Permit: DP12-0080
Permit Details
Status:
Complete
Type:
Development Package
Address:
6550 S MIDVALE PARK RD
Address NEW:
6550 S MIDVALE PARK RD
Apply Date:
05/29/2012
Applicant:
Kevin Petrick
Description:
DAIRY QUEEN
Permit Reviews
Permit Number - DP12-0080
Permit Status: Complete
Permit Description: DAIRY QUEEN
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/29/2012 | DEV PKG - OK TO SUBMIT | 05/29/2012 | COMPLETED |
| 05/29/2012 | DEV PKG | 08/24/2012 | COMPLETED |
| 08/24/2012 | DEV PKG - RESUBMITTAL | 08/30/2012 | COMPLETED |
| 08/30/2012 | DEV PKG - RESUBMITTAL | 09/18/2012 | COMPLETED |
| 09/18/2012 | DEV PKG - RESUBMITTAL | 09/21/2012 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP12-0080
Permit Description: DAIRY QUEEN
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/19/2012 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 12/19/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 12/18/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 12/19/2012 | SITE - SWPPP Correction Notice | Passed | {Activity date: 12/19/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 12/19/2012 | SITE - Stormwater Follow-up | Passed | {Activity date: 12/19/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 12/19/2012 | ENGR Grading Final | Passed | {Activity date: 12/19/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 12/19/2012 | SITE - SWPPP Violation Notice | Passed | {Activity date: 12/19/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 12/19/2012 | SITE - Stormwater Final Inspection | Passed | {Activity date: 12/19/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 12/19/2012 | COT - ENGR - Site - Assurance Release | Passed | {Activity date: 12/19/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 12/19/2012 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 12/19/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 12/20/2012 | ENGR Engineering Final | Passed | {Activity date: 12/20/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 12/20/2012 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 12/20/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 09/18/2012; Status: Continued; Inspector: jgreen; Comment: Entered by JGREEN2 - This project is proposing 2 columns for the drive thru canopy that are to be constructed adjacent to an existing concrete lined channel. Inspector needs to make sure that the construction of these columns do not cause adverse damage to the lined channel during constructing and that no sediment or debri is being added tot he wash. JG} |