Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
8702 E BROADWAY BL
Apply Date:
05/07/2012
Applicant:
Anthony Capps
Description:
BURGER KING

Permit Reviews

Permit Number - DP12-0066
Permit Status: Complete
Permit Description: BURGER KING
Start Date Submittal Complete Date Status  
05/07/2012 DEV PKG - OK TO SUBMIT 05/14/2012 COMPLETED Review Details
05/14/2012 SITE and/or GRADING 07/27/2012 COMPLETED Review Details
07/27/2012 RESUB - SITE and/or GRADING 08/17/2012 COMPLETED Review Details
08/17/2012 RESUB - SITE and/or GRADING 08/28/2012 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP12-0066
Permit Description: BURGER KING
Total Completed Inspections - 7
Date Description Inspector Results Comments
09/05/2012 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 09/05/2012; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) this site is not required to have a storm water permt, however the contractor must comply with the city of tucson's storm water permit by keeping disturbed soil on site and out of storm drains.
2) call for inspection for any changes and/or concerns with the approved grading and landscape plan.
3) may need to add supplemental sediment controls at a later time, (rock entrance, silt sock at catch basin....).}
11/02/2012 SITE - Stormwater Setup and Controls Passed {Activity date: 11/02/2012; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - SITE SPECIFIC SEDIMENT CONTROLS HAVE BEEN INBSTALLED AND APPROVED}
12/17/2012 SITE - Stormwater Follow-up Passed {Activity date: 12/17/2012; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - SITE PAVED} ; {Activity date: 12/12/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - SITE BEING PAVED TODAY
NO CHANGES AND/OR COCNERNS AT THIS TIME
NO STORM WATER CONCERNS} ; {Activity date: 12/11/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO CHANGES AND/OR CONCERNS AT THIS TIME

SITE PAVING BEING DONE WILL CHECK NXT WEEK} ; {Activity date: 11/16/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SOME SITE WORK BEING DONE.
2) CURB CUTS FOR SURFACE DRAINAGE, SCUPPERS FOR ROOF DRAINS, AND WATER HARVESTING AREA'S FOR INFILTRATION AND LANDSCAPING.
3) NO GRADING CONCERNS AT THIS TIME. PAVING IN TWO WEEKS.
4) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.} ; {Activity date: 11/02/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) NO SITE WORK BEING DONE YET
2) NO STORM WATER CONCERNS AT THIS TIME
3) TRASH ENCLOSURE HAS BEEN CONSTRUCTED} ; {Activity date: 10/31/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) NO SIGNIFICANT STORMWATER CONCERNS AT THIS TIME.
2) CONTRACTOR INSTALLING UTILITIES AND BLDG PAD. NO SITE WORK AT THIS TIME} ; {Activity date: 09/19/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 09/11/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
2) GRADING FOR BLDG PAD AT THIS TIME.} ; {Activity date: 09/10/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.}
12/17/2012 ENGR Grading Final Passed {Activity date: 12/17/2012; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 12/13/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - PAVING TAKING PLACE, NO CHANGES OR CONCERNS AT THIS TIME} ; {Activity date: 12/12/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - SITE BEING PAVED TODAY
NO CHANGES AND/OR COCNERNS AT THIS TIME
NO STORM WATER CONCERNS} ; {Activity date: 12/11/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO CHANGES AND/OR CONCERNS AT THIS TIME

SITE PAVING BEING DONE WILL CHECK NXT WEEK} ; {Activity date: 11/27/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO CONCERNS AND OR CHANGES} ; {Activity date: 11/16/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SOME SITE WORK BEING DONE.
2) CURB CUTS FOR SURFACE DRAINAGE, SCUPPERS FOR ROOF DRAINS, AND WATER HARVESTING AREA'S FOR INFILTRATION AND LANDSCAPING.
3) NO GRADING CONCERNS AT THIS TIME. PAVING IN TWO WEEKS.
4) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.} ; {Activity date: 11/15/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 10/31/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) NO SIGNIFICANT STORMWATER CONCERNS AT THIS TIME.
2) CONTRACTOR INSTALLING UTILITIES AND BLDG PAD. NO SITE WORK AT THIS TIME} ; {Activity date: 09/19/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - REBAR PLACED PER APPROVED PLANS AND DEV STD 6 -01.0 FOR THE TRASH ENCLOSURE. TWO #4 IN BOTTOM AND ONE VERT @ 32" ON CENTER.} ; {Activity date: 09/11/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
2) GRADING FOR BLDG PAD AT THIS TIME.}
12/17/2012 SITE - Stormwater Final Inspection Passed {Activity date: 12/17/2012; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
12/19/2012 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 12/19/2012; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 12/17/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - LANDSCAPING NOT COMPLETED PER PLAN}
12/19/2012 ENGR Engineering Final Passed {Activity date: 12/19/2012; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 12/17/2012; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - COMPLETE ALL SITE WORK PER APPROVED PLAN}