Permit: TR-PIA-1122-00001

Parcel: 14044004C

Inspection Status: Passed

Inspection History: TRSP - PIA - Drainage - Pipe Installation/Removal

Date Description Inspector Results Comments
07/29/2025 TRSP - PIA - Drainage - Pipe Installation/Removal Passed Headwall for triple barrel RCP drainage. Rebar inspection for floor.
07/30/2025 TRSP - PIA - Drainage - Pipe Installation/Removal Re-inspection required Rescheduled pour due to not having approved mix on site. BF was going to pre-mix on site.
07/31/2025 TRSP - PIA - Drainage - Pipe Installation/Removal Passed Sample cylinders taken for three barrel drainage head wall base
08/06/2025 TRSP - PIA - Drainage - Pipe Installation/Removal Passed Rebar inspection for headwall was done on site at triple barrel drainage along Alvernon just S of Los Reales. #4 rebar was used, spacing was at 8" for 4 foot header wall. One 90 degree bend in the structure. All rebar was in good shape and tied together with metal wire to keep in place and secure.
08/13/2025 TRSP - PIA - Drainage - Pipe Installation/Removal Passed Epoxy inspection on Fresno Valves installed on the south side of the RCP pipes. Three in total. Have been installed and functioning properly.
11/04/2025 TRSP - PIA - Drainage - Pipe Installation/Removal Canceled