Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP18-0248
Permit Details
Apply Date:
10/04/2018
Applicant:
Description:
SITE/GRADING - MCDONALD'S
Permit Reviews
Permit Number - DP18-0248
Permit Status: Complete
Permit Description: SITE/GRADING - MCDONALD'S
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/13/2019 | DEV PKG - REVISION | 06/12/2019 | COMPLETED |
10/04/2018 | DEV PKG - OK TO SUBMIT | 10/12/2018 | COMPLETED |
10/04/2018 | SITE and/or GRADING | 11/05/2018 | COMPLETED |
11/09/2018 | SITE and/or GRADING | 05/14/2019 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP18-0248
Permit Description: SITE/GRADING - MCDONALD'S
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/26/2019 | SITE - Stormwater Follow-up | Passed | {Activity date: 04/26/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - work is been completed there are no issues at this time.} | |
04/26/2019 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 04/26/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - The work has already been completed.} | |
05/06/2019 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 05/06/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 02/08/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by CBELL1 - If owner wants to remove the two palm trees on patio I am OK with that} | |
05/06/2019 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 05/06/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
05/06/2019 | ENGR Grading Final | Passed | {Activity date: 05/06/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
05/06/2019 | SITE - Stormwater Final Inspection | Passed | {Activity date: 05/06/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
05/06/2019 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 05/06/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PER STEVE SHIELDS.} ; {Activity date: 04/26/2019; Status: Denied; Inspector: BBENEDON; Comment: Entered by CBELL1 - It appears that there has been no previous inspections under this permit.} ; {Activity date: 01/15/2019; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by CBELL1 - changed to PA due to other inspections} | |
05/06/2019 | COT - ENGR - Signage Final | Passed | {Activity date: 05/06/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
06/17/2019 | ENGR Engineering Final | Passed | {Activity date: 06/17/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/03/2019; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by CBELL1 - } ; {Activity date: 04/26/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by CBELL1 - Complete the work shown on the plan including installing the handrail per CO T, PAG SD 105. Install curb stop in accessible spaces. Schedule inspection for both the DP and the combination permit at the same time.} |