved. Track out protection installed}
10/19/2022 SITE - Stormwater Follow-up N/A Complete (Recurring) {Activity date: 10/19/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. Trash accumulation offsite along north and east perimeter.} ; {Activity date: 09/29/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. No issues after last rain event} ; {Activity date: 09/14/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. No track out issues at this time. Construction Ongoing

} ; {Activity date: 08/03/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. All materials are contained within site.} ; {Activity date: 06/29/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continue. No issues or concerns at this time.

} ; {Activity date: 06/15/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - continues} ; {Activity date: 06/07/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. All materials contained within the site.

} ; {Activity date: 04/28/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. All materials contained within site boundaries} ; {Activity date: 04/01/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued no issues or concerns at this time

} ; {Activity date: 03/03/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. No issues at this time

} ; {Activity date: 02/02/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued} ; {Activity date: 01/21/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued} ; {Activity date: 01/11/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. No activity on site

} ; {Activity date: 12/10/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. No issues after last nights rain event} ; {Activity date: 12/01/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued} ; {Activity date: 10/27/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. No issues at this time. Building construction in progress} ; {Activity date: 10/07/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - . Continued.} ; {Activity date: 10/07/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - . Continued.} ; {Activity date: 09/30/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. No offsite discharge noted with a conclusion of this year’s monsoon

} ; {Activity date: 08/19/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. No issues or concerns at this time after last rain event} ; {Activity date: 07/14/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Erosion control is needed at basin overflow overflow} ; {Activity date: 05/06/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE NO ISSUSES OR CONCERNS AT THIS TIME} ; {Activity date: 04/21/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE MINOR TRACK OUT NOTED NO ISSUE OR CONCERNS AT THIS TIME} ; {Activity date: 04/16/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - Continue. Minor noted at this time. Grading in progress} ; {Activity date: 03/26/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE NO ISSUES AT THIS TIME} ; {Activity date: 02/10/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE - NO ISSUES OR CONCERNS AT THIS TIME} ; {Activity date: 01/27/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE - NO ISSUES AFTER LAST RAIN EVENT} ; {Activity date: 01/20/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. No issues at this time. Very little activity on site} ; {Activity date: 01/06/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - } ; {Activity date: 12/17/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. No issues or concerns at this time.} ; {Activity date: 12/02/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by PAHUMAD1 - Continued. Minor track out noted.} ; {Activity date: 11/24/2020; Status: Continued; Inspector: BBENENDON; Comment: Entered by PAHUMAD1 - } ; {Activity date: 11/12/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Continued. Minor track out noted at two entrances}
10/27/2022 COT - ENGR - Signage Final N/A Not Ready
10/26/2022 PDSD Site/Engineering Division - NPPO N/A Not Ready
10/27/2022 ENGR Engineering Final N/A Not Ready
09/08/2023 PDSD Engineering Division Pre-Construction SITE N/A Partial Pass
03/21/2024 SITE - Stormwater Final Inspection N/A Not Applicable It’s a new decade, let’s move forward.
11/28/2023 PDSD Site/Engineering Division - Landscaping N/A Not Ready
11/28/2023 ENGR Grading Final N/A Partial Pass grading for upper

Completed Inspections

Permit Status: Issued
Permit Number: DP19-0226
Permit Description: TENTATIVE PLAT/GRADING/FLD - Sentinel Vista, Lots 1-11, CA "A" (priv road and parking), CA "B" (land
Total Completed Inspections - 1
Date Description Inspector Results Comments
06/25/2024 ENGR Grading Final Passed This is a duplicate inspection approved for clarity

Documents

File Name Document Type  
1-13 OF 13.PDF DOCUMENTS VIEW
COMMENT RESPONSE LETTER, 01.13.21.PDF DOCUMENTS VIEW
ONLINE FILEDROP PAGE, 01.13.21, 10;45AM.PDF DOCUMENTS VIEW
REVISION LETTER, 11.25.20.PDF DOCUMENTS VIEW
PREMIER BUILDING, CONTRACTOR LETTER, 11.04.20.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
1-13 OF 13.PDF DEVELOPMENT PACKAGE VIEW
COMMENT RESPONSE LETTER, 06.17.2020.PDF DOCUMENTS VIEW
3RD SUBMITTAL COMMENT RESPONSE, 05.19.2020.PDF DOCUMENTS VIEW
ARCHITECTURAL VARIATION PLAN AND PRIVACY MITIGATION PLAN.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
DRAINAGE REPORT.PDF DOCUMENTS VIEW
DRAINAGE REPORT_ADDENDUM CALCULATIONS.PDF DOCUMENTS VIEW
FLD_MAILING CERTIFICATION AND ADDRESS LABELS.PDF DOCUMENTS VIEW
FLD_NEIGHBOR MEETING REQUEST.PDF DOCUMENTS VIEW
FLD_NEIGHBORHOOD MEETING MINUTES.PDF DOCUMENTS VIEW
FLD_SIGN IN SHEET.PDF DOCUMENTS VIEW
PREVIOUSLY APPROVED_S08-057 FINAL PLAT.PDF DOCUMENTS VIEW
NOTICE OF APPLICATION SUBMITTAL.PDF DOCUMENTS VIEW
COMMENT RESPONSE LETTER, 01.21.2020.PDF DOCUMENTS VIEW
HOME ELEVATION.PDF DOCUMENTS VIEW
LANDSCAPE COMMENT RESPONSE LETTER.PDF DOCUMENTS VIEW
WATER AVAILABILITY LETTER, CITY OF TUCSON.PDF DOCUMENTS VIEW
RETURNED MAILINGS.PDF DOCUMENTS VIEW
PIMACO ADDRESSING REVIEW, 02.18.2020.PDF DOCUMENTS VIEW
2ND SUBMITTAL COMMENT RESP, 03.20.2020.PDF DOCUMENTS VIEW
LANDSCAPE IN RW APPROVAL EMAIL.PDF DOCUMENTS VIEW