| 04/07/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
Inspection for compaction rescheduled for Tuesday, April 8th at 7 AM. |
| 04/08/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
|
| 04/09/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
|
| 04/10/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
|
| 04/11/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
10.5 yards of concrete was poured for curb between stations 22+00 and 26+00. |
| 04/14/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
Team is curb forming at stations 14+00 to 15+25 at the very beginning of the stretch and the very end at stations 27+00 to 30+00. Foreman said concrete pour will take place Tuesday, April 15th for this stretch. |
| 04/15/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
Curb and driveway returns for driveway B were poured (8 yds). Includes curb and gutter matching existing. |
| 04/16/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
Curb forming and curb driveway returns being formed between stations 23+00 and 29+00. |
| 04/17/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
8 yds of concrete were poured for curb returns at driveway C, D, and west side of E. |
| 04/18/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
8 yards of concrete were poured between stations 26+75 and 29+29. |
| 05/28/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
Site Inspection resulted in no PIA work being done today. Sidewalk and ADA ramps still needed between driveways D and E. |
| 06/09/2025 |
TRSP - PIA - Curb Placement |
|
Passed |
All curb placement has been completed. |
| 11/04/2025 |
TRSP - PIA - Curb Placement |
|
Canceled |
|