Inspection Status: Not Ready
Inspection History: PDSD Site/Engineering Division - Landscaping
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
PDSD Site/Engineering Division - Landscaping |
|
Not Ready |
|
| 10/27/2022 |
PDSD Site/Engineering Division - Landscaping |
|
Not Ready |
|
| 02/14/2023 |
PDSD Site/Engineering Division - Landscaping |
|
Complete (Recurring) |
Landscaping is continued contractor called be out for trash enclosure footing inspection need to add to number for bars on the back corner before pouring |
| 04/05/2024 |
PDSD Site/Engineering Division - Landscaping |
|
Passed |
|
| 04/18/2023 |
PDSD Site/Engineering Division - Landscaping |
|
Partial Pass |
Trees need to be staked . DG needs to be installed. This is only for building one |
| 04/18/2023 |
PDSD Site/Engineering Division - Landscaping |
|
Partial Pass |
Trees need to be staked and DG need to be in place. For building one only |
| 07/20/2023 |
PDSD Site/Engineering Division - Landscaping |
|
Partial Pass |
Landscape is not completed |
| 07/20/2023 |
PDSD Site/Engineering Division - Landscaping |
|
Partial Pass |
Landscape is not completed yet |
| 07/24/2023 |
PDSD Site/Engineering Division - Landscaping |
|
Partial Pass |
Pending verification of other Development Packages |
| 09/19/2023 |
PDSD Site/Engineering Division - Landscaping |
|
Passed |
|
| 10/16/2023 |
PDSD Site/Engineering Division - Landscaping |
|
Partial Pass |
COMPLETE ALL WORK AS SHOWN ON THE APPROVED REVISED DRAWINGS FOR THIS SITE |