| 04/08/2026 |
COT - HCBU - Framing |
|
Re-inspection required |
4-8-26: have architect submit a letter clarifying whether stud spacing at 16"o.c. is acceptable. Per stud spacing schedule, walls 15'8" to 16'-11" require 18gage studs at 1' o.c...add kickers at 4' o.c. where required. |
| 04/10/2026 |
COT - HCBU - Framing |
|
Partial Pass |
4-10-26: a revision has been submitted to the city for review but is still pending approval. Verified Framing per revision-okay to continue with insulation at own risk. |
| 04/16/2026 |
COT - HCBU - Framing |
|
Partial Pass |
4-16-26: provide 5/8" drywall/fire tape at firewalls located at storage room and at office. Install screws at 7" o.c. throughout. Drywall screw inspection for progress areas approved. Okay to tape & texture those areas but schedule an inspection for remainder locations to include, restrooms/ceilings. |
| 04/21/2026 |
COT - HCBU - Framing |
|
Partial Pass |
4/21/2026 dry wall screw inspection approved at remaining locations. Okay to proceed progress areas. |
| 05/11/2026 |
COT - HCBU - Framing |
|
Passed |
5-11-26: framing approved. |