Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address:
513 W OURY ST
Address NEW:
513 W OURY ST
Apply Date:
02/08/2018
Applicant:
Description:
E SITE/FLD - 513 W OURY ST

Permit Reviews

Permit Number - DP18-0035
Permit Status: Complete
Permit Description: E SITE/FLD - 513 W OURY ST
Start Date Submittal Complete Date Status  
02/08/2018 DEV PKG - OK TO SUBMIT 02/12/2018 COMPLETED Review Details
02/13/2018 DEV PKG 05/08/2018 COMPLETED Review Details
05/30/2018 DEV PKG - RESUBMITTAL 08/15/2018 COMPLETED Review Details
08/15/2018 DEV PKG - RESUBMITTAL 08/31/2018 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP18-0035
Permit Description: E SITE/FLD - 513 W OURY ST
Total Completed Inspections - 9
Date Description Inspector Results Comments
10/22/2019 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 10/22/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
10/22/2019 PDSD Site/Engineering Division - NPPO Passed {Activity date: 10/22/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
10/22/2019 ENGR Engineering Final Passed {Activity date: 10/22/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
10/22/2019 SITE - Stormwater Follow-up Passed {Activity date: 10/22/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
10/22/2019 ENGR Grading Final Passed {Activity date: 10/22/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
10/22/2019 SITE - Stormwater Final Inspection Passed {Activity date: 10/22/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
10/22/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 10/22/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
10/22/2019 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 10/22/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
10/22/2019 COT - ENGR - Signage Final Passed {Activity date: 10/22/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }

Documents

File Name Document Type  
SHEET 1-6 OF 6.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW