Inspection Status: Partial Pass
Inspection History: COT - HCME - Mechanical Final
| Date |
Description |
Inspector |
Results |
Comments |
| 03/05/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Information only for future unit inspections. |
| 03/17/2025 |
COT - HCME - Mechanical Final |
|
Canceled |
Contractor cancelled. |
| 03/24/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level #2, room checks: Rooms 201 - 217 |
| 03/25/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level #3, room units: 301 - 317 |
| 03/26/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level #4, Room units 401 - 417 |
| 03/27/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level #5; Room units 501 - 517. |
| 04/01/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level #1; Town houses 101 - 104. Level #6 completed. |
| 04/14/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level #7, Room units 702 - 717. |
| 04/15/2025 |
COT - HCME - Mechanical Final |
|
Canceled |
Contractor cancelled. |
| 04/21/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level #7, Room units: 701, 702, 703, 711, 713. Level #8, Room units 801 - 817. |
| 04/22/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level #9, Room units 901 - 917. |
| 04/30/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level #9; Room units 901 - 917. |
| 05/01/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level #10: Room units 1001 - 1009. |
| 05/02/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level #10, Room units 1009 - 1016 |
| 05/05/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level #11; Room units 1131, 1132, 1133, 1134. Corridors #8, 9, 10: IDF Rooms, Electric rooms, janitor closets, trash rooms. |
| 05/06/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Level 10.5, pool/amenities areas, restrooms and storage areas. NOTE: grilling area is not complete. |
| 05/07/2025 |
COT - HCME - Mechanical Final |
|
Partial Pass |
Garage levels #1 & #2 |
| 05/08/2025 |
COT - HCME - Mechanical Final |
|
Passed |
|