Permit: TD-DEV-1223-00480

Parcel: 126191910


Addresses:

4431 E 22ND ST

Inspection Status: Not Ready

Inspection History: ENGR Paving

Date Description Inspector Results Comments
01/20/2026 ENGR Paving Not Ready Holes in asphalt for cross bracing of Solar Canopy need to be patched.
01/22/2026 ENGR Paving Passed 01/22/26
Contractor pressed in 2 small swales with heat sufficient to remedy puddling at SW section of parking lot. The holes from bracing of the PV canopy columns were patched.
11/07/2025 ENGR Paving Partial Pass 11/7/25
I met with contractor. He wanted to show subgrade elevation was correct in bay at NE end of parking lot. He wanted to move pile of AB into this area. String line between hub and top of curb 12.5" correct. Check rest of Subgrade on Monday.
11/10/2025 ENGR Paving Partial Pass 11/10/25
South parking lot minus the east parking bay (covered with AB) Subgrade good.
Contractor missed a curb cut but it is being fixed now. Also a couple cracked curbs that will need to be repaired. Slopes good. drainage looks correct. This area ready for AB. When paving Asphalt at apron on 22nd will need to be cut back neatly a couple feet.
Subgrade compaction good. Rest of parking lot Subgrade will be looked at Wednesday or later.
11/12/2025 ENGR Paving Partial Pass 11/12/25 subgrade of driveline of North parking area string line from curbs to hubs. Noted some areas that needed to be shaved and others made up with extra ABC with contractor. Send pictures with these areas addressed... Checked subgrade in South parking lot of areas not looked at before with same results. Finish with subgrade. Okay to place ABC pending pictures of fixed areas.
11/14/2025 ENGR Paving Partial Pass 11/14/25
South parking lot Bays and Diveline. Bays at 2.5" depth curbs correct and marked for asphalt thickness. Driveline not 100% with 3" Depth. Winrow needs clean up and a couple areas need to be shaved .5" Compaction reports for this areas not yet ready. Okay to Pave this area pending complying compaction tests of AB and driveline depth issues are fixed that I discussed with contractor. I will be out early Monday to confirm and to inspect North parking area.
11/17/2025 ENGR Paving Partial Pass 11/17/25
Okay to pave south and north parking areas. Drivelines and bays checked for 3" and 2.5". Field density reports are good and slopes drainage are good. Hubs correct and curb reveals good. Final pictures will be sent of a few areas when at 100%...