Inspection Status: Not Ready

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Date Description Inspector Results Comments
02/04/2026 COT - HCBU - Excavation/Rebar/Zoning  Not Ready
03/09/2026 COT - HCBU - Excavation/Rebar/Zoning  Passed
06/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Building #3. Partial pass. PERIMETER FOOTINGS. GRID LINE 1 ABOUT 5 ´ FROM GRID LINE A-D. ALL OF GRID LINE D. GRID LINE 6 AND 7. Okay for concrete placement. 6/20/2024
11/13/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Admin building. Line A/1-7 footings. Reinforcement per plan. Okay for concrete placement. 11/13/2024