Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 05/24/2018 |
ENGR Engineering Final
|
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 02/28/2018 |
ENGR Engineering Final
|
DROBERTS |
Partial Approval |
Entered by DROBERT5 - STILL WAITING FOR THE DEVELOPER TO COMPLETE ALL OF THE WORK ON THIS SITE |
| 03/28/2017 |
ENGR Engineering Final
|
MRUSSO |
Partial Approval |
Entered by DROBERT5 - 1) COMPLETE SIDE- WALKS ALONG LOTS THAT HAVE NOT BEEN BUILT OUT.
2) INSTALL THE WALKWAY SHOWN NEXT TO LOT#46 PER THE APPROVED PLAN.
3) MITER RET BASIN BLEED PIPE TO MATCH SLOPE AS SHOWN ON APPROVED PLANS
4) INSTALL HAND RAILING AT SIDE-WALK SCUPPERS PER PLAN
5) FILE A NOTICE OF TERMINATION WITH ADEQ FOR YOUR STORM WATER PERMIT
6) STABILIZE REMAINING LOTS |
| 03/06/2017 |
ENGR Engineering Final
|
MRUSSO |
Prior to Final Inspectn |
Entered by DROBERT5 - 1) PROVIDE A CERT. STATEMENT FROM THE ENG OF RECORD, STATING THAT THE SITE/GRADING WAS SUBSTANTIALLY COMPLETED PER THE APPROVED PLAN.
2) PROVIDE A FINAL REVISED PLAN FOR FINAL GRADING INSPECTION
3) CALL IN FOR FINAL GRADING FOR DP15-0140 |
| 05/24/2018 |
ENGR Engineering Final
|
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 03/28/2017 |
ENGR Engineering Final
|
MRUSSO |
Partial Approval |
Entered by DROBERT5 - 1) COMPLETE SIDE- WALKS ALONG LOTS THAT HAVE NOT BEEN BUILT OUT.
2) INSTALL THE WALKWAY SHOWN NEXT TO LOT#46 PER THE APPROVED PLAN.
3) MITER RET BASIN BLEED PIPE TO MATCH SLOPE AS SHOWN ON APPROVED PLANS
4) INSTALL HAND RAILING AT SIDE-WALK SCUPPERS PER PLAN
5) FILE A NOTICE OF TERMINATION WITH ADEQ FOR YOUR STORM WATER PERMIT
6) STABILIZE REMAINING LOTS |
| 03/06/2017 |
ENGR Engineering Final
|
MRUSSO |
Prior to Final Inspectn |
Entered by DROBERT5 - 1) PROVIDE A CERT. STATEMENT FROM THE ENG OF RECORD, STATING THAT THE SITE/GRADING WAS SUBSTANTIALLY COMPLETED PER THE APPROVED PLAN.
2) PROVIDE A FINAL REVISED PLAN FOR FINAL GRADING INSPECTION
3) CALL IN FOR FINAL GRADING FOR DP15-0140 |