Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: TRSP - PIA - Sidewalk Placement
Permit Number - TR-PIA-1122-00001
Inspection Description - TRSP - PIA - Sidewalk Placement
Inspection Status - Passed
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/21/2025 | TRSP - PIA - Sidewalk Placement | Passed | Compaction tests did not pass due to low density and low moisture. Concrete is cancelled for next day. | |
| 04/22/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk area was re-tested for compaction and did not pass. Subgrade is low in moisture and compaction from the light at Alvernon and Los Reales up to driveway B. | |
| 04/23/2025 | TRSP - PIA - Sidewalk Placement | Passed | A one-point proctor was taken at the site of sidewalk to be placed and resulted in a 127 optimum density and 9% optimum moisture. With this proctor, the sidewalk subgrade at 6” nuclear test did not pass again. Contractor was going to reprocess the area, use a sheep’s foot and added moisture to test the following day. | |
| 04/24/2025 | TRSP - PIA - Sidewalk Placement | Passed | Multiple density tests were taken over three days to reach an acceptable density (94%). Much compaction effort was placed to do so due to the type of soil in the area. | |
| 04/25/2025 | TRSP - PIA - Sidewalk Placement | Passed | 20 yards of approved concrete was poured between stations 10+00 and 12+00. | |
| 04/25/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sub grade at station 17+00 between driveways B & C passed with >95% compaction. | |
| 04/28/2025 | TRSP - PIA - Sidewalk Placement | Passed | 21 yards of concrete for sidewalk poured between stations 12+00 and 14+25. | |
| 04/29/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk inspection station 10+00 to 14+00 and form inspection from stations 15+00 to 19+65. | |
| 04/30/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk was poured between stations 15+00 and 18+30. 20 yards were poured. Sample cylinders were taken on site. | |
| 04/30/2025 | TRSP - PIA - Sidewalk Placement | Passed | Subgrade tested for compaction/density and passed both areas with >95% (between stations 19+00 & 22+25 as well as 23+00 & 26+00.) | |
| 05/01/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk was poured between stations 19+00 and 22+50. 30 yards were poured. | |
| 05/06/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk inspection for two sections, between stations 15+ & 18+50 as well as stations 19+10 & 22+50. Slopes are within plan specifications of 1.5%. | |
| 05/07/2025 | TRSP - PIA - Sidewalk Placement | Passed | ADA ramps pour at driveways B, C, and D (total 6) | |
| 05/08/2025 | TRSP - PIA - Sidewalk Placement | Passed | ADA ramps have been reworked in order to follow and comply to 2015 PAG standards. | |
| 05/09/2025 | TRSP - PIA - Sidewalk Placement | Passed | Site inspection results in no PIA work being done today. ADA ramps have been reworked and ready for pour on Monday. | |
| 05/12/2025 | TRSP - PIA - Sidewalk Placement | Passed | Re-pour of ADA ramps. Four are being poured today and the other four the next day. Started on driveways B and C. Samply cylinders were taken. | |
| 05/16/2025 | TRSP - PIA - Sidewalk Placement | Passed | No work on site today | |
| 05/19/2025 | TRSP - PIA - Sidewalk Placement | Passed | ADA ramp inspection for all ramps located at driveways B, C, and D. | |
| 05/23/2025 | TRSP - PIA - Sidewalk Placement | Passed | Site Inspection of sidewalk and ADA ramps between driveways D and E. | |
| 05/27/2025 | TRSP - PIA - Sidewalk Placement | Passed | Site Inspection - sidewalk between driveways D and E is still not poured along with two ADA ramps. | |
| 05/29/2025 | TRSP - PIA - Sidewalk Placement | Passed | Site Inspection - turndown sidewalk ready to be poured but no date given yet. | |
| 05/30/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk between driveways D and E is still sitting ready to be poured along with the ADA ramps at driveway E. | |
| 06/04/2025 | TRSP - PIA - Sidewalk Placement | Passed | Site Inspection - No PIA work - sidewalk and ADA ramps between driveways D and E are still waiting to be poured. | |
| 06/05/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk and ADA ramps still pending between driveways D and E. | |
| 06/06/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk site inspection. No PIA work being done on site today. Sidewalk subgrade and ADA ramps are ready to be poured. No date has been given. | |
| 06/09/2025 | TRSP - PIA - Sidewalk Placement | Passed | Still waiting on sidewalk between driveways D and E and ADA ramps at driveway E. | |
| 06/10/2025 | TRSP - PIA - Sidewalk Placement | Passed | Foreman said sidewalk is to be scheduled for pour sometime this week. | |
| 06/12/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk between driveways D and E need some attention before being poured. ADA ramps will need touch ups as well. Areas have been prepared for over a month now. | |
| 06/13/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk not ready to be poured. | |
| 06/16/2025 | TRSP - PIA - Sidewalk Placement | Passed | No PIA work being done. Sidewalk section between driveways D and E still waiting. ADA ramps on driveway E are formed but not poured. | |
| 06/19/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk between driveways D and E still has not been poured. ADA ramps at Driveway E are formed but have not been poured. | |
| 06/23/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk between driveways D and E is still not poured. ADA ramps at driveway E are still formed but not poured. | |
| 06/24/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk between driveways D and E still isn’t poured. ADA ramps at driveway E are still on hold as well. | |
| 06/25/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk section between driveways D and E is not ready to be poured. | |
| 06/26/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk section between driveways D and E were being looked at by subcontractor. No definitive date has been given yet for pour. | |
| 06/27/2025 | TRSP - PIA - Sidewalk Placement | Passed | Sidewalk section between driveways D and E will not be poured today. ADA ramps at driveway E are formed but not being poured today | |
| 07/09/2025 | TRSP - PIA - Sidewalk Placement | Passed | Forms are set and trenching is being done for a "turndown" sidewalk with trenches at minimum 15". This is a redline the engineer put in place due to a low spot or possible "flood plain" area. | |
| 07/10/2025 | TRSP - PIA - Sidewalk Placement | Passed | CalPortland delivered 50 yds of concrete to pour ADA ramp and sidewalk between driveways D and E. Sample test cylinders were taken. | |
| 07/14/2025 | TRSP - PIA - Sidewalk Placement | Passed | ADA ramp on the W side of driveway E conforms to ADA specifications as well as PAG standards and specifications. Slopes are within <2%. Truncated domes are installed and are in solid with no hollow spots. | |
| 08/20/2025 | TRSP - PIA - Sidewalk Placement | Passed | Measured for slope percentages, and landings as well as transition pieces and sidewalk cross slopes were within the specifications. Truncated domes were also void of any hollow spots. | |
| 11/04/2025 | TRSP - PIA - Sidewalk Placement | Canceled |