Permit: DP14-0107
Permit Details
Status:
Complete
Type:
Development Package
Address:
5201 N GRACIOUS CT
Address NEW:
5201 N GRACIOUS CT
Apply Date:
06/18/2014
Applicant:
Description:
GRADING
Permit Reviews
Permit Number - DP14-0107
Permit Status: Complete
Permit Description: GRADING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/02/2015 | REVISION - GRADING | 02/12/2015 | COMPLETED |
| 06/18/2014 | GRADING | 07/15/2014 | COMPLETED |
| 08/26/2014 | RESUB - SITE and/or GRADING | 08/26/2014 | COMPLETED |
Conditions
Permit Number - DP14-0107
Permit Status: Complete
Permit Description: GRADING
| Date | Description | Comments |
|---|---|---|
| 06/25/2014 | GRADING PERMIT CONDITIONS: The following 11 conditions apply to this grading permit DP14-0107:1)Call for Pre-construction meeting. For a PDSD Engineering Inspection, call IVR (740-6970), or schedule with a Customer Service Representative at the Planning & Development Services Department - Angie 837-4917, or contact PDSD Engineering at 837-4888, or schedule inspections online at: http://www.ci.tucson.az.us/dsd/Online_Services/Online_Permits/online_permits.html 2)Copy of approved plan/permit DP14-0107 shall be kept at site at all times until final grading approval.3)These sets of plans act as the approved final grading plans for Gracious Estates Lot 4 custom grading per approved plans sealed by Dr Peter Livingston, P.E. 4)There shall be no disturbance outside of the disturbance/grading limits as shown on approved grading plans. Disturbance outside these limits may result in Notice of Violation, Stop Work Order, fines, and / or require revised plan submittal & review. Temporary fencing is required at north and northeast disturbance limits.5)PDSD Inspector should inspect special grading such as temporary fencing, stormdrain pipe installation, and cut / fill slopes when under construction. | |
| 06/25/2014 | 6)Trenching, bedding, installation, backfill compaction for stormdrain pipe shall conform to American Concrete Pipe Association compaction and installation specifications or PC/COT Stnd Specs sections 501-2.06, 501-3.02, 501-3.03(H), and 501-3.04. 7)If grading construction is expected to last longer than the expiration date of the grading permit, contact PDSD to renew/extend the Grading Permit. If Final Grading Inspection has not been completed before the Grading Permit expires, and the permit has not been renewed, additional fees and reviews may be required.8)Revisions to the design must be discussed with a Civil Engineer at the City of Tucson Planning & Development Services Department Engineering Division, prior to any construction activity, to determine whether additional details, calculations, drainage report, or a revised grading plan is needed, or, whether changes may be provided on as-builts. All work completed without approval is subject to Notice of Violation or Stop Work Order. 9)Permittee shall notify the PDSD when the grading operation is ready for final grading inspection. Final grading approval shall not be given until all work, including installation of all drainage improvements and their permanent protective devices, and all permanent erosion control measures have been completed in accordance with the approved grading plan and grading permit, and all conditions of permit are completed. Any revegetated areas shall require Landscaping approval of established vegetation prior to Final Grading Approval. Any other exposed areas that are not reseeded shall be covered in gravel or hand placed rip rap, unless other material is proposed, reviewed, and accepted by City of Tucson.10)Temporary erosion and sediment control devices may be placed at locations where stormwater runoff exits grading limits to prevent debris, construction silt, and/or chemicals from entering streets or any drainage ways. Any interim erosion and sediment controls that are installed should be maintained, per approved grading plans or per EOR, at downstream areas of disturbance limits, and at project completion removed.11)Project Engineering completion letters, as well as As-Builts are required to be submitted prior to final Grading Inspection. Letter of certification from Engineer of Record for project substantial completion is required and submitted prior to final grading inspection. As-builts should include as-built elevations for finished pad grade, front of driveway at street elevation, stormdrain pipe inverts, and other areas as deemed needed by surveyor. |
Completed Inspections
Permit Status: Complete
Permit Number: DP14-0107
Permit Description: GRADING
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/25/2014 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 07/25/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) NO NPPO WITH THIS LOT 2) INSTALL SEDIMENT CONTROLS ALONG THE NORTH/NORTHEAST PERIMETER 3) INSTALL GRADING LIMIT BOUNDRY FENCE PER YOUR APPROVED PLAN/CONDITIONS 4) CALL FOR RE-INSPECTION WHEN SEDIMENT CONTROLS ARE INSTALLED} |
|
| 02/10/2015 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 01/12/2015; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - 1) PROVIDE VERIFICATION THAT YOU MEET THE REQUIREMENTS OF THE TENTATIVE PLAT. 2)PROVIDE AS-BUILT DRAWINGS AND CERTIFICATION LETTER FROM THE ENGINEER OF RECORD FOR THIS SITE. 3) VERIFY THE DRAINAGE AT THE NORTHWEST CORNER OF THIS SITE, THIS AREA MAY NEED ADDITIONAL PROTECTION FROM THE CURRENT FLOW PATTERNS.} ; {Activity date: 02/10/2015; Status: Approved; Inspector: eleibol1; Comment: Entered by ELEIBOL1 - } |
|
| 02/10/2015 | SITE - Stormwater Final Inspection | Passed | {Activity date: 01/12/2015; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - REMOVE THE STORMWATER CONTROLS FROM THIS SITE PRIOR TO CALLING IN ANOTHER FINAL.} ; {Activity date: 02/10/2015; Status: Approved; Inspector: eleibol1; Comment: Entered by ELEIBOL1 - } | |
| 02/10/2015 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 01/12/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 02/10/2015; Status: Approved; Inspector: eleibol1; Comment: Entered by ELEIBOL1 - } | |
| 02/11/2015 | ENGR Engineering Final | Passed | {Activity date: 01/12/2015; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - PROVIDE AS-BUILT DOCUMENTATION AND CERTIFICATION LETTER FROM THE ENGINEER OF RECORD. ADDRESS ALL PREVIOUS COMMENTS AND COMPLETE ALL WORK AS SHOWN ON THE APPROVED PLANS FOR THIS SITE.} ; {Activity date: 02/11/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 02/10/2015; Status: Approved; Inspector: eleibol1; Comment: Entered by ELEIBOL1 - RLS letter received 10FEB15.} | |
| 02/11/2015 | SITE - Stormwater Follow-up | Passed | {Activity date: 01/12/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 02/11/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 02/10/2015; Status: Approved; Inspector: eleibol1; Comment: Entered by ELEIBOL1 - Talked to Mike; okay to final after receiving surveyor's letter.} ; {Activity date: 09/09/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER COCNERNS AT THIS TIME} | |
| 02/11/2015 | ENGR Grading Final | Passed | {Activity date: 01/12/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 02/11/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 02/10/2015; Status: Approved; Inspector: eleibol1; Comment: Entered by ELEIBOL1 - As-builts reviewed and acceptable, talked to Mike; okay to final after receiving surveyor's letter.} ; {Activity date: 09/09/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) CONTRACTOR INSTALLING TWO 15" RCP ALONG ENTRACNCE TO LOT#4. 2) INVERT ELEVATION CLOSE TO PAD ELEVATION, 1.3' OF COVER MINIMUM PER PLAN. 3) 5'X5' ROCK RIP RAP PAD AT OUTLET TO CULVERT PIPES. 4) ENSURE EXISTING DRAINAGE CHANNEL DRAINS INTO PIPE 5) REVISED PLAN SHOWS ALL CHANGES MADE} |