Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2025 | Partial Pass | Contractor can grout the last 4 foot of the wall on the north end of the project grouted 150 lineal feet of the wall | ||
| 04/15/2025 | Canceled | |||
| 06/02/2025 | Partial Pass | 6/2/25 East parking wall footer approx 225 LF then tuns corner heads east for another 60 LF Footer dimensions and reinforcement are correct to plan. Okay to pour footer. |
||
| 06/06/2025 | Partial Pass | See checklist items for details. I Also looked at 2 single dumpster refuse enclosures footings. Reinforcing is correct, footer dimensions are correct. Compaction tests are also good. Good to pour footings and bollards for refuse enclosures. | ||
| 06/16/2025 | Partial Pass | Okay to grout cells. Every cell below grade grout filled. All verts filled. All grout is to be vibrated. Call us back out to look at bond beams at top of walls before grouting. Also call us back out when refuse enclosure walls are at half built for pre-grout. | ||
| 06/23/2025 | Partial Pass | 6/23/25 East Parking lot wall is built to 8' with continuous #4 bond beam at top. 4" cap block will go on top. Horizontal reinforcement correct. Vertical reinforcement is correct. This section of wall runs from 90* corner at west end of building south to about 30 ft north of man gate corner. This section of wall is ready for grout. -Next section south of wall above is 2 courses high and continues running south to man gate. Bond beam in correct and are verts correct. This will match above wall in height. Good to grout this section -Last section runs east 30 yards from corner/end of east parking lot wall. 4' high. Reinforcing correct. Good to grout this section. Call us back in for pre grout inspection when walls are At 4' or at top of wall at bond beam. Vibrate all grout. |
||
| 06/25/2025 | Partial Pass | Call in refuse enclosure inspection for tomorrow. Reinforcing It is correct okay to grout RE. When screen and retaining walls are finished call them in to close them all out. See checklist items for details. | ||
| 06/26/2025 | Canceled | |||
| 07/08/2025 | Partial Pass | 8’ walls Are under Zoning review as DDO. Wall at risk pending approval of DDO. see checklist for details. | ||
| 07/30/2025 | Partial Pass | 7 /30/25 2' monument wall Footer. Located at west side of entrance on 22nd. #4 verts@ 48" OC alternating bends. 2 #4 cont horz. Spacing and footer dims good. Two verts are supposed to be at wall ends and corner. 1 vert is missing at one end. Contractor will send picture of vert before it is poured. 7/31/25 Picture approved. Okay to pour footer |
||
| 09/08/2025 | Partial Pass | 9/8/25 Footer. Compaction tests good. Footer reinforcement correct. Footer dimensions correct. Okay to pour footer along west side of site. Approximately last 30 ft of N end of this of this wall is not approved to go over 6'. |
||
| 09/16/2025 | Not Ready | |||
| 09/18/2025 | Partial Pass | 9/18/25 18" X 10" pony wall footer for dog park behind building. Two number five continuous bars with number five verts every 48 inches. Verts are placed correctly at the start and end of walls and at expansion joints, ties correct. Compaction good- Okay to pour. Grout all below grade cells and reinforced cells and vibrate grout. |
||
| 09/23/2025 | Partial Pass | 9/23/25 West wall #4 continuous bond beam in place lapped correct at finish grade. Use ladders at 16" oc for horizontal reinforcement. Vibrate all grout. Grout all cells to finish grade. Ok to grout bond beam. Call us back out when done with first lift for another pre grout inspection so we can check horz and vertical lap. Do not build wall past 6' where not approved. Call us back out for Flatwork forms when ready. |
||
| 09/30/2025 | Partial Pass | 9/30/25 Last 75’ of 1st Lift ready for grout. okay to grout. |
||
| 10/02/2025 | Partial Pass | 10/2/25 West wall 2nd lift. From the south at 22nd north to where 8' wall turns to 6'. Bond beam is correct at top of wall with expansion joint sections taped correct. Ok to grout This section then stop at 6' transition. Vibrate all grout. Request pre grout inspection inspection for rest of west wall 2nd lift when ready. |
||
| 12/04/2025 | Passed |