Parcel: 14044004C

Inspection Status: Passed

Inspection History: TRSP - PIA - Sidewalk Placement

Permit Number - TR-PIA-1122-00001

Inspection Description - TRSP - PIA - Sidewalk Placement

Inspection Status - Passed

Date Description Inspector Results Comments
04/21/2025 TRSP - PIA - Sidewalk Placement Passed Compaction tests did not pass due to low density and low moisture. Concrete is cancelled for next day.
04/22/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk area was re-tested for compaction and did not pass. Subgrade is low in moisture and compaction from the light at Alvernon and Los Reales up to driveway B.
04/23/2025 TRSP - PIA - Sidewalk Placement Passed A one-point proctor was taken at the site of sidewalk to be placed and resulted in a 127 optimum density and 9% optimum moisture. With this proctor, the sidewalk subgrade at 6” nuclear test did not pass again. Contractor was going to reprocess the area, use a sheep’s foot and added moisture to test the following day.
04/24/2025 TRSP - PIA - Sidewalk Placement Passed Multiple density tests were taken over three days to reach an acceptable density (94%). Much compaction effort was placed to do so due to the type of soil in the area.
04/25/2025 TRSP - PIA - Sidewalk Placement Passed 20 yards of approved concrete was poured between stations 10+00 and 12+00.
04/25/2025 TRSP - PIA - Sidewalk Placement Passed Sub grade at station 17+00 between driveways B & C passed with >95% compaction.
04/28/2025 TRSP - PIA - Sidewalk Placement Passed 21 yards of concrete for sidewalk poured between stations 12+00 and 14+25.
04/29/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk inspection station 10+00 to 14+00 and form inspection from stations 15+00 to 19+65.
04/30/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk was poured between stations 15+00 and 18+30. 20 yards were poured. Sample cylinders were taken on site.
04/30/2025 TRSP - PIA - Sidewalk Placement Passed Subgrade tested for compaction/density and passed both areas with >95% (between stations 19+00 & 22+25 as well as 23+00 & 26+00.)
05/01/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk was poured between stations 19+00 and 22+50. 30 yards were poured.
05/06/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk inspection for two sections, between stations 15+ & 18+50 as well as stations 19+10 & 22+50. Slopes are within plan specifications of 1.5%.
05/07/2025 TRSP - PIA - Sidewalk Placement Passed ADA ramps pour at driveways B, C, and D (total 6)
05/08/2025 TRSP - PIA - Sidewalk Placement Passed ADA ramps have been reworked in order to follow and comply to 2015 PAG standards.
05/09/2025 TRSP - PIA - Sidewalk Placement Passed Site inspection results in no PIA work being done today. ADA ramps have been reworked and ready for pour on Monday.
05/12/2025 TRSP - PIA - Sidewalk Placement Passed Re-pour of ADA ramps. Four are being poured today and the other four the next day. Started on driveways B and C. Samply cylinders were taken.
05/16/2025 TRSP - PIA - Sidewalk Placement Passed No work on site today
05/19/2025 TRSP - PIA - Sidewalk Placement Passed ADA ramp inspection for all ramps located at driveways B, C, and D.
05/23/2025 TRSP - PIA - Sidewalk Placement Passed Site Inspection of sidewalk and ADA ramps between driveways D and E.
05/27/2025 TRSP - PIA - Sidewalk Placement Passed Site Inspection - sidewalk between driveways D and E is still not poured along with two ADA ramps.
05/29/2025 TRSP - PIA - Sidewalk Placement Passed Site Inspection - turndown sidewalk ready to be poured but no date given yet.
05/30/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk between driveways D and E is still sitting ready to be poured along with the ADA ramps at driveway E.
06/04/2025 TRSP - PIA - Sidewalk Placement Passed Site Inspection - No PIA work - sidewalk and ADA ramps between driveways D and E are still waiting to be poured.
06/05/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk and ADA ramps still pending between driveways D and E.
06/06/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk site inspection. No PIA work being done on site today. Sidewalk subgrade and ADA ramps are ready to be poured. No date has been given.
06/09/2025 TRSP - PIA - Sidewalk Placement Passed Still waiting on sidewalk between driveways D and E and ADA ramps at driveway E.
06/10/2025 TRSP - PIA - Sidewalk Placement Passed Foreman said sidewalk is to be scheduled for pour sometime this week.
06/12/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk between driveways D and E need some attention before being poured. ADA ramps will need touch ups as well. Areas have been prepared for over a month now.
06/13/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk not ready to be poured.
06/16/2025 TRSP - PIA - Sidewalk Placement Passed No PIA work being done. Sidewalk section between driveways D and E still waiting. ADA ramps on driveway E are formed but not poured.
06/19/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk between driveways D and E still has not been poured. ADA ramps at Driveway E are formed but have not been poured.
06/23/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk between driveways D and E is still not poured. ADA ramps at driveway E are still formed but not poured.
06/24/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk between driveways D and E still isn’t poured. ADA ramps at driveway E are still on hold as well.
06/25/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk section between driveways D and E is not ready to be poured.
06/26/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk section between driveways D and E were being looked at by subcontractor. No definitive date has been given yet for pour.
06/27/2025 TRSP - PIA - Sidewalk Placement Passed Sidewalk section between driveways D and E will not be poured today. ADA ramps at driveway E are formed but not being poured today
07/09/2025 TRSP - PIA - Sidewalk Placement Passed Forms are set and trenching is being done for a "turndown" sidewalk with trenches at minimum 15". This is a redline the engineer put in place due to a low spot or possible "flood plain" area.
07/10/2025 TRSP - PIA - Sidewalk Placement Passed CalPortland delivered 50 yds of concrete to pour ADA ramp and sidewalk between driveways D and E. Sample test cylinders were taken.
07/14/2025 TRSP - PIA - Sidewalk Placement Passed ADA ramp on the W side of driveway E conforms to ADA specifications as well as PAG standards and specifications. Slopes are within <2%. Truncated domes are installed and are in solid with no hollow spots.
08/20/2025 TRSP - PIA - Sidewalk Placement Passed Measured for slope percentages, and landings as well as transition pieces and sidewalk cross slopes were within the specifications. Truncated domes were also void of any hollow spots.
11/04/2025 TRSP - PIA - Sidewalk Placement Canceled