Permit Details

Status:
Complete
Type:
Development Package
Apply Date:
01/05/2018
Applicant:
Marty Magelli
Description:
SITE/GRADING - JACK IN THE BOX

Permit Reviews

Permit Number - DP18-0004
Permit Status: Complete
Permit Description: SITE/GRADING - JACK IN THE BOX
Start Date Submittal Complete Date Status  
01/05/2018 DEV PKG - OK TO SUBMIT 01/05/2018 COMPLETED Review Details
01/05/2018 DEV PKG 02/16/2018 COMPLETED Review Details
03/22/2018 DEV PKG - RESUBMITTAL 04/18/2018 COMPLETED Review Details
04/18/2018 DEV PKG - RESUBMITTAL 05/03/2018 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP18-0004
Permit Description: SITE/GRADING - JACK IN THE BOX
Total Completed Inspections - 9
Date Description Inspector Results Comments
05/15/2018 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 05/15/2018; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
09/14/2018 SITE - Stormwater Setup and Controls Passed {Activity date: 09/14/2018; Status: Approved; Inspector: bbenedo1; Comment: Entered by BBENEDO1 - }
10/11/2018 PDSD Site/Engineering Division - NPPO Passed {Activity date: 10/11/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
10/11/2018 SITE - Stormwater Follow-up Passed {Activity date: 10/11/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 09/25/2018; Status: Correction Required; Inspector: BBENEDON; Comment: Entered by CMURPHY1 - There are no concerns at this time, the site is well contained.

Thank you Brian} ; {Activity date: 09/14/2018; Status: Continued; Inspector: bbenedo1; Comment: Entered by BBENEDO1 - No concerns} ; {Activity date: 07/03/2018; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME, ALL WORK IS CONTAINED WITHIN THE COMPOUND}
10/11/2018 ENGR Grading Final Passed {Activity date: 10/11/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
10/11/2018 COT - ENGR - Signage Final Passed {Activity date: 10/11/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
10/18/2018 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 10/18/2018; Status: Approved; Inspector: bbenedo1; Comment: Entered by BBENEDO1 - } ; {Activity date: 10/11/2018; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DROBERT5 - COMPLETE ALL LANDSCAPING ITEMS AS SHOWN ON THE APPROVED DRAWINGS FOR THIS SITE.} ; {Activity date: 09/14/2018; Status: Not ready for Inspection; Inspector: bbenedo1; Comment: Entered by BBENEDO1 - }
10/18/2018 SITE - Stormwater Final Inspection Passed {Activity date: 10/18/2018; Status: Approved; Inspector: bbenedo1; Comment: Entered by BBENEDO1 - } ; {Activity date: 10/11/2018; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NOT READY AT THIS TIME, PROVIDE APPROVED REVISED DRAWINGS FOR ANY CHANGES THAT HAVE BEEN MADE TO THIS SITE, A CERTIFICATION LETTER FROM THE ENGINEER OF RECORD FOR THIS SITE WHEN THE FINAL INSPECTIONS OF THIS PERMIT ALL SCHEDULED.}
10/25/2018 ENGR Engineering Final Passed {Activity date: 10/25/2018; Status: Approved; Inspector: JV; Comment: Entered by JVWINKL1 - } ; {Activity date: 10/18/2018; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by CBELL1 - Superintendent Pete} ; {Activity date: 10/17/2018; Status: Not ready for Inspection; Inspector: bbenedo1; Comment: Entered by BBENEDO1 - There was no sip required for this job.
09190, grading final, not ready. See the notes from 10:11 requiring a certification letter.} ; {Activity date: 10/11/2018; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NOT READY AT THIS TIME, PROVIDE APPROVED REVISED DRAWINGS FOR ANY CHANGES THAT HAVE BEEN MADE TO THIS SITE, A CERTIFICATION LETTER FROM THE ENGINEER OF RECORD FOR THIS SITE WHEN THE FINAL INSPECTIONS OF THIS PERMIT ALL SCHEDULED.} ; {Activity date: 09/14/2018; Status: Not ready for Inspection; Inspector: bbenedo1; Comment: Entered by BBENEDO1 - }

Documents

File Name Document Type  
None LETTER OF COMPLETION VIEW
001_COVER SHEET_1 OF 6.TIF DEVELOPMENT PACKAGE VIEW
002_SITE PLAN_2 OF 6.TIF DEVELOPMENT PACKAGE VIEW
003_GRADING / PAVING / UTILITY_3 OF 6.TIF DEVELOPMENT PACKAGE VIEW
004_LANDSCAPE_L-1 4 OF 6.TIF DEVELOPMENT PACKAGE VIEW
005_IRRIGATION_L-2 5 OF 6.TIF DEVELOPMENT PACKAGE VIEW
006_CONSTRUCTION_L-3 6 OF 6.TIF DEVELOPMENT PACKAGE VIEW
DP18-0004 COMMENT LETTER 1.26.18.PDF DOCUMENTS VIEW