Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address:
425 N GRANDE AV
Apply Date:
04/10/2018
Applicant:
Description:
SITE - NEW COMMMUNITY BUILDING AND POOL

Permit Reviews

Permit Number - DP18-0084
Permit Status: Complete
Permit Description: SITE - NEW COMMMUNITY BUILDING AND POOL
Start Date Submittal Complete Date Status  
04/10/2018 SITE and/or GRADING 04/10/2018 ACTIVE Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP18-0084
Permit Description: SITE - NEW COMMMUNITY BUILDING AND POOL
Total Completed Inspections - 9
Date Description Inspector Results Comments
10/02/2019 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 10/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 08/29/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Contractor has started landscaping at building entrance.} ; {Activity date: 07/17/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No landscaping has been installed at this time. I did go over the drawings with the general contractor, 6 inches minimum is required at depressed landscaped areas. Details call for staking. There is a basin, we will need a letter from the engineer certified grade at the end of the project.} ; {Activity date: 03/27/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by CBELL1 - I gave Luke a heads up that recessed landscaping areas shall have 6 inches clear space.}
10/02/2019 PDSD Site/Engineering Division - NPPO Passed {Activity date: 10/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
10/02/2019 ENGR Engineering Final Passed {Activity date: 10/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 09/24/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Accessible parking spaces require correction. Grading needs to be corrected at the south end of the first and second parking areas due to flooding. Stabilize the area between the pool and the new playground equipment. Steak the trees properly.}
10/02/2019 SITE - Stormwater Follow-up Passed {Activity date: 10/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 09/05/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - All materials are contained within the site.} ; {Activity date: 08/29/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - There is heavy mud on the side, but the track out is contained to the parking lot.} ; {Activity date: 08/22/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Contractor is working on new clubhouse building. No issues or concerns at this time} ; {Activity date: 07/17/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - There is no track out or dirt on the sidewalks at this time however protections are needed along east property boundary and temporary fencing to keep the sidewalks clear. Remove all plaster and concrete that is been dumped on the ground and provide a washout location.} ; {Activity date: 06/27/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No issues at this time. There is track out with in the private parking lot but none on to grande Avenue. There is construction Debris with in the parking lot that needs to be cleaned up} ; {Activity date: 04/16/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CMURPHY1 - No issues or concerns at this time
} ; {Activity date: 03/27/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - There are no issues or concerns at this time.}
10/02/2019 ENGR Grading Final Passed {Activity date: 10/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
10/02/2019 SITE - Stormwater Final Inspection Passed {Activity date: 10/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
10/02/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 10/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 03/27/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - There are no controls in place}
10/02/2019 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 10/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 03/27/2019; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by CBELL1 - I met on site with Luke @688-6688. The project is well underway and includes a new building, new utilities, remodel to the existing buildings. The plan does not indicate new asphalt however the contractor is replacing all of the parking spaces. The plan indicates nine van accessible spaces. There are currently more than nine existing accessible spaces on the site. I asked Luke to get clarification from his engineer with regards to the amount of accessible parking spaces required.
The site is over 5 acres however the plans do not require an SWPPP. Please call for Stormwater follow up inspections by weekly. There is no trash enclosure or drainage structures shown on the plan.The plan does indicate a 7 inch deep basin as well as 6 inch recessed landscaped areas}
10/02/2019 COT - ENGR - Signage Final Passed {Activity date: 10/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }

Documents

File Name Document Type  
001_OVERALL SITE PLAN_A1.1.TIF DEVELOPMENT PACKAGE VIEW
None DOCUMENTS VIEW