Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address:
4901 N ORACLE RD
Apply Date:
12/08/2017
Applicant:
Tri Miller
Description:
SITE/GRADING - SUBARU1st revision approved 6/14/18 (sheet 1, 3, 4, 5)

Permit Reviews

Permit Number - DP17-0290
Permit Status: Complete
Permit Description: SITE/GRADING - SUBARU1st revision approved 6/14/18 (sheet 1, 3, 4, 5)
Start Date Submittal Complete Date Status  
03/02/2018 DEV PKG - RESUBMITTAL 04/25/2018 COMPLETED Review Details
04/25/2018 DEV PKG - RESUBMITTAL 05/21/2018 COMPLETED Review Details
06/08/2018 DEV PKG - REVISION 06/18/2018 COMPLETED Review Details
12/08/2017 DEV PKG - OK TO SUBMIT 12/08/2017 COMPLETED Review Details
12/08/2017 DEV PKG 03/02/2018 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP17-0290
Permit Description: SITE/GRADING - SUBARU1st revision approved 6/14/18 (sheet 1, 3, 4, 5)
Total Completed Inspections - 9
Date Description Inspector Results Comments
11/21/2019 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 11/21/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
11/21/2019 PDSD Site/Engineering Division - NPPO Passed {Activity date: 11/21/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
11/21/2019 SITE - Stormwater Follow-up Passed {Activity date: 11/21/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
11/21/2019 SITE - Stormwater Final Inspection Passed {Activity date: 11/21/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
11/21/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 11/21/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
11/21/2019 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 11/21/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
11/21/2019 COT - ENGR - Signage Final Passed {Activity date: 11/21/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
03/11/2020 ENGR Engineering Final Passed {Activity date: 03/11/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 11/21/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Provide a letter from the engineer certifying that the work installed without inspection was installed per plan and that the site grading is also as shown on city approved plans.}
03/11/2020 ENGR Grading Final Passed {Activity date: 03/11/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 08/09/2019; Status: Not Applicable; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - NOT APPLICABLE FOR THE REQUEST FOR LIGHT POLE FOUNDATION, THIS INSPECTION IS TO BE DONE BY DAN QUINN OF THE BUILDING INSPECTORS.}

Documents

File Name Document Type  
001_COVER SHEET / NOTES_1 OF 9.TIF DEVELOPMENT PACKAGE VIEW
002_GRADING / PAVING NOTES_2 OF 9.TIF DEVELOPMENT PACKAGE VIEW
003_SITE_3 OF 9.TIF DEVELOPMENT PACKAGE VIEW
004_SITE_4 OF 9.TIF DEVELOPMENT PACKAGE VIEW
005_GRADING / PAVING_5 OF 9.TIF DEVELOPMENT PACKAGE VIEW
006_SITE / GRADING DETAILS_6 OF 9.TIF DEVELOPMENT PACKAGE VIEW
007_LANDSCAPE_7 OF 9.TIF DEVELOPMENT PACKAGE VIEW
008_LANDSCAPE_8 OF 9.TIF DEVELOPMENT PACKAGE VIEW
009_IRRIGATION_9 OF 9.TIF DEVELOPMENT PACKAGE VIEW
010_PLUMBING SITE_PSI.TIF DEVELOPMENT PACKAGE VIEW
FACILITY MAP.PDF DOCUMENTS VIEW
PAGES FROM DEVELOPMENT PKG.PDF DOCUMENTS VIEW
DRAINAGE STATEMENT01.PDF DOCUMENTS VIEW
GEOTECHNICAL REPORT WTI 2927JH086.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW
GEOTECH EVALUATION REPORT.PDF DOCUMENTS VIEW