Permit: DP18-0225
Permit Details
Apply Date:
09/10/2018
Applicant:
Kevin Hall
Description:
E SITE - Rio Del Sol Apartments, new multi-family residential.
Permit Reviews
Permit Number - DP18-0225
Permit Status: Complete
Permit Description: E SITE - Rio Del Sol Apartments, new multi-family residential.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/31/2019 | DEV PKG - RESUBMITTAL | 03/08/2019 | COMPLETED |
03/18/2019 | DEV PKG - RESUBMITTAL | 04/01/2019 | COMPLETED |
07/03/2019 | DEV PKG - REVISION | 07/25/2019 | COMPLETED |
09/06/2018 | DEV PKG - OK TO SUBMIT | 09/10/2018 | COMPLETED |
09/12/2018 | DEV PKG | 10/12/2018 | COMPLETED |
11/19/2018 | DEV PKG - RESUBMITTAL | 12/19/2018 | COMPLETED |
02/01/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 04/12/2023 | APPROVED |
09/28/2023 | DEVELOPMENT PACKAGE NEW v.1 | 10/02/2023 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP18-0225
Permite Description: E SITE - Rio Del Sol Apartments, new multi-family residential.
Total Outstanding Inspections - 7
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/24/2023 | COT - ENGR - Site - Assurance Release | N/A | Not Applicable | |
07/24/2023 | ENGR - Drainage Structures | N/A | Partial Pass | Pending verification of other Development Packages |
07/24/2023 | COT - ENGR - Stormwater | N/A | Partial Pass | |
10/17/2023 | Final inspection to ensure all landscape and water harvesting SITE | N/A | Partial Pass | Building #5 and #6 are not completed with landscape rock and common area is still under construction, will recall inspection when completed. |
07/24/2023 | PDSD Site/Engineering Division - Landscaping | N/A | Partial Pass | Pending verification of other Development Packages |
07/24/2023 | SITE - Stormwater Follow-up | N/A | Partial Pass | Pending verification of other Development Packages |
01/17/2023 | ENGR Grading Final | N/A | Complete (Recurring) | Install the rebar for the floor for trash enclosure it’s raining today and can’t pour until tomorrow or when the rain stops must remove all the water that’s on the bottom before pouring |
Completed Inspections
Permit Status: Complete
Permit Number: DP18-0225
Permit Description: E SITE - Rio Del Sol Apartments, new multi-family residential.
Total Completed Inspections - 22
Scheduled Inspections
Scheduled Inspections - DP18-0225
Status: Complete
Description: E SITE - Rio Del Sol Apartments, new multi-family residential.
Scheduled Date | Description | Entered By | Entered Date |
---|---|---|---|
02/21/2023 | ENGR Grading Final | Scheduled |