Inspection Status: Not Ready
Inspection History: COT - HCPL - Plumbing Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 04/30/2024 |
COT - HCPL - Plumbing Above Ceiling |
|
Not Ready |
|
| 06/27/2024 |
COT - HCPL - Plumbing Above Ceiling |
|
Re-inspection required |
6/27/24: copper piping shall not make contact with dissimilar metals (MC cable making contact throughout, Makings contact at top plates throughout), properly support copper piping throughout, DWV not under test, properly support Flex duct throughout, properly support MC cable through (off of grid), ensure that all light fixtures and A/C diffusers are properly supported by seismic wiring. |
| 07/15/2024 |
COT - HCPL - Plumbing Above Ceiling |
|
Passed |
|