Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - CofO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/19/2025 | COT - HCBU - CofO | Partial Pass | 5/6/25: Insulation at roof top equipment must be UV wrapped, All exterior plastic piping must be UV coated, water heater hot lines must be coated, Copper to galvanized pipe shall be made code compliance, Receptacle at HVAC units not functioning, PENDING CONDITIONS AND PTHER INSPECTIONS. 5/19/24: OKAY FOR LEVEL 4 TCO. PENDING CONDITIONS |
|
| 06/26/2025 | COT - HCBU - CofO | Passed |