Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
9105 E CAMINO ABRIL
Apply Date:
12/13/2013
Applicant:
Description:
SITE/GRADING- RITA RANCH

Permit Reviews

Permit Number - DP13-0248
Permit Status: Complete
Permit Description: SITE/GRADING- RITA RANCH
Start Date Submittal Complete Date Status  
09/10/2014 RESUB - SITE and/or GRADING 10/09/2014 COMPLETED Review Details
09/28/2015 REVISION - - 1ST 09/30/2015 COMPLETED Review Details
10/09/2014 RESUB - SITE and/or GRADING 09/28/2015 COMPLETED Review Details
12/13/2013 DEV PKG - OK TO SUBMIT 12/13/2013 COMPLETED Review Details
12/18/2013 SITE and/or GRADING 01/21/2014 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP13-0248
Permit Description: SITE/GRADING- RITA RANCH
Total Completed Inspections - 7
Date Description Inspector Results Comments
12/08/2014 SITE - Stormwater Setup and Controls Passed {Activity date: 12/08/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SITE IS LESS THAN ONE ACRE, NO SWPPP REQUIRED.
2) MUST KEEP SOIL ON SITE.
3) SEDIEMNT CONTROLS INSTALLED.
4) CALL FOR INSPECION FOR ANY CHANGES}
12/08/2014 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 12/08/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SITE IS LESS THAN ONE ACRE, NO SWPPP REQUIRED.
2) MUST KEEP SOIL ON SITE.
3) SEDIEMNT CONTROLS INSTALLED.
4) CALL FOR INSPECION FOR ANY CHANGES} ; {Activity date: 12/05/2014; Status: Cancelled; Inspector: MRUSSO; Comment: Entered by DROBERT5 - RAINING}
12/04/2015 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 12/04/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 04/07/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SOUTH SECTION OF SITE HAS BEEN STABILIZED WITH HYDROSEED
2) SEDIMENT CONTROLS IN PLACE AND MUST BE MAINTAINED}
12/04/2015 ENGR Engineering Final Passed {Activity date: 12/04/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 09/15/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - SEE NOTE #27 AN PAGE #1 ON APPROVED PLANS}
12/04/2015 SITE - Stormwater Follow-up Passed {Activity date: 12/04/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 10/22/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO CHANGES AT THIS TIME} ; {Activity date: 10/16/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVITY, NO CHANGES AND/OR CONCERNS AT THIS TIME} ; {Activity date: 10/07/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO CHANGES AND/OR CONCERNS AT THIS TIME} ; {Activity date: 10/02/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO CHANGES AND/ OR CONCERNS AT THIS TIME} ; {Activity date: 09/15/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 08/12/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 06/18/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME- NO ACTIVITY} ; {Activity date: 06/05/2015; Status: Continued; Inspector: MRUSSO1; Comment: Entered by DROBERT5 - NO CONSTRUCTION ACTIVITY AT THIS TIME} ; {Activity date: 05/08/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO CONSTRUCTION ACTIVITY AT THIS TIME
NO STORM WATER CONCERNS} ; {Activity date: 03/24/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by ARUIZ1 - 1. CONTRACTOR INSTALLING GABIONS ALONG CROSSING AT SE CORNER OF SITE
2. TOOK PICTURES OF ROCK RIP RAP WORK ALONG ALL DRAINAGES
3. STORM WTR PIPE INSTALLED HEAD WALL CONSTRUCTED} ; {Activity date: 03/06/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 03/04/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 03/03/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 02/10/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO STORM WATER/SITE CONCERNS AT THIS TIME} ; {Activity date: 02/02/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 01/22/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SEDIMENT CONTROLS HAVE BEEN INSTALLED ALONG THE EAST SIDE OF THE PROJECT PER THE APPROVED SWPPP AND THE PRE-CON INSPECTION RECOMMENDATIONS.
2) NOI IS POSTED AT THE ENTRANCE TO THE SITE
3) A STABILIZED CONSTRUCTION ENTRANCE HAS BEEN INSTALLED
4) SWEEP UP TRACKED SOIL OFF PUBLIC ROADWAYS
5) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED
6) MAY NEED TO ADD SEDIMENT CONTROLS ALONG THE DRAINAGE ON THE NORTH SIDE OF THE SITE}
12/04/2015 ENGR Grading Final Passed {Activity date: 12/04/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
12/04/2015 SITE - Stormwater Final Inspection Passed {Activity date: 12/04/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }

Documents

File Name Document Type  
001_COVER SHEET_1 OF 7.TIF DEVELOPMENT PACKAGE VIEW
002_DEVELOPMENT_2 OF 7.TIF DEVELOPMENT PACKAGE VIEW
003_PRIVATE PAVING / GRADING_3 OF 7.TIF DEVELOPMENT PACKAGE VIEW
004_DETAILS_4 OF 7.TIF DEVELOPMENT PACKAGE VIEW
005_LANDSCAPE_L-1.TIF DEVELOPMENT PACKAGE VIEW
006_WATER HARVESTING_L-2.TIF DEVELOPMENT PACKAGE VIEW
007_LANDSCAPE DETAILS_L-3.TIF DEVELOPMENT PACKAGE VIEW
None DOCUMENTS VIEW