Inspection Status: Not Ready
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 02/04/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Not Ready |
|
| 03/09/2026 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Passed |
|
| 06/20/2024 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Building #3. Partial pass. PERIMETER FOOTINGS. GRID LINE 1 ABOUT 5 ´ FROM GRID LINE A-D. ALL OF GRID LINE D. GRID LINE 6 AND 7. Okay for concrete placement. 6/20/2024 |
| 11/13/2024 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Admin building. Line A/1-7 footings. Reinforcement per plan. Okay for concrete placement. 11/13/2024 |