Inspection Status: Passed
Inspection History: TRSP - PIA - Roadway Subgrade
| Date |
Description |
Inspector |
Results |
Comments |
| 04/01/2025 |
TRSP - PIA - Roadway Subgrade |
|
Passed |
|
| 04/02/2025 |
TRSP - PIA - Roadway Subgrade |
|
Passed |
Proctor should be attained by target date of 4/7 when forms will be placed in preparation to pour curbs. |
| 04/04/2025 |
TRSP - PIA - Roadway Subgrade |
|
Passed |
|
| 04/22/2025 |
TRSP - PIA - Roadway Subgrade |
|
Passed |
After a re-test at the end of the day, we were able to get a passing test >95% between driveway C and D at station 22+50. |
| 04/22/2025 |
TRSP - PIA - Roadway Subgrade |
|
Passed |
Subgrade did not pass due to low density and moisture. Even though we had run the string line test from driveway C to D, and it was good, the low density negatively affects the ability of the project to move forward. |
| 04/25/2025 |
TRSP - PIA - Roadway Subgrade |
|
Passed |
Subgrade passed on Thursday, April 24th. with >95% compaction. |
| 05/28/2025 |
TRSP - PIA - Roadway Subgrade |
|
Passed |
Roadway subgrade has been completed. |
| 06/09/2025 |
TRSP - PIA - Roadway Subgrade |
|
Passed |
Roadway subgrade has been completed and paved. |
| 11/04/2025 |
TRSP - PIA - Roadway Subgrade |
|
Canceled |
|