Permit: DP15-0188

Parcel: Unknown


Addresses:

3700 S CALLE POLAR


Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP15-0188

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
04/14/2017 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
04/14/2017 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
04/14/2017 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
03/20/2017 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - WALKED THE SITE WITH THE DEVELOPER/CONTRACTOR TO SEE HOW THE WORK IS GOING. THEY WERE CURRENTLY PLACING THE ROCK RIP RAP ONTO THE SLOPES WITH FILTER FABRIC, BUT IT IS NOT THE FABRIC THAT WE USUALLY HAVE CALLED OUT IN THE DETAILS. I VERIFIED ON THE PLAN THAT NO SPECIFICATION WAS GIVEN ON THE TYPE OF FILTER FABRIC. I DID SUGGEST THE MIRAFI TYPE SINCE IT IS A MORE DURABLE PRODUCT AND WILL NOT DETERIORATE AS FAST AS THE MATERIAL THAT THEY ARE CURRENTLY USING. THEY WILL BE LOOKING FOR TEMPORARY C OF O FOR THIS SITE BEFORE THE MIDDLE OF APRIL. I HAVE ADVISED THEM TO COMPLETE ALL THE WORK ON THIS SITE, CONCENTRATING ON THE AREAS THAT MAY AFFECT THE MOVEMENT OF PEDESTRIAN TRAFFIC WITHIN THE SITE. INSTALLATION OF THE LANDSCAPING AND INSTALLING ALL GROUND COVER SHOULD BE HIGH ON THE LIST OF WORK TO BE COMPLETED FIRST.
03/21/2017 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - MET THE DEVELOPER ON SITE AND LOOKED AT THE ADA ACCESS THROUGH THE SITE. MOST OF THE SIDEWALK WITHIN THE SITE APPEARS TO MEET THE RUNNING SLOPE VALUES OF 5% OR LESS, AND THE CROSS SLOPE VALUE OF 2% OR LESS. THERE IS ONE LOCATION LOCATED AT THE SOUTHWEST CORNER OF BUILDING #9 THAT IS OUT OF COMPLIANCE FOR THE CROSS SLOPES. THE CONTRACTOR WILL REMOVE AND REPLACE THIS AREA SO THAT IT IS LESS THAN THE 2% MAXIMUM TOLERANCE FOR THE SLOPE VALUES PRIOR TO CALLING IN THIS SITE FOR THE FINAL INSPECTION.
03/21/2017 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) PROVIDE AN APPROVED PLAN SHOWING REVISION TO THE SITE FOR THE FINAL GRADING INSPECTION 2) PROVID A CERT STATEMENT FROM THE ENG OF RECORD PRIOR TO FINAL APPROVAL 3) COMPLETE ALL SITE WORK AND LANDSCAPING PRIOR TO FINAL APPROVAL
06/16/2016 ENGR Grading Final MRUSSO Continued Entered by MRUSSO1 - MET WITH SUPERINTENDENT ON SITE. 1) CALL IN FOR A PRE-CON MEETING PER YOUR PERMIT/ APPROVED PLANS. 2) IMPLEMENT YOUR STORM WATER PLAN, PRIOR TO GRUBBING AND GRADING. 3) CALL FOR INSPECTION WHEN CONTROLS ARE INSTALLED. 4) SITE IS IN NON-COMPLIANCE WITH YOUR STORM WATER PERMIT AND PLAN, CONTINUED NON-COMPLIANCE MAY RESULT IN A STOP WORK ORDER.
04/14/2017 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
03/23/2017 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - LOOKED AT ONE OF THE TWO TRASH ENCLOSURES FOOTINGS AND REBAR LAY OUT, INSTALLED PER APPROVED PLANS. PROVIDE PICS FOR SECOND ENCLOSURE WHEN COMPLETED
09/19/2016 ENGR Grading Final MRUSSO Continued Entered by MRUSSO1 - RE-BAR FOOTINGS FOR RAMADA COLUMN'S INSTALLED PER APPROVED PLAN - OK TO POUR CONCRETE