Permit Details

Status:
Complete
Type:
Development Package
Apply Date:
08/27/2015
Applicant:
Description:
GRADING ONLY

Permit Reviews

Permit Number - DP15-0140
Permit Status: Complete
Permit Description: GRADING ONLY
Start Date Submittal Complete Date Status  
08/27/2015 DEV PKG - OK TO SUBMIT (GRADING ONLY) 08/27/2015 COMPLETED Review Details
08/27/2015 GRADING 10/08/2015 COMPLETED Review Details
10/08/2015 GRADING 11/03/2015 ACTIVE Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP15-0140
Permit Description: GRADING ONLY
Total Completed Inspections - 9
Date Description Inspector Results Comments
01/15/2016 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 01/15/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) CALL FOR INSPECTION FOR ANY CHANGES OR QUESTIONS CONCERNING GRADING/LANDSCAPING/STORM WATER.
2) PERFORM STORM WATER SELF INSPECTION PER YOUR SWPPP.
3) INSTALL STABILIZED CONSTRUCTION ENTRANCE
4) INSTALL SEDIMENT CONTROLS ALONG PUBLIC DRAINAGE
5) INSTALL A CONCRETE/MATERIALS WASH OUT WHEN APPLICABLE
6) SEDIMENT CONTROLS MAY NEED TO BE ADJUSTED BASED ON SITE SPECIFICS ARE CHANGING CONDITIONS} ; {Activity date: 01/12/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) CALL IN FOR A PRE-CON MEETING PRIOR TO THE START OF CONSTRUCTION- OLEARY CONSTR (PAUL 240-2135)/KB HOMES (ERIC 250-5709).
2) IMPLEMENT STORM WATER CONTROLS AND REQUIREMENTS PRIOR TO CONSTRUCTION.}
02/29/2016 SITE - Stormwater Setup and Controls Passed {Activity date: 02/29/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - }
02/22/2017 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 02/22/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
02/22/2017 PDSD Site/Engineering Division - NPPO Passed {Activity date: 02/22/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
02/22/2017 SITE - Stormwater Follow-up Passed {Activity date: 02/22/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 12/12/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO INSPECTIONS CALLED IN} ; {Activity date: 04/01/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - SWEEP TRACKING OFF OF PRUDENCE ROAD} ; {Activity date: 03/22/2016; Status: Correction Required; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - 1) TRACKING ALONG THE WEST BOUNDRY
2) SWEEP SOIL OFF ADJACENT ROADWAY
3) ANY ENTRANCE/EXIT TO SITE MUST BE STABILIZED} ; {Activity date: 02/29/2016; Status: Correction Required; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - 1) MAY NEED TO ADD SEDIMENT CONTROLS ALONG THE WEST PERIMETER OF THE SITE
2) ENSURE CONSTRUCTION TRAFFIC USES THE STABILIZED CONSTRUCTION ENTRANCE
3) SWEEP UP SOIL OFF THE ADJACENT PUBLIC ROADWAY}
02/22/2017 ENGR Grading Final Passed {Activity date: 02/22/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
02/22/2017 COT - ENGR - Signage Final Passed {Activity date: 02/22/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
07/21/2017 SITE - Stormwater Final Inspection Passed {Activity date: 07/21/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 02/22/2017; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
05/24/2018 ENGR Engineering Final Passed {Activity date: 05/24/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 02/28/2018; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - STILL WAITING FOR THE DEVELOPER TO COMPLETE ALL OF THE WORK ON THIS SITE} ; {Activity date: 03/28/2017; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) COMPLETE SIDE- WALKS ALONG LOTS THAT HAVE NOT BEEN BUILT OUT.
2) INSTALL THE WALKWAY SHOWN NEXT TO LOT#46 PER THE APPROVED PLAN.
3) MITER RET BASIN BLEED PIPE TO MATCH SLOPE AS SHOWN ON APPROVED PLANS
4) INSTALL HAND RAILING AT SIDE-WALK SCUPPERS PER PLAN
5) FILE A NOTICE OF TERMINATION WITH ADEQ FOR YOUR STORM WATER PERMIT
6) STABILIZE REMAINING LOTS} ; {Activity date: 03/06/2017; Status: Prior to Final Inspectn; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) PROVIDE A CERT. STATEMENT FROM THE ENG OF RECORD, STATING THAT THE SITE/GRADING WAS SUBSTANTIALLY COMPLETED PER THE APPROVED PLAN.
2) PROVIDE A FINAL REVISED PLAN FOR FINAL GRADING INSPECTION
3) CALL IN FOR FINAL GRADING FOR DP15-0140}

Documents

File Name Document Type  
001_COVER SHEET / NOTES_1 OF 6.TIF DEVELOPMENT PACKAGE VIEW
002_GRADING NOTES_2 OF 6.TIF DEVELOPMENT PACKAGE VIEW
003_GRADING_3 OF 6.TIF DEVELOPMENT PACKAGE VIEW
004_GRADING DETAILS_4 OF 6.TIF DEVELOPMENT PACKAGE VIEW
005_GRADING DETAILS_5 OF 6.TIF DEVELOPMENT PACKAGE VIEW
006_EROSING CONTROL_6 OF 6.TIF DEVELOPMENT PACKAGE VIEW
None DOCUMENTS VIEW