Parcel: 12512080A


Addresses:

3302 E SPEEDWAY BL


Inspection Status: Partial Pass

Inspection History: For trash and recycling enclosures

Permit Number - TD-DEV-0724-00217

Inspection Description - For trash and recycling enclosures

Inspection Status - Partial Pass

Date Description Inspector Results Comments
04/25/2025 For trash and recycling enclosures Partial Pass Depth, rebar size & placement is good. Ready to pour footing.
04/30/2025 For trash and recycling enclosures Partial Pass Contractors good to pour the grout for the trash enclosure walls
05/06/2025 For trash and recycling enclosures Partial Pass Wall grout is good, bollards are in place. We will need to inspect rebar before slab is poured.
05/09/2025 For trash and recycling enclosures Partial Pass Slab rebar is good, dimensions and slope are good, okay to pour slab.
05/16/2025 For trash and recycling enclosures Partial Pass 5/16/25. Slab and apron poured and correct. Wall is 9 courses on top of footer. 69" above slab.
Gates and 1” retaining pipe in slab not installed yet.
09/26/2025 For trash and recycling enclosures Passed
09/26/2025 For trash and recycling enclosures Passed