Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
445 S ALVERNON WY
Apply Date:
04/04/2018
Applicant:
Description:
SITE - ADDITION TO BLDG

Permit Reviews

Permit Number - DP18-0079
Permit Status: Complete
Permit Description: SITE - ADDITION TO BLDG
Start Date Submittal Complete Date Status  
04/04/2018 SITE and/or GRADING 04/04/2018 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP18-0079
Permit Description: SITE - ADDITION TO BLDG
Total Completed Inspections - 9
Date Description Inspector Results Comments
11/14/2019 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 11/14/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No work shown on city approved existing site plan.} ; {Activity date: 11/13/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Caldwell construction Pauline, Adam, Renee. Has recently inherited this project and will obtain a set of approve plans and call for inspection when ready. Engineering needs to verify that all work has been completed as shown on city approved Site plan} ; {Activity date: 11/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Could not locate contractor with Caldwel construction. No message was provided. There appears to be ongoing work in two locations on the site. Only plan in Provo is a 2008 site plan. Please provide contact information when rescheduling this inspection provide plans for new work to be inspected.}
11/14/2019 PDSD Site/Engineering Division - NPPO Passed {Activity date: 11/14/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No work shown on city approved existing site plan.} ; {Activity date: 11/13/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Caldwell construction Pauline, Adam, Renee. Has recently inherited this project and will obtain a set of approve plans and call for inspection when ready. Engineering needs to verify that all work has been completed as shown on city approved Site plan} ; {Activity date: 11/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Could not locate contractor with Caldwel construction. No message was provided. There appears to be ongoing work in two locations on the site. Only plan in Provo is a 2008 site plan. Please provide contact information when rescheduling this inspection provide plans for new work to be inspected.}
11/14/2019 ENGR Engineering Final Passed {Activity date: 11/14/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No work shown on city approved existing site plan.} ; {Activity date: 11/13/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Caldwell construction Pauline, Adam, Renee. Has recently inherited this project and will obtain a set of approve plans and call for inspection when ready. Engineering needs to verify that all work has been completed as shown on city approved Site plan} ; {Activity date: 11/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Could not locate contractor with Caldwel construction. No message was provided. There appears to be ongoing work in two locations on the site. Only plan in Provo is a 2008 site plan. Please provide contact information when rescheduling this inspection provide plans for new work to be inspected.}
11/14/2019 SITE - Stormwater Follow-up Passed {Activity date: 11/14/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No work shown on city approved existing site plan.} ; {Activity date: 11/13/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Caldwell construction Pauline, Adam, Renee. Has recently inherited this project and will obtain a set of approve plans and call for inspection when ready. Engineering needs to verify that all work has been completed as shown on city approved Site plan} ; {Activity date: 11/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Could not locate contractor with Caldwel construction. No message was provided. There appears to be ongoing work in two locations on the site. Only plan in Provo is a 2008 site plan. Please provide contact information when rescheduling this inspection provide plans for new work to be inspected.}
11/14/2019 SITE - Stormwater Final Inspection Passed {Activity date: 11/14/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No work shown on city approved existing site plan.} ; {Activity date: 11/13/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Caldwell construction Pauline, Adam, Renee. Has recently inherited this project and will obtain a set of approve plans and call for inspection when ready. Engineering needs to verify that all work has been completed as shown on city approved Site plan} ; {Activity date: 11/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Could not locate contractor with Caldwel construction. No message was provided. There appears to be ongoing work in two locations on the site. Only plan in Provo is a 2008 site plan. Please provide contact information when rescheduling this inspection provide plans for new work to be inspected.}
11/14/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 11/14/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No work shown on city approved existing site plan.} ; {Activity date: 11/13/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Caldwell construction Pauline, Adam, Renee. Has recently inherited this project and will obtain a set of approve plans and call for inspection when ready. Engineering needs to verify that all work has been completed as shown on city approved Site plan} ; {Activity date: 11/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Could not locate contractor with Caldwel construction. No message was provided. There appears to be ongoing work in two locations on the site. Only plan in Provo is a 2008 site plan. Please provide contact information when rescheduling this inspection provide plans for new work to be inspected.}
11/14/2019 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 11/14/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No work shown on city approved existing site plan.} ; {Activity date: 11/13/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Caldwell construction Pauline, Adam, Renee. Has recently inherited this project and will obtain a set of approve plans and call for inspection when ready. Engineering needs to verify that all work has been completed as shown on city approved Site plan} ; {Activity date: 11/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Could not locate contractor with Caldwel construction. No message was provided. There appears to be ongoing work in two locations on the site. Only plan in Provo is a 2008 site plan. Please provide contact information when rescheduling this inspection provide plans for new work to be inspected.}
11/14/2019 COT - ENGR - Signage Final Passed {Activity date: 11/14/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No work shown on city approved existing site plan.} ; {Activity date: 11/13/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Caldwell construction Pauline, Adam, Renee. Has recently inherited this project and will obtain a set of approve plans and call for inspection when ready. Engineering needs to verify that all work has been completed as shown on city approved Site plan} ; {Activity date: 11/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Could not locate contractor with Caldwel construction. No message was provided. There appears to be ongoing work in two locations on the site. Only plan in Provo is a 2008 site plan. Please provide contact information when rescheduling this inspection provide plans for new work to be inspected.}
11/15/2019 ENGR Grading Final Passed {Activity date: 11/15/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by AMARTIN1 - } ; {Activity date: 11/13/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Caldwell construction Pauline, Adam, Renee. Has recently inherited this project and will obtain a set of approve plans and call for inspection when ready. Engineering needs to verify that all work has been completed as shown on city approved Site plan} ; {Activity date: 11/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Could not locate contractor with Caldwel construction. No message was provided. There appears to be ongoing work in two locations on the site. Only plan in Provo is a 2008 site plan. Please provide contact information when rescheduling this inspection provide plans for new work to be inspected.}