Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Parcel: 14106020D


Addresses:

7345 E VALENCIA RD


Inspection Status: Not Ready

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-0523-01382

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Not Ready

Date Description Inspector Results Comments
01/03/2024 COT - HCBU - Excavation/Rebar/Zoning  Not Ready 1/3/24: not needed at this time
01/04/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass E1-E8 E to D on 1 and E to D on 8
01/05/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass /5/24: A.6 and 5 not ready all other interior spread footings okay to pour concrete
Gridline A, 5.5 and 5 spread footings okay to pour
01/12/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/12/24: E line 2.5 to 5.4
01/16/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/16/24 Line A1 THROUGH gridline 4 okay to pour for anchor bolts and grade beam
Footings on line A/4.5, 6. A.6 LOCATION 5
Gridline 8 footing location D, C.5, AND C.3 OKAY TO POUR
12 OF REBAR PIERS 36INCH DIAMETER
3 48 INCH DIAMETER PIERS OKAY TO PLACE
01/17/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/17/24: gridline 1 A-D okay to place concrete for anchor bolts and rebar cage
01/19/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/19/24: gridline A /4.5 TO 6 ANCHOR BOLTS
6.5 GRIDLINE E COLUM
GRIDLINE E 1 AND 1.5 ANCHOR BOLT
GRIDLINE 1 TO D.6 8 FT PASS COLUM
GRIDLUNE E 2.5 COLUM
GRIDLINE 8 FROM C.3 TO D ANCHORBOLTS OKAY TO PLACE CONCRETE
01/30/2024 COT - HCBU - Excavation/Rebar/Zoning  Not Ready
01/31/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1/31/24: Gridline 1 D.6 AND D
GRIDLINE A from 4.5 to 6
Gridline D.6 TO C AND GRIDLINE 8 okay to place concrete
02/01/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/1/24: gridline 4.5 between a.6 and c.5 slab trench okay to place concrete
02/06/2024 COT - HCBU - Excavation/Rebar/Zoning  Re-inspection required 2/6/24: top of footing for piers need to be cleared of all dirt exposing concrete before pour. Reinspection required.
02/09/2024 COT - HCBU - Excavation/Rebar/Zoning  Not Ready 2/9/24: not ready
02/13/2024 COT - HCBU - Excavation/Rebar/Zoning  Not Ready 2/13/24: not ready.
02/14/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/14/24: duct and treatment area. T trench
02/21/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2/21/24: treatment cell room DUCT TRENCH okay to pour up to 2'4 mark. Loading docks at gridline E 1.5 TO 2.5 AND 5 TO 6.5
03/04/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/4/24: dock e line 1.5 to 2.5 okay to place concrete for dock pit floor
03/05/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/5/24: t trench okay to pour concrete rebar to schedule
03/07/2024 COT - HCBU - Excavation/Rebar/Zoning  Re-inspection required 12/18/23: line E- 3.7 through 8 okay to place concrete
12/20/23: D.6 TO E line south footing. E-3 to E-1. E-1 D.6
E-1 to A/1 north side of building footers
A-1 to A-4 west side of building
E1-E8 E to D on 1 and E to D on 8
1/3/24: not needed at this time

1/5/24: A.6 and 5 not ready all other interior spread footings okay to pour concrete
Gridline A, 5.5 and 5 spread footings okay to pour
1/12/24: E line 2.5 to 5.4

1/16/24 Line A1 THROUGH gridline 4 okay to pour for anchor bolts and grade beam
Footings on line A/4.5, 6. A.6 LOCATION 5
Gridline 8 footing location D, C.5, AND C.3 OKAY TO POUR
12 OF REBAR PIERS 36INCH DIAMETER
3 48 INCH DIAMETER PIERS OKAY TO PLACE
1/17/24: gridline 1 A-D okay to place concrete for anchor bolts and rebar cage
1/19/24: gridline A /4.5 TO 6 ANCHOR BOLTS
6.5 GRIDLINE E COLUM
GRIDLINE E 1 AND 1.5 ANCHOR BOLT
GRIDLINE 1 TO D.6 8 FT PASS COLUM
GRIDLUNE E 2.5 COLUM
GRIDLINE 8 FROM C.3 TO D ANCHORBOLTS OKAY TO PLACE CONCRETE

1/31/24: Gridline 1 D.6 AND D
GRIDLINE A from 4.5 to 6
Gridline D.6 TO C AND GRIDLINE 8 okay to place concrete.
2/1/24: gridline 4.5 between a.6 and c.5 slab trench okay to place concrete
2/6/24: top of footing for piers need to be cleared of all dirt exposing concrete before pour. Reinspection required.
2/9/24: not ready
2/13/24: not ready.
2/14/24: duct and treatment area. T trench
2/21/24: treatment cell room DUCT TRENCH okay to pour up to 2'4 mark. Loading docks at gridline E 1.5 TO 2.5 AND 5 TO 6.5
3/4/24: dock e line 1.5 to 2.5 okay to place concrete for dock pit floor
3/5/24: t trench okay to pour concrete rebar to schedule
3/7/24: not ready
03/12/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/11/24: Dock pits north east of facility reinforcement per plan. Ok to proceed.
03/12/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/12/24: slab on grade pour 1 north end of warehouse section and docks to east.
03/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/11/24: Dock pits north east of facility reinforcement per plan. Ok to proceed.
3/18/24: slab on grade pour 2 ok to pour.
03/19/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/19/24: treatment cell verticals first floor ok to pour slab.
03/21/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/21/24: gridline E from 5 to 6.5 okay to pour concrete for dock floors (4)
03/22/2024 COT - HCBU - Excavation/Rebar/Zoning  Canceled 3/22/24: canceled per contractor
03/25/2024 COT - HCBU - Excavation/Rebar/Zoning  Canceled 3/25/24: canceled per contractor
03/27/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3/27/24: slab on grade pour 3 ok to place concrete
04/03/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/3/24: West side treatment cell level 1 rebar is in place, cleaned, and properly tied off. Okay to install opposite side of forms and button up wall for concrete pour.
04/09/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/9/24: b line from grindline 6 to 8 and gridline 6.5 between A.2 to b.7 treatment cell walls
04/24/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/24/24: partial for the riser area floor north east corner of building
04/24/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4/24/24: partial for the riser area floor north east corner of building
05/03/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/3/24: level one east wall treatment cell okay to place concrete.
05/16/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5/15/24: level one treatment center partition wall
06/07/2024 COT - HCBU - Excavation/Rebar/Zoning  Not Ready 6/7/24: not ready
06/13/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 6/13/24: mezzanine lower rebar mat to schedule
07/25/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 7/25/24: treatment cell mezzanine rebar to schedule okay to pour concrete
08/13/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 8/13/24: rototron room and treatment cell walls above mezzanine gridline 8 from c.5 to B
Gridline c.5 from 7 to 8
08/26/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 8/26/24: south and west mezzanine treatment cell exterior walls okay to pour concrete
09/06/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 9/5/24: mezzanine rotor room west and north walls okay to place concrete.
09/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 9/18/2024 rebar per plan for the Treatment Cell hallway ceiling both east and west ends. Okay for concrete placement.
09/19/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 9/19/2024 octagonal mat foundation and anchor bolts detail. For water tank and water suppression system. Okay for concrete placement.
12/18/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/18/23: line E- 3.7 through 8 okay to place concrete
12/20/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass