Parcel: 11504495A


Addresses:

1001 N PARK AV


Inspection Status: Partial Pass

Inspection History: COT - HCBU - Masonry Pregrout 

Permit Number - TC-COM-1222-00337

Inspection Description - COT - HCBU - Masonry Pregrout 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/03/2024 COT - HCBU - Masonry Pregrout  Partial Pass Inspection should read Building progress: Level #2, placement #2; columns at GL: L/4.1, K/2, K/1.2, M/1.2, G/2, I/1.4, J/2, G.8/1.1, M/1.2, A/3, H/4, H/5. OK to set forms and place concrete in progress areas.
01/22/2024 COT - HCBU - Masonry Pregrout  Partial Pass Level #1 CMU walls at first lift: G/1.1 - G/3.7, G/3.7 - H/3.7, G/4 - F/5.5, G/4 - F.5/4, G/3.7 - H/3.7. OK to grout progress areas.
01/25/2024 COT - HCBU - Masonry Pregrout  Not Ready Contractor cancelled, will reschedule for 26 January.
01/26/2024 COT - HCBU - Masonry Pregrout  Partial Pass CMU walls at 4’ - 8’ at GL: G/1.1 - 4, G.8/1.2 - 2.8. CMU walls at 0’ - 4’ at GL: B.7 - E.5/5.1, G.5/5 - 5.5, G - G.8/3.7, E/4 -5, E/4 - 5, C - D.5/5, G.8/2.8 - 1.1. OK to place grout in progress areas.
02/07/2024 COT - HCBU - Masonry Pregrout  Not Ready Contractor cancelled, will reschedule for 8 February.
02/08/2024 COT - HCBU - Masonry Pregrout  Partial Pass CMU walls at parking ramp (South wall topped out - except for opening at East end). Northwest garage area; North and South CMU walls topped out. Ok to grout progress areas.
02/12/2024 COT - HCBU - Masonry Pregrout  Partial Pass Northeast garage area (North wall at 12’ - 16’). Ok to grout progress area; approximately 100 feet.
02/14/2024 COT - HCBU - Masonry Pregrout  Not Ready Contractor cancelled.
03/01/2024 COT - HCBU - Masonry Pregrout  Partial Pass Level #1, CMU walls at GL: 1/A - G at 0’ - 4’; 4’ - 8’. Ok to grout progress areas.
03/05/2024 COT - HCBU - Masonry Pregrout  Partial Pass West garage entry area at 16’, East wall at level #1, 8’ - 12’. Ok to grout progress areas.
03/08/2024 COT - HCBU - Masonry Pregrout  Canceled Contractor cancelled due to weather
03/13/2024 COT - HCBU - Masonry Pregrout  Partial Pass Slab for buck hoist at 12’6’ x 15’ with double rebar mat; #5 bar on bottom at 12” on center and #4 rebar on top mat at 12” on center. Ok to place concrete in progress areas.
03/15/2024 COT - HCBU - Masonry Pregrout  Canceled Contractor cancelled grout inspection.
03/21/2024 COT - HCBU - Masonry Pregrout  Partial Pass Generator room CMU walls (North - South topped out at 22’ - East West at 18’8”). Ok to grout progress areas.
04/05/2024 COT - HCBU - Masonry Pregrout  Partial Pass Level #1.5; Fitness parapet walls - topped out. Ok to grout and place masonry caps in progress area.
Level #1; Electric room CMU walls at 4’ - 8’. Transformer area, CMU walls at 0’,- 4’. Ok to grout progress areas.
04/26/2024 COT - HCBU - Masonry Pregrout  Partial Pass Exterior walls at Southwest corner of building at 8’ - 12’ of colored CMU. OK to grout progress areas.
06/06/2024 COT - HCBU - Masonry Pregrout  Partial Pass Level #10.5, Elevator lobby area: CMU walls at 21’ 4”. OK to place grout in progress . Elevator shaft sheathing on Level #7; separation walls for electric room at elevator shafts #7 and #8.
12/06/2024 COT - HCBU - Masonry Pregrout  Passed