Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
3700 S CALLE POLAR
Apply Date:
10/27/2015
Applicant:
Lisa Bowers
Description:
SITE/ GRADING -10 NEW VETERANS MULTI HOUSING BUILDINGS Originally approved 3/23/2016 (17 pages)

Permit Reviews

Permit Number - DP15-0188
Permit Status: Complete
Permit Description: SITE/ GRADING -10 NEW VETERANS MULTI HOUSING BUILDINGS Originally approved 3/23/2016 (17 pages)
Start Date Submittal Complete Date Status  
01/15/2016 DEV PKG - RESUBMITTAL 03/16/2016 COMPLETED Review Details
03/09/2017 DEV PKG - REVISION 03/17/2017 COMPLETED Review Details
03/16/2016 DEV PKG - RESUBMITTAL 04/19/2016 COMPLETED Review Details
03/17/2017 DEV PKG - REVISION 03/23/2017 COMPLETED Review Details
04/14/2017 DEV PKG - REVISION 04/21/2017 COMPLETED Review Details
10/27/2015 DEV PKG - OK TO SUBMIT 11/02/2015 COMPLETED Review Details
11/03/2015 DEV PKG 01/15/2016 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP15-0188
Permit Description: SITE/ GRADING -10 NEW VETERANS MULTI HOUSING BUILDINGS Originally approved 3/23/2016 (17 pages)
Total Completed Inspections - 9
Date Description Inspector Results Comments
06/23/2016 SITE - Stormwater Setup and Controls Passed {Activity date: 06/23/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - 1) SITE IS IN COMPLIANCE WITH SWPPP AND COT INSPECTION RECOMMENDATIONS.
2) ENSURE TRACKING OF SOIL IS SWEPT ROUTINELY.
3) INSTALL A CONCRETE WASH OUT WHEN APPLICABLE.
4) CALL IN FOLLOW UP INSPECTION AS NEEDED}
06/23/2016 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 06/23/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } ; {Activity date: 06/16/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - MET WITH SUPERINTENDENT ON SITE.

1) CALL IN FOR A PRE-CON MEETING PER YOUR PERMIT/ APPROVED PLANS.
2) IMPLEMENT YOUR STORM WATER PLAN, PRIOR TO GRUBBING AND GRADING.
3) CALL FOR INSPECTION WHEN CONTROLS ARE INSTALLED.
4) SITE IS IN NON-COMPLIANCE WITH YOUR STORM WATER PERMIT AND PLAN, CONTINUED NON-COMPLIANCE MAY RESULT IN A STOP WORK ORDER.}
04/14/2017 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 04/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
04/14/2017 PDSD Site/Engineering Division - NPPO Passed {Activity date: 04/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
04/14/2017 SITE - Stormwater Follow-up Passed {Activity date: 04/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 03/22/2017; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO STORMWATER CONCERNS AT THIS TIME.} ; {Activity date: 03/21/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) ENSURE THE STORM WATER PLAN IS STILL IN EFFECT UNTIL THE SITE IS STABILIZED
2) FILE A NOTICE OF TERMINATION WITH ADEQ} ; {Activity date: 03/06/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED} ; {Activity date: 02/02/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 01/19/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 12/12/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 11/02/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - NO STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 10/20/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - 1) ENSURE SEDIEMNT CONTROLS REMAIN IN PLACE AND ARE MAINTAINED THROUGHOUT CONSTRUCTION
2) SWEEP UP TRACKED SOIL ROUTINELY
3) PERFOM SELF INSPECTION AND DOCUMENT THEM PER YOUR SWPPP.} ; {Activity date: 09/22/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - 1) ENSURE TEMPORARY SEDIMENT CONTROLS REMAIN IN PLACE UNTIL CONSTRUCTION IS COMPLETED.
2) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED PER PLAN AND DOCUMENTED} ; {Activity date: 07/06/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 06/24/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - NO CHANGES AND/OR CONCERNS AT THIS TIME}
04/14/2017 ENGR Grading Final Passed {Activity date: 04/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
04/14/2017 SITE - Stormwater Final Inspection Passed {Activity date: 04/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
04/14/2017 COT - ENGR - Signage Final Passed {Activity date: 04/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
04/26/2017 ENGR Engineering Final Passed {Activity date: 04/26/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 04/24/2017; Status: Denied; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO PLANS ON SITE} ; {Activity date: 04/20/2017; Status: Not ready for Inspection; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NOT READY FOR FINAL APPROVAL} ; {Activity date: 04/19/2017; Status: Not ready for Inspection; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NOT READY FOR FINAL APPROVAL} ; {Activity date: 04/14/2017; Status: Prior to Final Inspectn; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) COMPLETE LANDSCAPING, TO INCLUDE ROCK AND ALL PLANTING PER THE APPROVED PLAN
2) PROVIDE A CITY OF TUCSON APPROVED PLAN FOR FINAL GRADING INSPECTION
3) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD
4) COMPLETE ALL SITE WORK TO INCLUDE INSTALL OF ALL HADRAILING, AND ANY FLAT WORK SHOWN ON THE APPROVED PLANS} ; {Activity date: 03/21/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) PROVIDE AN APPROVED PLAN SHOWING REVISION TO THE SITE FOR THE FINAL GRADING INSPECTION
2) PROVID A CERT STATEMENT FROM THE ENG OF RECORD PRIOR TO FINAL APPROVAL
3) COMPLETE ALL SITE WORK AND LANDSCAPING PRIOR TO FINAL APPROVAL} ; {Activity date: 10/20/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - ENSURE ANY AND ALL CHANGES TO THE SITE/GRADING/LANDSCAPING, ARE SHOWN ON THE APPROVED PLANS AND ARE AVAILABLE FOR FINAL SITE INSPECTION}