Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address:
601 W 22ND ST
Address NEW:
601 W 22ND ST
Apply Date:
03/01/2012
Applicant:
Description:
RESTAURANT DEPOT

Permit Reviews

Permit Number - DP12-0023
Permit Status: Complete
Permit Description: RESTAURANT DEPOT
Start Date Submittal Complete Date Status  
03/01/2012 DEV PKG - OK TO SUBMIT (SITE) 03/05/2012 COMPLETED Review Details
03/05/2012 SITE 05/17/2012 COMPLETED Review Details
05/17/2012 RESUB - SITE and/or GRADING 06/05/2012 COMPLETED Review Details
06/05/2012 RESUB - SITE and/or GRADING 06/08/2012 COMPLETED Review Details
08/31/2012 REVISION - SITE 08/31/2012 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP12-0023
Permit Description: RESTAURANT DEPOT
Total Completed Inspections - 11
Date Description Inspector Results Comments
06/20/2012 SITE - Stormwater Setup and Controls Passed {Activity date: 06/20/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
06/20/2012 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 06/20/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - COMPLET HAND OUT AND CALL BACK .}
11/07/2012 Final inspection to ensure all landscape and water harvesting SITE Passed {Activity date: 11/07/2012; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
11/07/2012 SITE - SWPPP Correction Notice Passed {Activity date: 11/07/2012; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 07/06/2012; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - ALL DRIVEWAYS GAVE BEEN CLEANED AT THIS TIME.} ; {Activity date: 07/05/2012; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - MINOR TRACK OUT NOTED ON THE EAST SIDE OF THE PROJECT. THE PRIME CONTRACTOR WILL NOTIFY EAGLE ROCK WHEN THEY RETURN TO ORDER SWEEPER SERVICE FOR THE AFFECTED STREETS.} ; {Activity date: 06/28/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 06/28/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GOT WITH CONTRACTOR TO ADD TRACK OUT ROCK AND CEAN AND KEEP STREET CLEAN. HAVE PHOTOS.}
11/07/2012 SITE Passed {Activity date: 11/07/2012; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
11/07/2012 PDSD Site/Engineering Division - NPPO Passed {Activity date: 11/07/2012; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
11/07/2012 ENGR Grading Final Passed {Activity date: 11/07/2012; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 08/23/2012; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - CREWS WORKING ON PLACING THE EXTERIOR MATERIAL ON THE WEST SIDE OF THE BUILDING, THEY HAVE ALSO STARTED ON THE EAST SIDE OF THE BUILDING. A CREW IS TRENCHING FOR DRAINAGE PIPE AND IS PLACING SOME OF THE 12 INCH HDPE PIPE AT THE NORTH WEST SIDE OF THE SITE. MINOR MODIFICATIONS MAY HAVE TO BE MADE TO THE LAYOUT DUE TO FOOTERS THAT HAVE ALREADY BEEN POURED ON THE NORTHSIDE OF THE BUILDING, THESE WILL BE NOTED IN THE AS-BUILT DRAWINGS AS NEEDED.} ; {Activity date: 08/16/2012; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - WALKED THE SITE WITH THE CONTRACTOR AND LOOKED AT THE CURRENT WORK THAT THEY ARE PEROFRMING. CURRENTLY THEY ARE INSTALLING SOME OF THE DRAINAGE PIPE LOCATED IN THE SOUTHWEST CORNER OF THE SITE, THIS WILL BE BACKFILLED TODAY. ADDITIONAL PIPES WILL BE PLACE LATER THIS WEEK AND NEXT WEEK AND WILL BE SCHEDULED FOR INSPECTION AS THEY ARE NEEDED. ALSO CREWS CONTINUE TO WORK ON INSTALLING THE SUPPORTING STRUCTURES OF THE SITE AND ARE ANTICIPATING BEING ABLE TO START SKINNING THE BUILDING FRAME WITHIN THE NEXT 2 WEEKS. THE CONTRACTOR SAYS THAT HE WILL BE ASKING FOR HIS FINAL INSPECTIONS EITHER THE LAST WEEK OF SEPTEMBER OR THE FIRST WEEK OF OCTOBER. I HAVE REMINDED THEM THAT THERE IS STILL AN ISSUE WITH THE REMOVAL OF THE BILLBOARD FROM THIS SITE AS SHOWN ON THE APPROVED SET OF PLANS, AND IF THIS WORK HAS NOT BEEN COMPLETED BY THE TIME THAT THEY ARE CALLING IN THEIR FINAL INSPECTIONS THAT I MIGHT HAVE TO DENIE THE APPROVALS UNTIL THE BILLBOARD IS REMOVED. HE WILL BE HAVING A MEETING WITH THE OWNER THIS AFTER AND WILL BRING THAT ISSUE TO HIS ATTENTION TO MAKE SURE THAT THEY ARE AWARE OF PROBLEMS WITH FUTURE REQUEST FOR FINAL RELEASES.}
04/21/2017 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 04/21/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 04/02/2013; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - STILL WAITING FOR THE DEVELOPER TO CALL THIS SITE IN FOR THE FINAL INSPECTION.} ; {Activity date: 11/07/2012; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - WALKED THE SITE THE LANDSCAPE ITEMS HAVE NOT BEEN COMPLETED AT THIS TIME, THESE WILL BE RECHECKED NEXT WEEK.}
04/21/2017 SITE - Stormwater Follow-up Passed {Activity date: 04/21/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 11/07/2012; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME.} ; {Activity date: 08/23/2012; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME.} ; {Activity date: 08/16/2012; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME.} ; {Activity date: 08/01/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.} ; {Activity date: 07/24/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERN AT THIS TIME.} ; {Activity date: 07/20/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NEW ROCK WAS ADDED AT ENTRRANCE NO TRACK OUT AT THIS TIME.} ; {Activity date: 07/18/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.} ; {Activity date: 07/05/2012; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - MET WITH THE CONTRACTOR AND DISCUSSED THE MINOR TRACKOUT THAT HAS BEEN NOTED. THEY WILL ASK EAGLE ROCK TO ORDER A SWEEPER ONCE THEY RETURN ON EITHER 7/6/2012 OR 7/9/2012. I WILL GET WITH RON AND PICKUP THE PLANS FOR THIS SITE SO THAT I CAN START WATCHING THE SITE FROM THIS DATE FORWARD.} ; {Activity date: 06/29/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - STREETS ARE BEING CLEANED.} ; {Activity date: 06/26/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PICKED UP INFO PACKET.}
06/10/2020 ENGR Engineering Final Passed {Activity date: 06/10/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 04/21/2017; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DROBERT5 - PROVIDE THE AS-BUILT/REVISED DRAWINGS FOR ALL THE CHANGES MADE TO THIS SITE, AND A CERTIFICATION LETTER FROM THE ENGINEER OF RECORD PRIOR TO SCHEDULING THE FINAL INSPECTION FOR THIS SITE.} ; {Activity date: 04/02/2013; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - WAITING FOR THE CONTRACTOR TO COMPLETE ALL THE WORK ON THE APPROVED PLANS OR TO PROVIDE AN APPROVED SET OF REVISED DRAWINGS FOR THE FINAL INSPECTION.} ; {Activity date: 04/02/2013; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - CHECKED THE SITE TOO SEE IF ALL THE WORK HAD BEEN COMPLETED AT THIS TIME.}
06/10/2020 SITE - Stormwater Final Inspection Passed {Activity date: 06/10/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 04/21/2017; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DROBERT5 - PROVIDE THE NOTICE OF TERMINATION FROM ADEQ FOR THIS SITE FOR THE FINAL CLOSURE} ; {Activity date: 11/07/2012; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DROBERT5 - COMPLETE ALL LANDSCAPING AND BASINS ON THIS SITE PRIOR TO SCHEDULING THIS INSPECTION.}

Documents

File Name Document Type  
001_COVER SHEET_1.TIF DEVPLANS VIEW
002_GENERAL NOTES_1A.TIF DEVPLANS VIEW
003_EXISTING CONDITION_2.TIF DEVPLANS VIEW
004_SITE_3.TIF DEVPLANS VIEW
005_EMERGENCY & SERVICE VEHICLE ACCESS_4.TIF DEVPLANS VIEW
006_GRADING_5.TIF DEVPLANS VIEW
007_RAINWATER HARVESTING_5A.TIF DEVPLANS VIEW
008_SITE MAP-SWPP NOTES_5B.TIF DEVPLANS VIEW
009_SITE MAP-SWPP_5C.TIF DEVPLANS VIEW
010_SITE MAP-SWPP PLAN DETAILS_5D.TIF DEVPLANS VIEW
011_UTILITY_6.TIF DEVPLANS VIEW
012_LANDSCAPE_7.TIF DEVPLANS VIEW
013_LANDSCAPE DETAILS_8.TIF DEVPLANS VIEW
014_IRRIGATION_8A.TIF DEVPLANS VIEW
015_IRRIGATION DETAILS_8B.TIF DEVPLANS VIEW
016_IRRIGATION DETAILS_8C.TIF DEVPLANS VIEW
017_DETAILS_9.TIF DEVPLANS VIEW
018_DETAILS_10.TIF DEVPLANS VIEW
019_DETAILS & SECTIONS_11.TIF DEVPLANS VIEW
None DOCUMENTS VIEW
CASH BOND 2012_06_08.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW