Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Progress
Permit Number - TC-COM-0523-01382
Inspection Description - COT - HCEL - Electrical Progress
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/15/2024 | COT - HCEL - Electrical Progress | Partial Pass | 8/15/24: south and east corner for rototron room okay to pour concrete around conduit in wall. | |
08/26/2024 | COT - HCEL - Electrical Progress | Partial Pass | 8/26/24: south and west mezzanine treatment cell exterior walls okay to pour concrete | |
10/01/2024 | COT - HCEL - Electrical Progress | Partial Pass | 10/1/24: underground electric for truck EV charging station and cameras for light poles north east corner parking lot trenches okay to backfill | |
10/02/2024 | COT - HCEL - Electrical Progress | Partial Pass | 10/2/24: underground electric for truck EV charging station and cameras for light poles in northwest corner of parking lot is trenched and conduit in place. okay to backfill | |
10/14/2024 | COT - HCEL - Electrical Progress | Partial Pass | X1 1"schedule 40 at 24” depth stubbed up for exterior lighting. All on west end of building. Okay to backfill progress areas. Shading required. 10/14/2024 | |
10/31/2024 | COT - HCEL - Electrical Progress | Partial Pass | 8/15/24: south and east corner for rototron room okay to pour concrete around conduit in wall. 8/26/24: south and west mezzanine treatment cell exterior walls okay to pour concrete 10/1/24: underground electric for truck EV charging station and cameras for light poles north east corner parking lot trenches okay to backfill 10/2/24: underground electric for truck EV charging station and cameras for light poles in northwest corner of parking lot is trenched and conduit in place. okay to backfill X1 1"schedule 40 at 24” depth stubbed up for exterior lighting. All on west end of building. Okay to backfill progress areas. Shading required. 10/14/2024 10/31/24: electrical underground at south east side of property for light pole bases and security per plan ok to proceed. |
|
11/13/2024 | COT - HCEL - Electrical Progress | Passed | 11-13-24, rebar verified as per approved plans for 2 footers together with rebar for slab both located in north area of warehouse. Also, inspected rebar for fire pump house, sign near entrance, and 8 light posts. All approved-okay to pour concrete. |