| 01/26/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Duct works in lower level at GL:D.5/3.7 - 3.8 |
| 03/19/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Stair press duct system #4 at Level #1 (16” x 24”) |
| 04/15/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #9, placement #2: columns at GL: J/2, J/5, J/6, J/7, L/7, L/6, L/5.3, L/2.8, M/5.3, M/4.1, L/4.1, M/2.8, M/1.2, M/2, K/1.2, K/2. OK to set forms and place concrete. Level #9, stairwell #1/shear wall #1. OK to set forms and place concrete in progress areas. Mechanical intermediate for air pressure duct system at Levels 1.5 - level 6. (16” x 24” duct system ) |
| 04/22/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Outside air duct system at Levels #1 - #3; Stair pressure duct system at Levels #1.5 - #6; Trash room exhaust duct system at Levels #1.5 - #3 |
| 05/09/2025 |
COT - HCME - Mechanical Intermediate |
|
Passed |
|
| 06/17/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Room units 100 - 104, 217, 317. Ok to insulate and cover walls. |
| 06/27/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Positive air ventilation shaft at levels #3 and #4; fire dampers in place for each level. |
| 06/28/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Positive air ventilation shaft at Levels #5 - #10, duct system and fire dampers are in place. |
| 07/01/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #2; Room units 202 - 209 |
| 07/02/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #2, Units 201, 210 - 212, 214 - 216. Ok to insulate and cover walls. |
| 08/05/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
In wall mechanical and above ceiling duct systems in room units; 301 - 309. |
| 08/06/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #3; Room units 310 - 317. Ok to insulate and cover walls. |
| 08/07/2024 |
COT - HCME - Mechanical Intermediate |
|
Canceled |
Contractor cancelled. |
| 08/16/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #1; Main,lobby area, study rooms , Elevator lobby area to main entry area (South), |
| 08/20/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #4; room units 402, 403, 406, 407, 408, 409. Ok to insulate and cover walls. |
| 08/22/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #1’ Lobby offices and mailroom corridor. Level #4, room units 401, 410, 412, 413, 414, 415, 416, 417. |
| 08/23/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Room units 404, 406, 414. |
| 08/26/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #4; Room unit #411. |
| 08/29/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #3 at room 310, raise duct work in corridor; below ceiling level. |
| 09/06/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #5; room units 502 - 510 |
| 09/09/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #5; room units #501, 511 - 517 |
| 09/13/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #5 corridor ceilings areas. |
| 09/19/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #6; room units 602 - 609 |
| 09/20/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #6: Room units 601, 610 - 617 |
| 09/26/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Mechanical above ceilings on Level #6. |
| 10/03/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #7; room units 702 - 709 |
| 10/04/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #7; Room units 701, 710 - 717, Level #1, Package room. |
| 10/11/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Elevator lobbies above ceilings at Levels #2 - #7. Level,#1, fitness/spa areas, mechanical rooms; maintenance rooms above ceilings and in walls. |
| 10/14/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level,#1.5 corridor walls below ceiling level. |
| 10/17/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #8, Room units 802 - 810 |
| 10/21/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #8, Room units (in wall) 810, 811, 812, 814. |
| 10/22/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #8; room units 810 - 817, 801. |
| 10/25/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #1.5; restrooms, corridors, storeroom, elevator lobby. Level #1, townhouse #101. |
| 10/31/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #9, Room units 902 - 909. |
| 11/01/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #9; Room units 901 - 917. |
| 11/05/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #9; above ceilings in corridors and elevator lobby. |
| 11/07/2024 |
COT - HCME - Mechanical Intermediate |
|
Not Ready |
Contractor cancelled. |
| 11/13/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #10: Room units; 1002 - 1009. |
| 11/15/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #10; Room units 1010, 1011, 1012, 1015, 1016. |
| 11/19/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level #10, corridors above ceiling. |
| 12/02/2024 |
COT - HCME - Mechanical Intermediate |
|
Not Ready |
Contractor cancelled, will reschedule for 3 December. |
| 12/06/2024 |
COT - HCME - Mechanical Intermediate |
|
Partial Pass |
Level 10.5, room units 1131 - 1134. Ok to insulate and cover walls. |