Permit Details

Status:
Issued
Type:
Development Package
Address:
10201 S SWAN RD
Address NEW:
10201 S SWAN RD
Apply Date:
03/21/2019
Applicant:
Description:
SITE/GRADING/SWPPP - Tucson Electric Power Sonoran Substation.

Permit Reviews

Permit Number - DP19-0070
Permit Status: Issued
Permit Description: SITE/GRADING/SWPPP - Tucson Electric Power Sonoran Substation.
Start Date Submittal Complete Date Status  
02/15/2019 DEV PKG - OK TO SUBMIT 03/25/2019 COMPLETED Review Details
03/25/2019 DEV PKG 05/01/2019 COMPLETED Review Details
06/21/2019 DEV PKG - RESUBMITTAL 07/17/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - DP19-0070
Permit Status: Issued
Permit Description: SITE/GRADING/SWPPP - Tucson Electric Power Sonoran Substation.
Total Outstanding Activity Conditions - 1
Date Name
07/19/2019 The salvage-only permit does not allow site grubbing, grading, or construction of any kind, other than the salvaging of those materials as indicated on the approved Native Plant Preservation Plan. No protected native plants, even if indicated on the approved Native Plant Preservation Plan for removal or destruction, may be destroyed or removed from the site until a grading permit has been issued for the project.On-Site MonitoringOn-site monitoring of all aspects of site clearing, grading, plant protection, preservation, salvage, and mitigation must be provided during project construction at the expense of the developer for all residential development that is over five acres and for all commercial and industrial development that is over one acre. The monitoring must be performed by an individual who is qualified in arid lands native plant resource identification and protection as specified in Section 7.7.4.D, Professional Expertise. The monitor must provide periodic progress reports to the developer outlining the status of work accomplished and any problems encountered. A copy of these reports must be submitted to the PDSD for the project file.

Completed Inspections

Permit Status: Issued
Permit Number: DP19-0070
Permit Description: SITE/GRADING/SWPPP - Tucson Electric Power Sonoran Substation.
Total Completed Inspections - 9
Date Description Inspector Results Comments
06/01/2020 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 06/01/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - }
06/01/2020 PDSD Site/Engineering Division - NPPO Passed {Activity date: 06/01/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - }
06/01/2020 ENGR Engineering Final Passed {Activity date: 06/01/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - }
06/01/2020 SITE - Stormwater Follow-up Passed {Activity date: 06/01/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - } ; {Activity date: 04/20/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - No concerns at this time some temporary controls and some permanent controls are installed at this time.} ; {Activity date: 03/12/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - No concerns at this time.} ; {Activity date: 02/10/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - No concerns at this time.} ; {Activity date: 01/09/2020; Status: Continued; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - NO CONCERNS AT THIS TIME CONTROLS ALL APPEAR TO BE WORKING} ; {Activity date: 11/20/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - No NOI Posted at gate. Waddle has been installed around site. Met with foreman for diversified about calling in for install of controls.}
06/01/2020 SITE - Stormwater Final Inspection Passed {Activity date: 06/01/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - }
06/01/2020 SITE - Stormwater Setup and Controls Passed {Activity date: 06/01/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - } ; {Activity date: 01/09/2020; Status: Continued; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - NO CONCERNS AT THIS TIME} ; {Activity date: 10/08/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Met with general contractor on site went over controls to Install. Install per approved plans. Provide Anoa’i and stormwater controls information at gate.}
06/01/2020 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 06/01/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - } ; {Activity date: 10/09/2019; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - THE PRE-CON MEETING WAS HELD YESTERDAY WITH RON LE DONNE AND REPRESENTATIVES OF DIVERSIFIED.} ; {Activity date: 10/03/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - no stormwater prevention plan noNOI On site. Talk to Brian about getting those and call back for another preconstruction meeting.}
06/01/2020 COT - ENGR - Signage Final Passed {Activity date: 06/01/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - }
10/31/2023 ENGR Grading Final Passed City Of Tucson water well pass

Documents

File Name Document Type  
PERMIT.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
GEOREPORT FINAL.PDF DOCUMENTS VIEW
TRANSMITTAL SHEET.PDF DOCUMENTS VIEW
DRAINAGE REPORT.PDF DOCUMENTS VIEW
ERR.PDF DOCUMENTS VIEW
SWPPP.PDF DOCUMENTS VIEW
COMMENT-RESPONSE LETTER 2019-07-08.PDF DOCUMENTS VIEW
SVO PERMIT_7-18-19.PDF DOCUMENTS VIEW
MONITORING REPORT_072919.PDF DOCUMENTS VIEW
MONITORING REPORT 8.12.19.PDF DOCUMENTS VIEW
1-20 OF 20.PDF DEVELOPMENT PACKAGE VIEW