Permit: DP16-0166
Permit Details
Apply Date:
09/20/2016
Applicant:
Philip Veneziano
Description:
SITE/GRADING NEW BLDG
Permit Reviews
Permit Number - DP16-0166
Permit Status: Complete
Permit Description: SITE/GRADING NEW BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/12/2017 | RESUB - SITE and/or GRADING | 01/13/2017 | COMPLETED |
| 09/20/2016 | DEV PKG - OK TO SUBMIT | 09/21/2016 | COMPLETED |
| 09/21/2016 | SITE and/or GRADING | 10/26/2016 | COMPLETED |
| 10/26/2016 | RESUB - SITE and/or GRADING | 11/01/2016 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP16-0166
Permit Description: SITE/GRADING NEW BLDG
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/17/2016 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 11/17/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - 1) NO CONTACT ON SITE 2) REVIEWED PLANS, SITE IS LESS THAN 1 ACRE THEREFORE NO SWPPP IS REQUIRED. 3) SPOKE WITH SUPERINTENDENT 4) SWEEP UP TRACKING OFF OF ADJACENT PUBLIC ROADWAY} ; {Activity date: 11/14/2016; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - MET WITH THE DEVELOPER/CONTRACTOR ON SITE IN THE AFTERNOON TOOK A LOOK AT THE WORK THAT THEY WILL BE PERFORMING. I HAVE ADVISED THEM THAT THEY ARE LESS THAN AN ACRE FOR THIS SITE SO THEY ARE NOT REQUIRED TO HAVE A SWPPP, BUT THEY WILL BE REQUIRED TO MAINTAIN THE SITE. MIKE RUSSO WILL COME OUT TO THE SITE ON 11/15/16 FOR THE REMAINING PRE-CON MEETING AND DISCUSS THE OPERATION. NO WORK HAS BEEN STARTED ON THIS SITE AT THIS TIME.} |
|
| 01/31/2017 | COT - ENGR - Signage Final | Passed | {Activity date: 01/31/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 02/06/2017 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 02/06/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 02/06/2017 | ENGR Grading Final | Passed | {Activity date: 02/06/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 02/17/2017 | ENGR Engineering Final | Passed | {Activity date: 02/17/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 02/07/2017; Status: Denied; Inspector: MRUSSO; Comment: Entered by DROBERT5 - COMPLETE PEDESTRIAN ACCESS FROM THE STREET TO THE BLDG, ENSURE IT MEETS ADA} | |
| 07/02/2017 | RSBU - Building Final | Passed | {Activity date: 07/02/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } |