Permit Number: DP19-0070
Parcel: 30370005A

Address:
10201 S SWAN RD

Review Status: Completed

Review Details: DEV PKG

Permit Number - DP19-0070
Review Name: DEV PKG
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/25/2019 SBEASLE1 START PLANS SUBMITTED Completed
03/26/2019 MASHFOR1 COT NON-DSD FIRE Approved Moving forward please identify fire hydrants (water source) on the plan set.
04/16/2019 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed
04/22/2019 ANDREW CONNOR LANDSCAPE REVIEW Reqs Change 7.7.5. PLANT PRESERVATION STANDARDS
Set Aside Methodology
Site Assessment
An Environmental Resource Report (ERR) in accordance with Sections 2-03.5.0, Environmental Resource Report, and 2-11.4.5, Set Aside Submittal, of the Administrative Manual must be prepared for the entire site to determine the general viability, density , and variety of Protected Native Plants within areas on the site . The ERR shall include an assessment of such areas of NUOS and shall prioritize the natural resource value of vegetated areas on the site in conformance with the intent and purpose of this section. Any area left undisturbed as provided in this Section must be shown in the ERR , and no other assessment need be done for such areas. The natural resource value for an area is assessed by the consideration of factors such as:
(1) Health, size, density, and variety of native plant species;
(2) The visual resource value of the area(s); and,
(3) The potential to maximize the preservation of contiguous areas of NUOS both on- and off-site.

The natural resource values for areas on the site and the area(s) to be set aside will be recorded in survivable manner as NUOS.

Submit an ERR in lieu of a Native Plant Inventory method.
04/24/2019 DAVID RIVERA ZONING REVIEW Reqs Change CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: David Rivera
PDSD Zoning Review Section

PROJECT: Sonoran Substation TEPC - Utilities Use Group / Power Substation
Development Package (1st Review) - 10201 S. Swan Road
DP19-0070 - RH Zoning - SE(2) Zoning Examiner Section 3.4.3

TRANSMITTAL DATE: April 24, 2019
DUE DATE: April 22, 2019

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is March 21, 2020.


2-06.3.12 - An index of sheets in the development package shall be provided on the first sheet.

1. COMMENT: Incorporate the civil and landscape sheets into one PDF file for the next submittal.


2-06.4.2.B - A brief legal description and a statement as to whether the project is a re-subdivision are to be provided. On re-subdivisions, provide the recording information of the existing subdivision plat;

2. COMMENT: For as more descriptive location, include in the brief legal description the SW ½ , SW 1/4.


2-06.4.3 - The administrative street address and relevant case numbers (development package document, subdivision, rezoning, board of adjustment, DDO, MDR, DSMR, overlay, etc.) shall be provided adjacent to the title block on each sheet.

3. COMMENT: Provide the development package case number, DP19-0070, adjacent to the title block on each sheet.


2-06.4.4.B - Identify major streets and regional watercourses within the square mile area and all streets that abut the subject property; and,

4. COMMENT: Label Wilmot Road on the location map.


2-06.4.7.A.6 - If a plan or plat is prepared in conjunction with other applications or overlays or the parcel being developed is subject to conditions of an application processed previously, additional information must be added to the plan. Such applications and overlays include, but are not limited to: annexations; rezonings; special exceptions; Board of Adjustment variances; Design Development Options; Technical Standard Modification Request; overlays (Airport Environs Zone, Environmental Resource Zone, Gateway Corridor Zone, Hillside Development Zone, Historic Preservation Zone, Major Streets and Routes, Rio Nuevo District, Scenic Corridor Zone, WASH); Modification of Development Regulations through the Downtown Area Infill Incentive District or Rio Nuevo District; Downtown Heritage Incentive Zone; or, Design Review Board. Provide the following information on the plan.

5. COMMENT: Reference the Annexation case number C15-14-05 in the lower right corner next to the title block of all plan sheets.

The proposed use requires approval through a Zoning Examiner Special Exception Procedure, Section 3.4.3. A SE case number will be assigned to this project once the application has been submitted and excepted. List as reference the SE case number in the lower right corner next to the title block. List as a general note the SE case number and any conditions of approval for the SE.

Include a General note on sheet 2 that states that this project has been designed to comply with the MS&R Setback regulations, UDC Section 5.4.

Include a General note on sheet 2 that states that this project has been designed to comply with the erz Overlay regulations, UDC Section 5.7. An ERR report may be required See Engineering and Landscape reviewer comments.

Include in general note 11 on sheet 2; a calculation for the MSL site elevation vs the SE end of runway elevation and list the tallest electrical or mechanic feature on the site with the elevation. (It is acknowledged that the tallest feature will probably not be affected.)


2-06.4.8 - Existing Site Conditions

2-06.4.8.B - All easements shall be drawn on the plan. The recordation information, location, width, and purpose of all easements on site will be stated. Blanket easements should be listed in the notes, together with recordation data and their proposed status. Should an easement not be in use and be proposed for vacation or have been abandoned, so indicate. However, should the easement be in conflict with any proposed building location, vacation of the easement shall occur prior to approval of plan unless written permission from easement holder(s) is provided.

6. COMMENT: If applicable provide the easement information as noted by the standard above.


2-06.4.9.D - Delineate proposed Natural Undisturbed Open Space (NUOS) in a surveyable manner.

7. COMMENT: As a general note list the SF area of the proposed NUOS noted on the DP.

If you have any questions about this transmittal, Contact David Rivera on Tuesday, or Wednesday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields any time during the week at (520) 837-4956 or email Steve.Shields@tucsonaz.gov

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
04/24/2019 DAVID RIVERA ZONING HC REVIEW Approved
04/30/2019 SBEASLE1 ZONING-DECISION LETTER REVIEW Reqs Change PLAN RETURNED FOR CORRECTIONS NOTICE
The reviews have been completed and a resubmittal is required.
Activity Number: DP19-0070
Project Description: SITE/GRADING/SWPPP - Tucson Electric Power Sonoran Substation.
To view review comments, visit PRO at www.tucsonaz.gov/PRO, then search by Activity Number. (If new comments aren't shown yet, check back later as data flows to PRO periodically throughout the day.)
After all corrections are made, name your 2nd submittal documents accordingly, for example: 2_Plan_Set.
Submit the following items to the PDSD Filedrop at https://www.tucsonaz.gov/file-upload-pdsd.
In the Project Description field, include the Activity Number.
1) Comment Response Letter (lists changes made to the Plan and to which reviewer comments you are responding)
2) Corrected Plan Set (all pages, full set)
3) Items requested by review staff
After resubmittal, the plans will re-enter the standard 20-working-day review cycle.
Prior to the completion of the next review, we require payment of the total fees (or the Review fees at a minimum). You can either pay in person at the permit counter or mail a check payable to the City of Tucson (address is below). Include the Activity Number on your check stub.
The fee balance is $6,889.68 (see the Balance column in the image below).
The Project Manager can be reached via email or phone: Andrew.Connor@TucsonAz.gov, (520) 837-4950.
Thank you.
Sharon Beasley

City of Tucson
Planning and Development Services
Attn: Permit Counter
201 N. Stone Avenue, First Floor
Tucson, AZ 85701
04/30/2019 JOHN VAN WINKLE ENGINEERING REVIEW Reqs Change DP19-0070

1) Show on plans and expand drainage report to show that the PAD elevation for the proposed substation is above the regulatory flood elevation for critical facilities. Reference City of Tucson City Code Chapter 26, definition of Critical Facility
2) Per Stormwater Detention/Retention Manual section 3.4.2 provide a grade control marker for the proposed detention/retention basin. On the plans please also provide the coordinates of the grade control marker so that it can be easily located in the future
3) Confirm basin draw down time will be less than 24 hours
4) Project is within the Lee Moore Study Area. Please review the Lee Moore Wash Basin Management Study and confirm project compliance. See following link https://onbase.pima.gov/publicaccess/FC/PublicAccessProvider.ashx?action=ViewDocument&overlay=Print&overrideFormat=PDF
5) Sheet 1. Add the SWPPP plan/project number under which this development will operate
6) Show on plans the radius of the proposed driveway connection to Swan Rd
7) Show on plans the location of any access gates. If there is an access gate off of Swan Rd, show that there is sufficient vehicular maneuvering area to preclude a vehicle from having to back out onto Swan Rd. For all access gates show that there is sufficient vehicle turn around area

John Van Winkle, P.E.
John.VanWinkle@tucsonaz.gov
520-837-5007

Final Status

Task End Date Reviewer's Name Type of Review Description
05/01/2019 SBEASLE1 OUT TO CUSTOMER Completed