Permit: DP12-0132
Permit Details
Apply Date:
08/09/2012
Applicant:
Lisa Bowers
Description:
PARK AVE HOUSINGOriginally approved 1/28/13Revision 1 approved 6/4/2013
Permit Reviews
Permit Number - DP12-0132
Permit Status: Complete
Permit Description: PARK AVE HOUSINGOriginally approved 1/28/13Revision 1 approved 6/4/2013
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/28/2013 | DEV PKG - RESUBMITTAL | 05/31/2013 | COMPLETED |
05/16/2014 | DEV PKG - REVISION | 06/11/2014 | COMPLETED |
06/04/2013 | REVISION - - 1ST | 05/16/2014 | COMPLETED |
06/11/2014 | DEV PKG - REVISION | 06/12/2014 | COMPLETED |
08/05/2014 | DEV PKG - REVISION | 11/10/2014 | COMPLETED |
08/09/2012 | DEV PKG - OK TO SUBMIT | 08/10/2012 | COMPLETED |
08/13/2012 | DEV PKG | 10/15/2012 | COMPLETED |
10/17/2012 | RESUBMITTAL - CDRC - DEV PLAN | 11/01/2012 | COMPLETED |
11/06/2012 | RESUBMITTAL - CDRC - DEV PLAN | 12/21/2012 | COMPLETED |
11/10/2014 | DEV PKG - REVISION | 11/10/2014 | ACTIVE |
12/21/2012 | DEV PKG - RESUBMITTAL | 01/28/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - DP12-0132
Permit Status: Complete
Permit Description: PARK AVE HOUSINGOriginally approved 1/28/13Revision 1 approved 6/4/2013
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/28/2013 | The following 20 conditions apply to DP12-0132:1)Call for Pre-construction meeting. For a PDSD Engineering Inspection, call IVR (740-6970), or schedule with a Customer Service Representative at Planning & Development Services Department (PDSD), or contact PDSD Engineering at 837-4888, or schedule inspections online at: http://cms3.tucsonaz.gov/pdsd/inspections2)Some grading or other construction activities will require separate special inspections by EOR or consultants. During these inspections it is recommended that PDSD Inspectors are present. Discuss during Pre-con or contact PDSD Engineering Inspector to confirm which inspections may be needed. 3)Project shall conform to recommendations and requirements found in geotechnical engineering report for this project and any subsequent addenda.4)Contractor is responsible to protect in place any existing utilities; all work within these easements must be coordinated with the proper utilities prior to any site construction. All recordation dkt/pg or sequence numbers shall be listed on subsequent plans for revisions or as-builts.5)A copy of stamped approved grading plan(s), permit(s), NOI, AzPDES general permit, geotechnical report/addenda, and other reports shall be kept at site at all times, until final grading approval.6)Disturbance Limits shall be maintained and no disturbance outside of approved project limits will be allowed. Stop Work Order may be issued if disturbance occurs outside of approved limits as shown on approved plans. There shall be no disturbance, construction vehicle traffic or parking, or stockpiling outside of approved limits as shown on approved plans.7)Interim erosion and sediment controls shall be maintained per approved grading plans at downstream areas of disturbance limits. Interim control measures shall be placed within approved project limits. Prior to final approval all temporary controls shall be removed and permanent controls shall be functioning in place.8)Stabilized entrances shall be maintained at all active access entrances. Use of water trucks or other dust controls shall be utilized, and construction entrances shall be maintained to minimize sedimentation, dust issues, and tracking.9)Any trees within SVT's shall be checked and trimmed to assure that they are clear of leaves and branches to a height of at least six feet above grade. Location of trees within existing and future sight visibility triangles may be restricted or modified as determined by City of Tucson Inspectors in order to preserve visibility.10)During construction activities, traffic control plans may be required if there is a safety hazard potential from construction activities conflicting with public traffic. It may be necessary to submit a copy of a traffic control plan to PDSD. Onsite traffic control plans shall minimize traffic hazard conditions between public access to buildings, and construction vehicles & activities. |
Conditions
Permit Number - DP12-0132
Permit Status: Complete
Permit Description: PARK AVE HOUSINGOriginally approved 1/28/13Revision 1 approved 6/4/2013
Date | Description | Comments |
---|---|---|
01/28/2013 | 11)Any revisions to Grading Plan sheets must be reviewed by PDSD Engineering Engineer and may include discussion, details, or a revised grading plan. Call PDSD Engineering Division at 791-5550 to discuss any revisions. Any revision shall include clarification of spot elevations and floodplain limits at west side of project to assure that proposed residential structure and location of portion of solid waste pick-up landing is outside of floodplain.12)If grading construction is expected to last longer than expiration date of permit, contact PDSD to renew/extend permit. If final grading inspection has not been completed before permit expires, and permit has not been renewed, additional fees and reviews may be required. Requests for permit extensions may be submitted to Planning & Development Services Department (attn: Claudia Buford), prior to permit expiration date, for consideration of grading plan extension approval.13)City of Tucson grading standards TSM Section 2 applies. 14)For inspection purposes, post City of Tucson's "AZPDES - Posting Requirements" green sheet, or the NOI at construction entrance of site, at beginning of construction activities, and maintain this posted document throughout project construction.15)Operator shall report to ADEQ any noncompliance (including spills) which may endanger human health or the environment. Operator shall orally notify office listed below within 24 hours:(a)Arizona Department of Environmental Quality1110 W. Washington, 5th floor (5515B-1)Phoenix, AZ 85007Office: 602-771-4466; Fax 602-771-450516)Receiving waters are West University Wash. Also the following water system is downstream: Santa Cruz River.17)Permitee shall notify PDSD when grading operation is ready for final grading inspection. Final grading approval shall not be given until all work, including installation of all drainage improvements and their permanent protective devices, and all erosion control measures have been completed in accordance with approved grading plan and grading permit, and all conditions of permit are completed. 18)Remaining signatures from Operators must be on site copy of SWPPP (exhibit or report) at or before commencement of construction. All Operators shall be identified and have separate certification statements. Assure these certifications are available on-site.19)After interim controls are removed, permanent erosion control are required on all disturbed areas, in form of vegetative cover, gravel, a sized decorative rock, and/or other controls.20)As-builts are required to be submitted. The as-built / "Final Revised Grading Plan" and substantial completion letter(s) may be submitted under activity number DP12-0132 to PDSD permit clerks. The documents will be reviewed and then if acceptable, a copy of the as-builts will be provided to PDSD Engineering Inspector for final grading inspections. For grading permit project closure documentation, submit: one copy of original grading plans, 2 copies of sheets that show as-built information, letters of completion (one for drainage improvements, and another letter for substantial completion of overall project). As-builts shall include: seal on sheets that show as-built data, pad elevations for parking structure and lowest finished floor at main level, inverts drainage pipes/systems, elevations around parking entry area showing elevations high enough to keep out jurisdictional floodplain, access easements near alley area as approved on PIA revision, and general grades as determined by RLS to show substantial completion for onsite and offsite improvements of project. |
Completed Inspections
Permit Status: Complete
Permit Number: DP12-0132
Permit Description: PARK AVE HOUSINGOriginally approved 1/28/13Revision 1 approved 6/4/2013
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/02/2013 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 04/02/2013; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - MET WITH SUPERINTENDENT ON SITE TO DISCUSS NEW TRASH ENCLOSURE. CONTRACTOR HAS BEEN WORKING ON SITE FOR A MONTH PRIOR TO CALLING FOR A GRADING/SITE/STORM WATER PRE-CON. PATRICK LINNENN WITH BEAL DERKENNE CONSTRUCTION 602-769-3167. CONTRACTOR DOES NOT HAVE A STORM WATER PERMIT OR PLAN HOWEVER MUST CONTINUE TO KEEP DISTURBED SOIL ON SITE. TRASH ENCLOSURE MUST HAVE BOLLARDS ALONG THE SIDES AND BACK AND HAVE A 10 X 10 CLEAR WIDTH WITH A 5 FOOT APRON AND GATES.} |
|
07/28/2014 | SITE - Stormwater Follow-up | Passed | {Activity date: 07/28/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 04/15/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICAT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 04/08/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} | |
08/05/2014 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 08/05/2014; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 01/08/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) LIMITED SITE WORK DUE TO THE FOOT PRINT OF THE BLDG. 2) MINIMAL SITE INSPECTIONS CALLED IN BY CONTRACTOR. 3) SITE IS LESS THAN 1 ACRE, THEREFORE NO SWPPP IS REQUIRED, HOWEVER DISTURBED SOIL MUST BE KEPT ON SITE DURING CONSTRUCTION. 4) ENSURE AN APPROVED SITE/GRADING/LANDSCAPE PLAN IS AVAILABLE ON SITE FOR A FINAL INSPECTION. 5) PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT ALL SITE GRADING WAS COMPLETED PER THE APPROVED PLAN. 6) ANY UNDERGROUD STORM DRAINAGE CAN NOT BE VERIFIED BY THE INSPECTOR AFTER INSTALLATION.} |
|
08/05/2014 | ENGR Grading Final | Passed | {Activity date: 08/05/2014; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
08/05/2014 | SITE - Stormwater Final Inspection | Passed | {Activity date: 08/05/2014; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
08/05/2014 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 08/05/2014; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
05/01/2018 | ENGR Engineering Final | Passed | {Activity date: 05/01/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 08/05/2014; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - COMPLETE ALL EXTERIOR WORK ON THIS SITE PRIOR TO SCHEDULING THIS INSPECTION.} ; {Activity date: 01/08/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) LIMITED SITE WORK DUE TO THE FOOT PRINT OF THE BLDG. 2) MINIMAL SITE INSPECTIONS CALLED IN BY CONTRACTOR. 3) SITE IS LESS THAN 1 ACRE, THEREFORE NO SWPPP IS REQUIRED, HOWEVER DISTURBED SOIL MUST BE KEPT ON SITE DURING CONSTRUCTION. 4) ENSURE AN APPROVED SITE/GRADING/LANDSCAPE PLAN IS AVAILABLE ON SITE FOR A FINAL INSPECTION. 5) PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT ALL SITE GRADING WAS COMPLETED PER THE APPROVED PLAN. 6) ANY UNDERGROUD STORM DRAINAGE CAN NOT BE VERIFIED BY THE INSPECTOR AFTER INSTALLATION.} |