Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Parcel: 14106020D


Addresses:

7345 E VALENCIA RD


Inspection Status: Not Ready

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-0523-01382

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Not Ready

Date Description Inspector Results Comments
01/03/2024 COT - HCBU - Excavation/Rebar/Zoning  Not Ready 1/3/24: not needed at this time
01/04/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass E1-E8 E to D on 1 and E to D on 8
01/05/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass /5/24: A.6 and 5 not ready all other interior spread footings okay to pour concrete
Gridline A, 5.5 and 5 spread footings okay to pour
01/12/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/12/24: E line 2.5 to 5.4
01/16/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/16/24 Line A1 THROUGH gridline 4 okay to pour for anchor bolts and grade beam
Footings on line A/4.5, 6. A.6 LOCATION 5
Gridline 8 footing location D, C.5, AND C.3 OKAY TO POUR
12 OF REBAR PIERS 36INCH DIAMETER
3 48 INCH DIAMETER PIERS OKAY TO PLACE
01/17/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/17/24: gridline 1 A-D okay to place concrete for anchor bolts and rebar cage
01/19/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/19/24: gridline A /4.5 TO 6 ANCHOR BOLTS
6.5 GRIDLINE E COLUM
GRIDLINE E 1 AND 1.5 ANCHOR BOLT
GRIDLINE 1 TO D.6 8 FT PASS COLUM
GRIDLUNE E 2.5 COLUM
GRIDLINE 8 FROM C.3 TO D ANCHORBOLTS OKAY TO PLACE CONCRETE
01/30/2024 COT - HCBU - Excavation/Rebar/Zoning  Not Ready
01/31/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/31/24: Gridline 1 D.6 AND D
GRIDLINE A from 4.5 to 6
Gridline D.6 TO C AND GRIDLINE 8 okay to place concrete
02/01/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/1/24: gridline 4.5 between a.6 and c.5 slab trench okay to place concrete
02/06/2024 COT - HCBU - Excavation/Rebar/Zoning  Re-inspection required 2/6/24: top of footing for piers need to be cleared of all dirt exposing concrete before pour. Reinspection required.
02/09/2024 COT - HCBU - Excavation/Rebar/Zoning  Not Ready 2/9/24: not ready
02/13/2024 COT - HCBU - Excavation/Rebar/Zoning  Not Ready 2/13/24: not ready.
02/14/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/14/24: duct and treatment area. T trench
02/21/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/21/24: treatment cell room DUCT TRENCH okay to pour up to 2'4 mark. Loading docks at gridline E 1.5 TO 2.5 AND 5 TO 6.5
03/04/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/4/24: dock e line 1.5 to 2.5 okay to place concrete for dock pit floor
03/05/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/5/24: t trench okay to pour concrete rebar to schedule
03/07/2024 COT - HCBU - Excavation/Rebar/Zoning  Re-inspection required 12/18/23: line E- 3.7 through 8 okay to place concrete
12/20/23: D.6 TO E line south footing. E-3 to E-1. E-1 D.6
E-1 to A/1 north side of building footers
A-1 to A-4 west side of building
E1-E8 E to D on 1 and E to D on 8
1/3/24: not needed at this time

1/5/24: A.6 and 5 not ready all other interior spread footings okay to pour concrete
Gridline A, 5.5 and 5 spread footings okay to pour
1/12/24: E line 2.5 to 5.4

1/16/24 Line A1 THROUGH gridline 4 okay to pour for anchor bolts and grade beam
Footings on line A/4.5, 6. A.6 LOCATION 5
Gridline 8 footing location D, C.5, AND C.3 OKAY TO POUR
12 OF REBAR PIERS 36INCH DIAMETER
3 48 INCH DIAMETER PIERS OKAY TO PLACE
1/17/24: gridline 1 A-D okay to place concrete for anchor bolts and rebar cage
1/19/24: gridline A /4.5 TO 6 ANCHOR BOLTS
6.5 GRIDLINE E COLUM
GRIDLINE E 1 AND 1.5 ANCHOR BOLT
GRIDLINE 1 TO D.6 8 FT PASS COLUM
GRIDLUNE E 2.5 COLUM
GRIDLINE 8 FROM C.3 TO D ANCHORBOLTS OKAY TO PLACE CONCRETE

1/31/24: Gridline 1 D.6 AND D
GRIDLINE A from 4.5 to 6
Gridline D.6 TO C AND GRIDLINE 8 okay to place concrete.
2/1/24: gridline 4.5 between a.6 and c.5 slab trench okay to place concrete
2/6/24: top of footing for piers need to be cleared of all dirt exposing concrete before pour. Reinspection required.
2/9/24: not ready
2/13/24: not ready.
2/14/24: duct and treatment area. T trench
2/21/24: treatment cell room DUCT TRENCH okay to pour up to 2'4 mark. Loading docks at gridline E 1.5 TO 2.5 AND 5 TO 6.5
3/4/24: dock e line 1.5 to 2.5 okay to place concrete for dock pit floor
3/5/24: t trench okay to pour concrete rebar to schedule
3/7/24: not ready
03/12/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/11/24: Dock pits north east of facility reinforcement per plan. Ok to proceed.
03/12/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/12/24: slab on grade pour 1 north end of warehouse section and docks to east.
03/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/11/24: Dock pits north east of facility reinforcement per plan. Ok to proceed.
3/18/24: slab on grade pour 2 ok to pour.
03/19/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/19/24: treatment cell verticals first floor ok to pour slab.
03/21/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/21/24: gridline E from 5 to 6.5 okay to pour concrete for dock floors (4)
03/22/2024 COT - HCBU - Excavation/Rebar/Zoning  Canceled 3/22/24: canceled per contractor
03/25/2024 COT - HCBU - Excavation/Rebar/Zoning  Canceled 3/25/24: canceled per contractor
03/27/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/27/24: slab on grade pour 3 ok to place concrete
04/03/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/3/24: West side treatment cell level 1 rebar is in place, cleaned, and properly tied off. Okay to install opposite side of forms and button up wall for concrete pour.
04/09/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/9/24: b line from grindline 6 to 8 and gridline 6.5 between A.2 to b.7 treatment cell walls
04/24/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/24/24: partial for the riser area floor north east corner of building
04/24/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/24/24: partial for the riser area floor north east corner of building
05/03/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/3/24: level one east wall treatment cell okay to place concrete.
05/16/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/15/24: level one treatment center partition wall
06/07/2024 COT - HCBU - Excavation/Rebar/Zoning  Not Ready 6/7/24: not ready
06/13/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 6/13/24: mezzanine lower rebar mat to schedule
07/25/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 7/25/24: treatment cell mezzanine rebar to schedule okay to pour concrete
08/13/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 8/13/24: rototron room and treatment cell walls above mezzanine gridline 8 from c.5 to B
Gridline c.5 from 7 to 8
08/26/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 8/26/24: south and west mezzanine treatment cell exterior walls okay to pour concrete
09/06/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 9/5/24: mezzanine rotor room west and north walls okay to place concrete.
09/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 9/18/2024 rebar per plan for the Treatment Cell hallway ceiling both east and west ends. Okay for concrete placement.
09/19/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 9/19/2024 octagonal mat foundation and anchor bolts detail. For water tank and water suppression system. Okay for concrete placement.
09/23/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Upper rhodotron room. West end and east end walls. Okay for concrete placement. 9/23/2024
10/02/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10/2/24: 2nd deck of rhodotron room rebar is in place. Okay for concrete pour.
10/04/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/11/24: Dock pits north east of facility reinforcement per plan. Ok to proceed.
3/18/24: slab on grade pour 2 ok to pour.
3/22/24: canceled per contractor
3/25/24: canceled per contractor
3/27/24: slab on grade pour 3 ok to place concrete
4/3/24: West side treatment cell level 1 rebar is in place, cleaned, and properly tied off. Okay to install opposite side of forms and button up wall for concrete pour.
4/9/24: b line from grindline 6 to 8 and gridline 6.5 between A.2 to b.7 treatment cell walls.
4/24/24: partial for the riser area floor north east corner of building
5/3/24: level one east wall treatment cell okay to place concrete.
5/15/24: level one treatment center partition wall
6/7/24: not ready
6/13/24: mezzanine lower rebar mat to schedule
7/25/24: treatment cell mezzanine rebar to schedule okay to pour concrete
9/5/24: mezzanine rotor room west and north walls okay to place concrete.

9/18/2024 rebar per plan for the Treatment Cell hallway ceiling both east and west ends. Okay for concrete placement.

Upper rhodotron room. West end and east end walls. Okay for concrete placement. 9/23/2024

10/2/24: 2nd deck of rhodotron room rebar is in place. Okay for concrete pour.
10/4/24: roof final rebar inspection on the treatment cell roof. Ok for concrete placement
10/22/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10/22/2024 partial pass. Total of 4 light pole bases approved. East end of building. Rebar and depth per plan. Okay for concrete placement.
11/05/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/18/23: line E- 3.7 through 8 okay to place concrete
12/20/23: D.6 TO E line south footing. E-3 to E-1. E-1 D.6
E-1 to A/1 north side of building footers
A-1 to A-4 west side of building
E1-E8 E to D on 1 and E to D on 8
1/3/24: not needed at this time

1/5/24: A.6 and 5 not ready all other interior spread footings okay to pour concrete
Gridline A, 5.5 and 5 spread footings okay to pour
1/12/24: E line 2.5 to 5.4

1/16/24 Line A1 THROUGH gridline 4 okay to pour for anchor bolts and grade beam
Footings on line A/4.5, 6. A.6 LOCATION 5
Gridline 8 footing location D, C.5, AND C.3 OKAY TO POUR
12 OF REBAR PIERS 36INCH DIAMETER
3 48 INCH DIAMETER PIERS OKAY TO PLACE
1/17/24: gridline 1 A-D okay to place concrete for anchor bolts and rebar cage
1/19/24: gridline A /4.5 TO 6 ANCHOR BOLTS
6.5 GRIDLINE E COLUM
GRIDLINE E 1 AND 1.5 ANCHOR BOLT
GRIDLINE 1 TO D.6 8 FT PASS COLUM
GRIDLUNE E 2.5 COLUM
GRIDLINE 8 FROM C.3 TO D ANCHORBOLTS OKAY TO PLACE CONCRETE

1/31/24: Gridline 1 D.6 AND D
GRIDLINE A from 4.5 to 6
Gridline D.6 TO C AND GRIDLINE 8 okay to place concrete.
11/05/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/1/24: gridline 4.5 between a.6 and c.5 slab trench okay to place concrete
2/6/24: top of footing for piers need to be cleared of all dirt exposing concrete before pour. Reinspection required.
2/9/24: not ready
2/13/24: not ready.
2/14/24: duct and treatment area. T trench
2/21/24: treatment cell room DUCT TRENCH okay to pour up to 2'4 mark. Loading docks at gridline E 1.5 TO 2.5 AND 5 TO 6.5
3/4/24: dock e line 1.5 to 2.5 okay to place concrete for dock pit floor
3/5/24: t trench okay to pour concrete rebar to schedule
3/7/24: not ready
3/12/24: slab on grade pour 1 north end of warehouse section and docks to east.
3/19/24: treatment cell verticals first floor ok to pour slab.
3/21/24: gridline E from 5 to 6.5 okay to pour concrete for dock floors (4)
4/24/24: partial for the riser area floor north east corner of building
8/13/24: rototron room and treatment cell walls above mezzanine gridline 8 from c.5 to B
Gridline c.5 from 7 to 8

8/26/24: south and west mezzanine treatment cell exterior walls okay to pour concrete

9/19/2024 octagonal mat foundation and anchor bolts detail. For water tank and water suppression system. Okay for concrete placement.
11/5/24: electrical underground for East side guard shack ok to backfill. 3 light pole bases around north and east side of property.
11/13/2024 COT - HCBU - Excavation/Rebar/Zoning  Passed 11-13-24, rebar verified as per approved plans for 2 footers together with rebar for slab both located in north area of warehouse. Also, inspected rebar for fire pump house, sign near entrance, and 8 light posts. All approved-okay to pour concrete.
11/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Passed 11/20/24: Total of 8 light pole bases are properly bored, rebar reinforcement cages are in place, #4 bare wire is coiled in bottom of footing and connected to the rebar cage and extending 16" above base top, sonotube forms are set and properly supported, and electrical conduit is ran to each pole bases. Okay to pour concrete
11/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Passed 11/20/24: Total of 8 light pole bases are properly bored, rebar reinforcement cages are in place, #4 bare wire is coiled in bottom of footing and connected to the rebar cage and extending 16" above base top, sonotube forms are set and properly supported, and electrical conduit is ran to each pole bases. Okay to pour concrete
12/18/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/18/23: line E- 3.7 through 8 okay to place concrete
12/20/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass