Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Parcel: 14106020D


Addresses:

7345 E VALENCIA RD


Inspection Status: Not Ready

Inspection History: COT - HCME - Mechanical Intermediate

Permit Number - TC-COM-0523-01382

Inspection Description - COT - HCME - Mechanical Intermediate

Inspection Status - Not Ready

Date Description Inspector Results Comments
01/15/2025 COT - HCME - Mechanical Intermediate Not Ready 5/15/24: mechanical piping in between treatment cell portion walls okay to cover

RTU 1 office area main runs. 106, 109, 107, 105, 104, 103, 102, 101, 125, 124. Pending room 108, 115, and 116. Okay to proceed progress areas. 8/20/2024

12/30/24: 4", 3" 1.5" & 1" blue compressed air lines are properly installed and under an air test of 100psi. Okay to proceed.
1/15/25: not ready
04/15/2025 COT - HCME - Mechanical Intermediate Partial Pass 5/15/24: mechanical piping in between treatment cell portion walls okay to cover

RTU 1 office area main runs. 106, 109, 107, 105, 104, 103, 102, 101, 125, 124. Pending room 108, 115, and 116. Okay to proceed progress areas. 8/20/2024

12/30/24: 4", 3" 1.5" & 1" blue compressed air lines are properly installed and under an air test of 100psi. Okay to proceed.
1/15/25: not ready
4/15/25: Hydronic piping under 105psi test ok to proceed. South end of building
04/23/2025 COT - HCME - Mechanical Intermediate Partial Pass 4-23-25, chilled water system on north side of tested under pressure at 100 psi.. Contractor will schedule an inspection once remaining system is installed.
05/02/2025 COT - HCME - Mechanical Intermediate Partial Pass 5/15/24: mechanical piping in between treatment cell portion walls okay to cover

RTU 1 office area main runs. 106, 109, 107, 105, 104, 103, 102, 101, 125, 124. Pending room 108, 115, and 116. Okay to proceed progress areas. 8/20/2024

12/30/24: 4", 3" 1.5" & 1" blue compressed air lines are properly installed and under an air test of 100psi. Okay to proceed.
1/15/25: not ready
4/15/25: Hydronic piping under 105psi test ok to proceed. South end of building
4-23-25, chilled water system on north side of tested under pressure at 100 psi.. Contractor will schedule an inspection once remaining system is installed.
5/2/25: Compressed air with cooling system approved ok to proceed.
05/06/2025 COT - HCME - Mechanical Intermediate Passed
05/16/2024 COT - HCME - Mechanical Intermediate Partial Pass 5/15/24: mechanical piping in between treatment cell portion walls okay to cover
08/20/2024 COT - HCME - Mechanical Intermediate Partial Pass RTU 1 office area main runs. 106, 109, 107, 105, 104, 103, 102, 101, 125, 124. Pending room 108, 115, and 116. Okay to proceed progress areas. 8/20/2024
12/30/2024 COT - HCME - Mechanical Intermediate Partial Pass 12/30/24: 4", 3" 1.5" & 1" blue compressed air lines are properly installed and under an air test of 100psi. Okay to proceed.