Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP18-0247
Permit Details
Apply Date:
10/03/2018
Applicant:
Description:
E SITE/GRADE/SWPPP - ABRAZO MICRO HOSPITAL
Permit Reviews
Permit Number - DP18-0247
Permit Status: Complete
Permit Description: E SITE/GRADE/SWPPP - ABRAZO MICRO HOSPITAL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/07/2019 | DEV PKG - RESUBMITTAL | 03/01/2019 | COMPLETED |
10/03/2018 | DEV PKG - OK TO SUBMIT | 10/05/2018 | COMPLETED |
10/10/2018 | DEV PKG | 12/14/2018 | COMPLETED |
12/18/2018 | DEV PKG - RESUBMITTAL | 01/23/2019 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP18-0247
Permite Description: E SITE/GRADE/SWPPP - ABRAZO MICRO HOSPITAL
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/10/2020 | COT - FCON - Sprinkler - Final | N/A | Canceled | {Activity date: 01/10/2020; Status: Not Applicable; Inspector: jvincent; Comment: Entered by JVINCEN1 - } |
01/10/2020 | COT - FCON - Fire - Final | N/A | Canceled | {Activity date: 01/10/2020; Status: Not Applicable; Inspector: jvincent; Comment: Entered by JVINCEN1 - } |
Completed Inspections
Permit Status: Complete
Permit Number: DP18-0247
Permit Description: E SITE/GRADE/SWPPP - ABRAZO MICRO HOSPITAL
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/07/2019 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 06/07/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } | |
06/07/2019 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 06/07/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } | |
04/23/2020 | SITE - Stormwater Follow-up | Passed | {Activity date: 04/23/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - } ; {Activity date: 03/25/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - No concerns at this time} ; {Activity date: 03/25/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - No concerns at this time} ; {Activity date: 03/11/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - Met with GC about adding temporary controls to curb openings} ; {Activity date: 03/11/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - Continue. Met with GC about adding temporary controls to curb openings} ; {Activity date: 02/19/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Walk site with GC went over a couple of small items to repair and controlled.} ; {Activity date: 01/29/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Walks site with GC went over some corrections on east end of sight. Provide designated concrete washout on site.} ; {Activity date: 12/31/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Met with GC about adding rock to entrance.} ; {Activity date: 12/18/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Walks site with GC no concerns at this time.} ; {Activity date: 12/04/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - . Walk site with GC talked about Repairing controls on south west corner of sight. And adding track out rock to entrance.} ; {Activity date: 12/04/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - Walk site with GC talked about Repairing controls on south west corner of sight. And adding track out rock to entrance.} ; {Activity date: 11/20/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - No concerns at this time.} ; {Activity date: 11/06/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - No concerns at this time.} ; {Activity date: 10/23/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Walk site with general contractor no concerns at this time.} ; {Activity date: 10/09/2019; Status: Continued; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - NO CONCERNS AT THIS TIME FOR THE STORMWATER CONTROLS. I HAVE ADVISED THE CONTRACTORS THAT THEY NEED TO CLEANUP CONCRETE SPOIL PILES ON THE SITE FROM TODAYS POUR. I HAVE ALSO ASKED TO EITHER CONSTRUCT A WASHOUT AREA OR CONTRACT THIS SERVICE OUT SINCE THEY ARE IN VIOLATION OF THE STORMWATER ORDINANCE AT THIS TIME AND CAN BE SITED BY ADEQ IF IT IS NOT CLEANED UP ASAP. I WILL ASKED RON LEDONNE TO CHECK THIS SITE OUT ON FRIDAY WHEN HE RETURNS TO ENSURE THAT THE CLEANUP HAS TAKEN PLACED AS DIRECTED} ; {Activity date: 09/25/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - No concerns at this time.} ; {Activity date: 09/11/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Corrections were made from last inspection report.} ; {Activity date: 08/28/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Walk site with GC went over corrections needed for temporary controls on North West side of site.} ; {Activity date: 08/14/2019; Status: Continued; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - NO CONCERNS AT THIS TIME FOR THIS SITE.} ; {Activity date: 07/31/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - No concerns at this time.} ; {Activity date: 07/16/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Walk site with GC all controls look good. Broken hydraulic line on Back hoe. Hazardous spill kit on site. No other concerns at this time.} ; {Activity date: 06/27/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - What side of the general contractor and third party Storm water inspector. No concerns at this time.} | |
04/23/2020 | ENGR Grading Final | Passed | {Activity date: 04/23/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - } ; {Activity date: 03/25/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - } ; {Activity date: 03/25/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - } | |
05/12/2020 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 05/12/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - } | |
05/12/2020 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 05/12/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - } | |
05/12/2020 | SITE - Stormwater Final Inspection | Passed | {Activity date: 05/12/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - } | |
05/12/2020 | COT - ENGR - Signage Final | Passed | {Activity date: 05/12/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - } | |
05/13/2020 | ENGR Engineering Final | Passed | {Activity date: 05/13/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - } ; {Activity date: 05/12/2020; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Complete all striping installation of wheel stops. Provide certification letter with seal from engineer of record For all grading and drainage per approved plans.} |