Inspection History Details
Inspection Status: Partial Pass
Inspection History: SITE - Sign Footer/Setback/Excavation Layout/Rebar
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/30/2025 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Partial Pass | 7/30/25 I looked at Two light pole footings. One next to refuse enclosures and one at east side of entrance at 22nd. Both are built to plan. Detail T13 in Structural Drawings. |
|
| 09/12/2025 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Partial Pass | 4 2.5 x 2.5 x 1’ footers for Ramada on N Side. Reinforcing correct. Okay to pour footers. | |
| 09/17/2025 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Partial Pass | 9/17/25 Three light pole footers at Northeast of building. Reinforcing and footer dimensions correct to plan. Grounds good. OK to pour these three pole footers. |
|
| 09/22/2025 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Not Ready | Rained out on Friday. | |
| 09/29/2025 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Partial Pass | 9/29/25 Pony wall at dog park at dog park in rear of building. Bond Beam and reinforcement correct. OK to grout and finish wall. Pony wall at west of front entrance. Bon beam and horizontal reinforcement good OK to grout this pony wall. West wall except for last 75 feet to South side next pony wall at front entrance. This 75 feet is not ready for grout. First lift North of this point is built, horizontal reinforcing correct. Okay to grout first lift request pre-grout inspection when Bond Beam is ready at top. |
|
| 11/06/2025 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Partial Pass | 11/6/25 4' Pony wall footer. Details in Arch Plan. Radius at South end of parking lot. 1-4" wide x 12" 2 continuous bars. Remove any loose dirt and dirt less than 3 inches from rebar. Verts at 48 oc. Okay to pour footer. Request pregrout inspection when bond beam is ready. Also, OK to pour remaining sidewalk ramp forms have all been checked for correct slopes and compaction is good. |
|
| 12/03/2025 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | Passed | 12/3/25 Pre-grout wall inspection. Half wall south of building that separates driveway from building. Reinforcing correct. Wall will be grouted solid. Vibrate all grout. Okay to grout this wall |