Parcel: 11504495A


Addresses:

1001 N PARK AV


Inspection Status: Partial Pass

Inspection History: COT - HCBU - Framing

Permit Number - TC-COM-1222-00337

Inspection Description - COT - HCBU - Framing

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/02/2024 COT - HCBU - Framing Partial Pass Level #2, pour #2 post tension cable system. Ok to place concrete in progress areas.
01/09/2024 COT - HCBU - Framing Partial Pass Post tension cable system at Level #3; Placement #3. Ok to place concrete in progress areas.
01/10/2024 COT - HCBU - Framing Partial Pass Level #3 columns at GL: 1.1/B, 1.1/C, 2.2/B, 2.2/C, 5.1/C, 2/E.2, 1.1/E.2, 3/E. OK to set forms and place concrete in progress areas.
01/11/2024 COT - HCBU - Framing Partial Pass Level #3; columns at GL: G/1.1, G/2, G/3, F/5, F/6, F/7, E/5, D/6, D/7, C/4, C/5, B.6/6, B.7/7. Shear walls at core #1; 3.7 - 3.4/E - F. Ok to set forms and place concrete.
01/16/2024 COT - HCBU - Framing Not Ready Contractor cancelled. Will reschedule.
01/19/2024 COT - HCBU - Framing Partial Pass Post tension cable system on Level #3, Placement #2. Level #2, stairwell landing #1, stairwell landing #2. OK to place concrete in progress areas.
01/22/2024 COT - HCBU - Framing Not Ready Contractor cancelled due to weather.
01/25/2024 COT - HCBU - Framing Partial Pass Level #3 columns at GL; G.8/1.1, G.8/2, H/3, H/4, H/5, H/6, H/7, I/1.4, J/5, J/Y, J/7, J/2. OK to set forms and place concrete in progress areas.
01/26/2024 COT - HCBU - Framing Partial Pass Level #3 columns at GL: L/7, L/6, L/5.3, M/5.3, L/4.1, M/4.1, L/2.8, M/2.8, M/2, M/1.2. OK to set forms and place concrete in progress areas.
01/29/2024 COT - HCBU - Framing Partial Pass Level #3, shear walls at stairwell #2. Ok to place forms and pour concrete in progress areas. Level #4, post tension system at pre pour #1. Ok to place Concrete in progress areas.
01/30/2024 COT - HCBU - Framing Partial Pass Level #4, placement #1, columns at : !B/1.1, C/1.1, B/2.2, C/2.2, C/2.8, B/2.8, C/4, C/5, B.6/7, B.6/6. OK to set forms and place concrete.
01/31/2024 COT - HCBU - Framing Partial Pass Level #4, Placement #1 columns at GL: E.2/1.1, E.2/2, G/1.1, G/3,E/3, E/5.1,F/5.1, G/2.2, F/6, F/7, D/7, D/6. OK to set forms and place concrete in progress areas.
02/05/2024 COT - HCBU - Framing Partial Pass Level #4, Placements #2: post tension cable system inspection. Ok to place concrete in progress areas.
02/06/2024 COT - HCBU - Framing Partial Pass Level #4, placement #2: columns at GL: G.8/1.1, I/1.4, G.8/2, H/3, H/4, H/5.1/. OK to set forms and place concrete.
02/07/2024 COT - HCBU - Framing Partial Pass Level #4, placement #2: columns at GL: J/2, K/1.2, K/2,<L/2.8, M/2.8, M/1.2, M/2, M/4.1, L/4.1, M/5.3, L/6, J/7, J/6, J/5.1, L/5.3. OK to set forms and place concrete in progress areas. Level #4, placement #2; shear walls at stairwell #1, Ok to set forms and place concrete in progress areas.
02/12/2024 COT - HCBU - Framing Partial Pass Level #5, placement #1. Ok to place concrete in progress areas.
02/14/2024 COT - HCBU - Framing Partial Pass Level #5, placement #2 columns at GL: B/1.1, B/2.2, B/2.8, C/1.1, C/2, C/2.8, C/4, C/5.1, B.6/6, B.7/7, D/7, D/6, E/1.1, E.2/2, E/3, E/5, F/5, F/6, F/7, G/1.1, G/2. OK to set forms and place concrete in progress areas. HVAC: Level #1 - level#3, duct system at 24” x 36”from Level #1 to 90 degree elbow.
02/16/2024 COT - HCBU - Framing Partial Pass 2/16/24:PT Level 5 Pour 2 ok to pour, slab at south east corner 1st floor ok to pour. Pending curb.
02/20/2024 COT - HCBU - Framing Partial Pass Level #5, placement #2 columns at GL; G.8/1.1, 2/G.8, I/1.4, J/2, K/2, K/1.2,H/3, H/4, H/5, H/6, H/7, J/7, J/6, J/5. OK to set forms and place concrete in progress areas.
02/21/2024 COT - HCBU - Framing Partial Pass Level #5, Placement #2 columns at GL: M/1.2, M/2, M/2.8, L/2.8, M/4.1, L/4.1, L/5.3, M/5.3, L/6, L/7. OK to set forms and place concrete in progress areas. Stairwell #1, shear walls; OK to set for,s and place concrete in progress areas. Level #1’ Southeast,corner,of,building at GL: H/7 - L, L/7 - 3.7, 14’” curb. Ok to set forms and place concrete in progress areas.
02/26/2024 COT - HCBU - Framing Partial Pass Level #6, placement #2; post tension cable inspection.
02/28/2024 COT - HCBU - Framing Partial Pass Level #6, placement #1 columns at GL: B/1.1, C/1.1,B/2.2, C/2.2, B/2.8, C/2.8, C/5.1, C/4, B.6/6, B.7/7, E/3, G/3, E.2/1.1, E.2/2, F/5, E/5, D/G, D/7, F/7, F/6, G/2, G/1.1. OK to set forms and place concrete in progress areas. Stair well #2 and shear wall #2. Ok to set forms and place concrete in progress areas.
03/01/2024 COT - HCBU - Framing Partial Pass Post tension cable system at L6, placement #2. Ok to place concrete in progress areas.
03/05/2024 COT - HCBU - Framing Partial Pass Level #6, placement #2, columns at GL:G.8/1.1, G.8/2, H/3, H/4, H/5, H/6, H/7, I/1.4, J/7, J/6, L/6/,,L/7, M/5.3, L/5.3, J/5, L/4.1, M/4.1, M/2.I, L/2.8, M/2, M/1.2, K/2, K/1.1, J/2. OK to set forms and place concrete in progress areas. Stairwell #1, shear wall #1. Ok to set forms and place concrete in progress areas.
03/08/2024 COT - HCBU - Framing Canceled Contractor cancelled due to weather.
03/11/2024 COT - HCBU - Framing Partial Pass Level #7, placement #1 post tension cable system. Level #7, placement #1 columns at GL: E.2/1.1, B/1.1, G/2, C/2.2, B/2.2, E.2/2, B/2.8, C/2.8, E/3, G/3, C/4, B6.6/6, D/6, F/6, C/5.1, E/5.1, F/5.1. OK to set forms and place concrete in progress areas. Electric Underground at 2 @ 4” conduits from electric room to transformer #21 (SES, RL, RH). Ok to cover progress areas.
03/13/2024 COT - HCBU - Framing Partial Pass Level #7, placement #1 columns at GL; C/5.1, E/5.1, F/5.1. OK to set forms and place concrete. Stairwell #1 shear walls, Ok to set forms and place concrete in progress areas.
03/15/2024 COT - HCBU - Framing Partial Pass Level #7; placement #2 post tension cable system. Ok to place concrete in progress areas.
03/18/2024 COT - HCBU - Framing Partial Pass Level #7, placement #2 columns a GL: G.8/1.1, G.8/2, I/1.4, H/3, H/4, H/5, H/6, H/7. OK to set forms and place concrete in progress areas.
03/19/2024 COT - HCBU - Framing Partial Pass Level #7, placement #2 columns at GL: J/7, J/6, L/7, L/6, L/5.3, M/5.3, M/4.1, L/4.1, J/5, L/2.8, M/2.8, N/2, M1.2, K/1.2, K/2, J/2. ok to set forms and place concrete in progress areas. Stairwell.shear wall #1; Ok to set forms and place concrete in progress areas.
03/22/2024 COT - HCBU - Framing Partial Pass Level #8, placement #1: post tension cable system. Ok to place concrete in progress areas.
03/25/2024 COT - HCBU - Framing Canceled 2/16/24:PT Level 5 Pour 2 ok to pour, slab at south east corner 1st floor ok to pour. Pending curb.
3/25/24: canceled per Tony
03/26/2024 COT - HCBU - Framing Partial Pass Level #8, placement #2 columns at GL: B/1.1, B/2.2< B/7, C/1.1, C/2.2, C/5, B.7/6, D/5, D/6, D/7. OK to set forms and place concrete in progress areas. Level #8. stairwell #1, shear wall #1; Ok to set forms and place concrete in progress areas.
03/27/2024 COT - HCBU - Framing Partial Pass Level #8, Placement #2: post tension cable system. Level #8, placement #2 columns (24 columns)
03/28/2024 COT - HCBU - Framing Partial Pass Columns on Level #8, Placement #2 at GL: G.8/1.1, G.8/1.2, H/3, H/4, H/5, H/6, H/7, J/7, J/6, J/5, L/7, L/6, L/5.3, M/5.3, M/4.1, L/4.1, L/2.8, M/2.8, M/2, M/1.2, K/1.2, K/2, J/2, I/1.4. OK to set forms and place concrete in progress areas.
04/05/2024 COT - HCBU - Framing Partial Pass Level #9, placement #1: post tension cable system. Ok to place concrete in progress areas.
04/08/2024 COT - HCBU - Framing Partial Pass Shear wall/stairwell #2 on Level #9. Level #9, placement #1; 12 columns. Ok to set forms and place concrete in progress areas.
04/09/2024 COT - HCBU - Framing Partial Pass Information only; fire protection for slip track framing. Ok to utilize product throughout.
04/11/2024 COT - HCBU - Framing Partial Pass Level #9, placement #2 of post tension cable system. Ok to place concrete in progress areas.
04/12/2024 COT - HCBU - Framing Partial Pass Level #9, placement #2: columns H/7, H/6, H/5, H/4, H/3, G.8/2, G/1.1, I/1.4. Ok to set forms and place concrete in progress areas.
04/18/2024 COT - HCBU - Framing Partial Pass Level #10, placement #1: post tension cable system. Ok to place concrete in progress areas.
Level #4, exterior framing and sheathing. Ok to waterproof progress areas.
04/19/2024 COT - HCBU - Framing Partial Pass Level #10, placement #1; columns at GL: B/1.1, C/1.1, B/2.2, C/2.8, B/2.8, C/2.8, C/E, C/5.1, B.6/6, B.7/7. OK to set forms and place concrete in progress areas.
Lefel #3, Elevator shaft #1, fire rated Sheetrock at,2 and 3 hour rating. Ok to Fire caulk progress areas.
04/22/2024 COT - HCBU - Framing Partial Pass Level #10, Placement #2; columns at GL: G/1.1, G/2, G/3, F/5, F/6, F/7, E.2/1.1, E.2/2, E/3, E/5.1, D/6, D/7. OK to set forms and place concrete in progress areas. Level #10, Placement #1 stairwell/elevator shear wall. Ok to set forms and place concrete.
04/24/2024 COT - HCBU - Framing Partial Pass Level #10, Placement #2; Post tension cable system. Ok to place Concrete in progress areas.

Over-hang ceiling at levels #2 - #3. Ok to insulate and cover progress areas.
04/26/2024 COT - HCBU - Framing Partial Pass Level #10, placement #2 columns at GL: J/2, K/2, K/1.2, M/1.2, M/2, L/2.8, M/2.8, M/4.1, L/4.1, L/5.3, M/5.3, L/6, L/7, J/7, J/6, J/5. Ok to set forms and place concrete in progress areas. Stairwell/shear walls #2, Ok to set forms and place concrete in progress areas.
05/06/2024 COT - HCBU - Framing Partial Pass Level #10.5; placement #1 of post tension cable system. Ok to place concrete in progress areas.
05/09/2024 COT - HCBU - Framing Partial Pass Level #10.5, placement #1: concrete wall at 4’ - 6” at South East and East portion of placement #1 - approximately 150’.
05/13/2024 COT - HCBU - Framing Partial Pass Level 10.5, Post tension cable system. Ok to place concrete in progress areas. (last PT inspection for this project).
05/15/2024 COT - HCBU - Framing Partial Pass Level 10.5, Top out slab with compressed styrofoam and #4 rebar. Ok to place concrete in progress areas of Northeast portion of level. North pony wall at 4’ 4” at approximately 110’. Ok to set forms and place concrete in progress areas. South support wall at 8’ x 50’; Ok to place concrete in progress areas.
05/21/2024 COT - HCBU - Framing Partial Pass Level #10.5 pony walls at exterior 4’ rebar at Northwest to Southwest portion of slab; Southwest to Southeast portion of slab area, Pony walls at 8’ Southeast to Northeast to Northwest portion of slab area.
05/29/2024 COT - HCBU - Framing Partial Pass Inspections are for masonry pre-grout at storage/stairwell #1186, CMU walls at 9’9” - 11’ 9”, area K400 at 9’ 9” - 11’ 1 3/4”, Exterior walls at Elevator service/Fire Service area at 8’ (2nd lift). OK to grout progress areas. Level #10.5.

Level #10.5 rebar: pool and spa area walls at 60”; planter areas at North portion of level. Ok to,set forms and place grout in progress,areas.
06/21/2024 COT - HCBU - Framing Partial Pass Level #10.5, townhouse rooms (structural framing). Ensure all clips and hold-downs are properly installed; stairwell #2 and electric room. Positive air supply vent wrapping: levels 3 - 1-.5. Ok to cover progress areas.
07/10/2024 COT - HCBU - Framing Partial Pass Level #10.5, Room units 1133 and 1134.
09/06/2024 COT - HCBU - Framing Canceled Contractor cancelled.
09/20/2024 COT - HCBU - Framing Partial Pass Level #6; Room units: 601, 610 - 617. Level #10.5: pool equipment room.
11/09/2023 COT - HCBU - Framing Partial Pass Level #1, Pour #3 columns at GL: A/U, A/5.4, A/5.9/ A/5.1, D/5.9, E/5, F/5, G/5, F/6, F/7, B.6/7, C/5. OK to set forms and place concrete.
11/13/2023 COT - HCBU - Framing Not Ready Columns are not ready, contractor cancelled.
11/14/2023 COT - HCBU - Framing Partial Pass Columns at GL: G/3.7, G.3/5.9, G.3/7, D/7, B.6/6. OK to set forms and place concrete in progress areas.
11/17/2023 COT - HCBU - Framing Partial Pass Level #1, double matted rebar system at GL: G.8/N, 1/ 7. Placement #4, Ok to place concrete in progress areas.
11/20/2023 COT - HCBU - Framing Partial Pass Level #1 columns at GL: G/8.2, H/4, H/5.1, I/1.4, M/4, M/2.8, L/4, H/2.8. Ok,to set forms and place concrete.
11/27/2023 COT - HCBU - Framing Partial Pass Level #1, mezzanine slab, post tension cable system. Ok to place concrete in progress areas.
11/28/2023 COT - HCBU - Framing Partial Pass Level #1, South stairwell core walls. Columns at GL: J/5, J/6, L/6, M/5.3. OK to set forms and place concrete in progress areas.
11/29/2023 COT - HCBU - Framing Partial Pass Elevator wall at GL: 3 - 4/H, H.6/4. Column at L/5.3. Ok to set forms and place concrete in progress areas.
11/30/2023 COT - HCBU - Framing Partial Pass Columns at GL; B.6/6, B.7/7, D/6, D/7, C/5, E/5, F/6. OK to set forms and place concrete.
12/04/2023 COT - HCBU - Framing Partial Pass Elevator core walls at GL: E - F/3.7 - 4.1, Ok to set forms and place concrete.
12/06/2023 COT - HCBU - Framing Partial Pass Level #1, Post Tension Cable system on slab at GL: G - M/1 - 7. Ok to place concrete in progress areas.
12/13/2023 COT - HCBU - Framing Partial Pass Main entry area, (Y column) at GL: L1 - L2. OK to set forms and place concrete.
12/15/2023 COT - HCBU - Framing Not Ready Contractor cancelled. Will reschedule for18 December
12/18/2023 COT - HCBU - Framing Not Ready Contractor cancelled.
12/18/2024 COT - HCBU - Framing Partial Pass Shear wall Sheetrock nailing in unit 1131.
12/19/2023 COT - HCBU - Framing Partial Pass Post tension cable system at Level #1, placement #2. Ok to place concrete in progress areas.
12/19/2024 COT - HCBU - Framing Partial Pass
12/22/2023 COT - HCBU - Framing Not Ready Contractor cancelled due to weather conditions, will reschedule for 26 December
12/26/2023 COT - HCBU - Framing Partial Pass Level #2. columns at GL: B.6/6, B.7/7, D/6, D/7, F/6, F/7. OK to set forms and place concrete in progress areas.