Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
3700 S CALLE POLAR
Apply Date:
10/27/2015
Applicant:
Lisa Bowers
Description:
SITE/ GRADING -10 NEW VETERANS MULTI HOUSING BUILDINGS Originally approved 3/23/2016 (17 pages)

Permit Reviews

Permit Number - DP15-0188
Permit Status: Complete
Permit Description: SITE/ GRADING -10 NEW VETERANS MULTI HOUSING BUILDINGS Originally approved 3/23/2016 (17 pages)
Start Date Submittal Complete Date Status  
01/15/2016 DEV PKG - RESUBMITTAL 03/16/2016 COMPLETED Review Details
03/09/2017 DEV PKG - REVISION 03/17/2017 COMPLETED Review Details
03/16/2016 DEV PKG - RESUBMITTAL 04/19/2016 COMPLETED Review Details
03/17/2017 DEV PKG - REVISION 03/23/2017 COMPLETED Review Details
04/14/2017 DEV PKG - REVISION 04/21/2017 COMPLETED Review Details
10/27/2015 DEV PKG - OK TO SUBMIT 11/02/2015 COMPLETED Review Details
11/03/2015 DEV PKG 01/15/2016 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP15-0188
Permit Description: SITE/ GRADING -10 NEW VETERANS MULTI HOUSING BUILDINGS Originally approved 3/23/2016 (17 pages)
Total Completed Inspections - 9
Date Description Inspector Results Comments
06/23/2016 SITE - Stormwater Setup and Controls Passed {Activity date: 06/23/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - 1) SITE IS IN COMPLIANCE WITH SWPPP AND COT INSPECTION RECOMMENDATIONS.
2) ENSURE TRACKING OF SOIL IS SWEPT ROUTINELY.
3) INSTALL A CONCRETE WASH OUT WHEN APPLICABLE.
4) CALL IN FOLLOW UP INSPECTION AS NEEDED}
06/23/2016 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 06/23/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } ; {Activity date: 06/16/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - MET WITH SUPERINTENDENT ON SITE.

1) CALL IN FOR A PRE-CON MEETING PER YOUR PERMIT/ APPROVED PLANS.
2) IMPLEMENT YOUR STORM WATER PLAN, PRIOR TO GRUBBING AND GRADING.
3) CALL FOR INSPECTION WHEN CONTROLS ARE INSTALLED.
4) SITE IS IN NON-COMPLIANCE WITH YOUR STORM WATER PERMIT AND PLAN, CONTINUED NON-COMPLIANCE MAY RESULT IN A STOP WORK ORDER.}
04/14/2017 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 04/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
04/14/2017 PDSD Site/Engineering Division - NPPO Passed {Activity date: 04/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
04/14/2017 SITE - Stormwater Follow-up Passed {Activity date: 04/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 03/22/2017; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO STORMWATER CONCERNS AT THIS TIME.} ; {Activity date: 03/21/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) ENSURE THE STORM WATER PLAN IS STILL IN EFFECT UNTIL THE SITE IS STABILIZED
2) FILE A NOTICE OF TERMINATION WITH ADEQ} ; {Activity date: 03/06/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED} ; {Activity date: 02/02/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 01/19/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 12/12/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 11/02/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - NO STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 10/20/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - 1) ENSURE SEDIEMNT CONTROLS REMAIN IN PLACE AND ARE MAINTAINED THROUGHOUT CONSTRUCTION
2) SWEEP UP TRACKED SOIL ROUTINELY
3) PERFOM SELF INSPECTION AND DOCUMENT THEM PER YOUR SWPPP.} ; {Activity date: 09/22/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - 1) ENSURE TEMPORARY SEDIMENT CONTROLS REMAIN IN PLACE UNTIL CONSTRUCTION IS COMPLETED.
2) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED PER PLAN AND DOCUMENTED} ; {Activity date: 07/06/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 06/24/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - NO CHANGES AND/OR CONCERNS AT THIS TIME}
04/14/2017 ENGR Grading Final Passed {Activity date: 04/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
04/14/2017 SITE - Stormwater Final Inspection Passed {Activity date: 04/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
04/14/2017 COT - ENGR - Signage Final Passed {Activity date: 04/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
04/26/2017 ENGR Engineering Final Passed {Activity date: 04/26/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 04/24/2017; Status: Denied; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO PLANS ON SITE} ; {Activity date: 04/20/2017; Status: Not ready for Inspection; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NOT READY FOR FINAL APPROVAL} ; {Activity date: 04/19/2017; Status: Not ready for Inspection; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NOT READY FOR FINAL APPROVAL} ; {Activity date: 04/14/2017; Status: Prior to Final Inspectn; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) COMPLETE LANDSCAPING, TO INCLUDE ROCK AND ALL PLANTING PER THE APPROVED PLAN
2) PROVIDE A CITY OF TUCSON APPROVED PLAN FOR FINAL GRADING INSPECTION
3) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD
4) COMPLETE ALL SITE WORK TO INCLUDE INSTALL OF ALL HADRAILING, AND ANY FLAT WORK SHOWN ON THE APPROVED PLANS} ; {Activity date: 03/21/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) PROVIDE AN APPROVED PLAN SHOWING REVISION TO THE SITE FOR THE FINAL GRADING INSPECTION
2) PROVID A CERT STATEMENT FROM THE ENG OF RECORD PRIOR TO FINAL APPROVAL
3) COMPLETE ALL SITE WORK AND LANDSCAPING PRIOR TO FINAL APPROVAL} ; {Activity date: 10/20/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - ENSURE ANY AND ALL CHANGES TO THE SITE/GRADING/LANDSCAPING, ARE SHOWN ON THE APPROVED PLANS AND ARE AVAILABLE FOR FINAL SITE INSPECTION}

Documents

File Name Document Type  
None LETTER OF COMPLETION VIEW
001_COVER SHEET_1 OF 17.TIF DEVELOPMENT PACKAGE VIEW
002_NOTES_2 OF 17.TIF DEVELOPMENT PACKAGE VIEW
003_SITE_3 OF 17.TIF DEVELOPMENT PACKAGE VIEW
004_GRADING / DRAINAGE_4 OF 17.TIF DEVELOPMENT PACKAGE VIEW
004_GRADING / DRAINAGE REVISED_4A-17.TIF DEVELOPMENT PACKAGE VIEW
005_UTILITIES / EASEMENTS_5 OF 17.TIF DEVELOPMENT PACKAGE VIEW
006_DETAILS_6 OF 17.TIF DEVELOPMENT PACKAGE VIEW
007_DETAILS_7 OF 17.TIF DEVELOPMENT PACKAGE VIEW
008_SWPPP_8 OF 17.TIF DEVELOPMENT PACKAGE VIEW
009_SITE DEMOLITION L1.0_9 OF 17.TIF DEVELOPMENT PACKAGE VIEW
010_LANDSCAPE L1.1_10 OF 17.TIF DEVELOPMENT PACKAGE VIEW
011_LANDSCAPE MATERIALS DETAIL L1.2_11 OF 17.TIF DEVELOPMENT PACKAGE VIEW
012_LANDSCAPE DETAILS L1.3_12 OF 17.TIF DEVELOPMENT PACKAGE VIEW
013_LANDSCAPE SPECIFICATIONS L1.4_13 OF 17.TIF DEVELOPMENT PACKAGE VIEW
014_IRRIGATION L2.0_14 OF 17.TIF DEVELOPMENT PACKAGE VIEW
015_IRRIGATION DETAILS L2.1_15 OF 17.TIF DEVELOPMENT PACKAGE VIEW
016_IRRIGATION DETAILS L2.2_16 OF 17.TIF DEVELOPMENT PACKAGE VIEW
017_IRRIGATION SPECIFICATIONS L2.3_17 OF 17.TIF DEVELOPMENT PACKAGE VIEW
ADDRESSING COMMENT DP15-0188.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW