Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 01/12/2015 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 02/10/2015 |
ENGR Grading Final |
eleibol1 |
Approved |
Entered by ELEIBOL1 - As-builts reviewed and acceptable, talked to Mike; okay to final after receiving surveyor's letter. |
| 09/09/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) CONTRACTOR INSTALLING TWO 15" RCP ALONG ENTRACNCE TO LOT#4.
2) INVERT ELEVATION CLOSE TO PAD ELEVATION, 1.3' OF COVER MINIMUM PER PLAN.
3) 5'X5' ROCK RIP RAP PAD AT OUTLET TO CULVERT PIPES.
4) ENSURE EXISTING DRAINAGE CHANNEL DRAINS INTO PIPE
5) REVISED PLAN SHOWS ALL CHANGES MADE |
| 01/12/2015 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 02/11/2015 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 02/10/2015 |
ENGR Grading Final |
eleibol1 |
Approved |
Entered by ELEIBOL1 - |
| 01/12/2015 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 02/11/2015 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 02/10/2015 |
ENGR Grading Final |
eleibol1 |
Approved |
Entered by ELEIBOL1 - |
| 01/12/2015 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 02/11/2015 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 02/10/2015 |
ENGR Grading Final |
eleibol1 |
Approved |
Entered by ELEIBOL1 - As-builts reviewed and acceptable, talked to Mike; okay to final after receiving surveyor's letter. |
| 09/09/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) CONTRACTOR INSTALLING TWO 15" RCP ALONG ENTRACNCE TO LOT#4.
2) INVERT ELEVATION CLOSE TO PAD ELEVATION, 1.3' OF COVER MINIMUM PER PLAN.
3) 5'X5' ROCK RIP RAP PAD AT OUTLET TO CULVERT PIPES.
4) ENSURE EXISTING DRAINAGE CHANNEL DRAINS INTO PIPE
5) REVISED PLAN SHOWS ALL CHANGES MADE |