Inspection History Details
Inspection Status: Not Ready
Inspection History: For trash and recycling enclosures
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/20/2026 | For trash and recycling enclosures | Not Ready | Doors need to close better. There is a padlock hasp that is keeping both from closing correctly and 1” pipe needs to be in place in 4 spots where cane bolt can slide down to hold doors in position. | |
| 02/04/2026 | For trash and recycling enclosures | Passed | ||
| 06/09/2025 | For trash and recycling enclosures | Partial Pass | Okay to pour wall footers. | |
| 06/23/2025 | For trash and recycling enclosures | Partial Pass | 6/23/25 Both Refuse Enclosures are built 2.5 courses up with a #5 bond beam. Reinforcing is correct. Good to grout bond beam. Vibrate all grout. | |
| 06/26/2025 | For trash and recycling enclosures | Partial Pass | 6/26/25 Both refuse enclosure walls are about 5'. Reinforcing correct. Okay to pour grout. Vibrate all reinforced cells. After grout is poured do not build walls past 6ft. I need to resolve issue about wall height discrepancy with my supervisor. This will be resolved soon. |
|
| 07/08/2025 | For trash and recycling enclosures | Partial Pass | 7/7/25 Okay to grout bond beam at top of walls. Call in rebar inspection for refuse enclosure floors when ready. |
|
| 07/30/2025 | For trash and recycling enclosures | Partial Pass | 7/30/25 Rebar for slabs is correct. #4 ew. 3" clear. Compaction good Slope is correct, clearances are good. Okay to pour both floors/aprons |