Inspection Status: Not Ready
Inspection History: COT - HCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 03/11/2025 |
COT - HCBU - Framing |
|
Not Ready |
Needed interior shear nailing |
| 03/12/2025 |
COT - HCBU - Framing |
|
Partial Pass |
Level Two floor deck. |
| 03/18/2025 |
COT - HCBU - Framing |
|
Not Ready |
wanted Interior shear bracing |
| 03/25/2025 |
COT - HCBU - Framing |
|
Partial Pass |
Level One, corridor shear walls. |
| 03/27/2025 |
COT - HCBU - Framing |
|
Not Ready |
wanted Decking 3rd floor |
| 04/08/2025 |
COT - HCBU - Framing |
|
Not Ready |
wanted shear on level one |
| 05/27/2025 |
COT - HCBU - Framing |
|
Re-inspection required |
Not ready. Fire caulking missing throughout. 5/27/2025 |
| 06/18/2025 |
COT - HCBU - Framing |
|
Partial Pass |
rock wool and fire caulk 2nd floor units 213-224 |
| 07/02/2025 |
COT - HCBU - Framing |
|
Partial Pass |
7-2-25: lath inspection on the north side alcove at 2nd and 3rd floor. Okay to continued with construction at progress areas. |
| 07/09/2025 |
COT - HCBU - Framing |
|
Passed |
|