Inspection Status: Partial Pass
Inspection History: FCON – OH Piping & Hydro
| Date |
Description |
Inspector |
Results |
Comments |
| 06/14/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
Ok to drywall units D02, D03, D04, 217,317. |
| 07/22/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
2nd Floor Oh/Hydro. 210psi. |
| 07/30/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
2nd and 3rd floor trash chutes ok to cover. |
| 08/09/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
OK to drywall rooms, missing head in hallway and mechanical room in hallway missing head. |
| 08/26/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
OH/Hydro 4th Floor. 200psi. |
| 09/17/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
Floors 5, 1 and 1.5 are approved. |
| 09/24/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
Floor 6 approved. |
| 10/04/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
7th floor approved. |
| 10/23/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
8th floor approved. |
| 10/28/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
Unit 101 approved |
| 11/06/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
9th floor approved. |
| 11/15/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
10th floor approved. 10.5 elevator lobby ok to hard lid. |
| 12/11/2024 |
FCON – OH Piping & Hydro |
|
Partial Pass |
Floor 10.5 units 1132,1131,1134,1133 and bathrooms approved. |
| 05/08/2025 |
FCON – OH Piping & Hydro |
|
Passed |
|